Hazardous waste · violations by year
Hazardous waste violations in Texas in 2017
- 147Handlers cited
- 660Violations on record
- 1stAmong Texas counties that year
Texas has 147 hazardous waste handlers with at least one violation on record during 2017, across 660 separate violations. Each row below carries the date the violation was recorded, the agency that recorded it and the kind of violation it was.
Other years
Violations recorded in 2017
| Date | Handler | Where | Kind | Recorded by |
|---|---|---|---|---|
| 2017-05-04 | CONSOLIDATED CASTING HUTCHINS | Hutchins | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-04 | CONSOLIDATED CASTING HUTCHINS | Hutchins | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-05-04 | CONSOLIDATED CASTING HUTCHINS | Hutchins | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-04 | CONSOLIDATED CASTING HUTCHINS | Hutchins | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-03 | TEXANA TANK CAR & MANUFACTURING | Nash | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-03 | TEXANA TANK CAR & MANUFACTURING | Nash | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-03 | ARKEMA BEAUMONT PLANT | Beaumont | Interim Status Standards for Owners and Operators of HW TSDs: General Facility Standards | S |
| 2017-05-03 | ARKEMA BEAUMONT PLANT | Beaumont | Standards Applicable to Generators of HW: General | S |
| 2017-05-03 | ARKEMA BEAUMONT PLANT | Beaumont | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-05-01 | JEWELL HUDGENS MACHINE | Lufkin | Standards for Used Oil: Generators | S |
| 2017-05-01 | JEWELL HUDGENS MACHINE | Lufkin | Standards Applicable to Generators of HW: General | S |
| 2017-05-01 | JEWELL HUDGENS MACHINE | Lufkin | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | Standards for Universal Waste Management: Standards for Small Quantity Handlers | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | Standards for Universal Waste Management: Standards for Small Quantity Handlers | S |
| 2017-04-27 | DELEK REFINING TYLER REFINERY | Tyler | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | Standards Applicable to Generators of HW: General | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | Land Disposal Restrictions: General | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | Standards Applicable to Generators of HW: Manifest Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-04-27 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | HUE THI NGOC NGUYEN DBA INWOOD 1.49 CLEANERS | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | HUE THI NGOC NGUYEN DBA INWOOD 1.49 CLEANERS | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-27 | HUE THI NGOC NGUYEN DBA INWOOD 1.49 CLEANERS | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-25 | EQUISTAR CHEMICALS CHANNELVIEW COMPLEX | Channelview | ID and Listing of HW: Criteria for Identifying the Characteristics of HW and for Listing HW | E |
| 2017-04-25 | EQUISTAR CHEMICALS CHANNELVIEW COMPLEX | Channelview | Standards for Owners and Operators of HW TSDs: Preparedness and Prevention | E |
| 2017-04-25 | EQUISTAR CHEMICALS CHANNELVIEW COMPLEX | Channelview | Standards for Owners and Operators of HW TSDs: Manifest System, Recordkeeping and Reporting | E |
| 2017-04-25 | EQUISTAR CHEMICALS CHANNELVIEW COMPLEX | Channelview | Land Disposal Restrictions: Prohibitions on Storage | E |
| 2017-04-24 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-20 | PERFORMANCE CONTRACTING | Pasadena | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-04-20 | PERFORMANCE CONTRACTING | Pasadena | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-04-12 | EXXONMOBIL BEAUMONT REFINERY | Beaumont | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-12 | PINE DUNES GOLF AND RESORT CLUB | Frankston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-12 | PINE DUNES GOLF AND RESORT CLUB | Frankston | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-12 | PINE DUNES GOLF AND RESORT CLUB | Frankston | Standards for Used Oil: Generators | S |
| 2017-04-12 | PINE DUNES GOLF AND RESORT CLUB | Frankston | ID and Listing of HW: General | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Standards Applicable to Generators of HW: General | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Interim Status Standards for Owners and Operators of HW TSDs: General Facility Standards | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | Standards Applicable to Generators of HW: Manifest Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-10 | HIGH TECH FINISHING | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-10 | QUALA HOLDINGS | Saginaw | Standards Applicable to Generators of HW: General | E |
| 2017-04-10 | QUALA HOLDINGS | Saginaw | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | E |
| 2017-04-10 | RAYBURN ENERGY STATION | Sherman | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-04-07 | COMET ONE-HOUR CLEANERS | Lubbock | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-07 | COMET ONE-HOUR CLEANERS | Lubbock | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-07 | COMET ONE-HOUR CLEANERS | Lubbock | ID and Listing of HW: General | S |
| 2017-04-07 | COMET ONE-HOUR CLEANERS | Lubbock | Standards for Used Oil: Generators | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Standards for Used Oil: Generators | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Land Disposal Restrictions: General | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Standards Applicable to Generators of HW: General | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | Land Disposal Restrictions: General | S |
| 2017-04-05 | UNIVAR SOLUTIONS DALLAS DAN MORTON | Dallas | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | Land Disposal Restrictions: General | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | Standards Applicable to Generators of HW: Manifest Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-03-30 | XPO LOGISTICS FREIGHT LHO | Houston | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | Standards for Universal Waste Management: Standards for Small Quantity Handlers | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | Standards for Universal Waste Management: Standards for Small Quantity Handlers | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | Standards Applicable to Generators of HW: General | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | Land Disposal Restrictions: General | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-29 | FRITO-LAY ENVIRONMENTAL SYSTEMS | Fort Worth | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-23 | INTERNATIONAL GALVANIZERS | Beaumont | Land Disposal Restrictions: General | S |
| 2017-03-23 | INTERNATIONAL GALVANIZERS | Beaumont | EPA Administered Permit Programs: the HW Permit Program General Information | S |
| 2017-03-23 | INTERNATIONAL GALVANIZERS | Beaumont | Interim Status Standards for Owners and Operators of HW TSDs: General Facility Standards | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Interim Status Standards for Owners and Operators of HW TSDs: Tank Systems | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Standards Applicable to Recordkeeping and Reporting Applicable to Small and Large Quantity Generators | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Standards for Used Oil: Generators | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Interim Status Standards for Owners and Operators of HW TSDs: Air Emission Standards for Tanks, Surface Impoundments and Containers | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Standards Applicable to Generators of HW: General | S |
| 2017-03-23 | BUCKEYE TEXAS PROCESSING | Corpus Christi | Standards for Used Oil: Generators | S |
| 2017-03-15 | VALERO MCKEE PLANT | Sunray | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-03-15 | VALERO MCKEE PLANT | Sunray | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-03-14 | IPSCO KOPPEL TUBULARS BAYTOWN WORKS | Baytown | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-14 | NXP USA | Austin | Interim Status Standards for Owners and Operators of HW TSDs: Use and Management of Containers | S |
| 2017-03-14 | NXP USA | Austin | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
| 2017-03-14 | PRATT & WHITNEY DARO COATINGS DIVISION | Grand Prairie | State Statutory or Regulatory requirements that are broader-in-scope than the federal RCRA requirements | S |
| 2017-03-14 | PRATT & WHITNEY DARO COATINGS DIVISION | Grand Prairie | Interim Status Standards for Owners and Operators of HW TSDs: Contingency Plan and Emergency Procedures | S |
| 2017-03-14 | PRATT & WHITNEY DARO COATINGS DIVISION | Grand Prairie | Standards Applicable to Generators of HW: Pre-Transport Requirements Applicable to Small and Large Quantity Generators | S |
Figures from EPA’s RCRAInfo download.