A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Denali County, Alaska during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Denali County facility page.
Denali County, Alaska, 2024
- Stack tests 12
Air-emissions inspections in Denali County, other years
Air-emissions inspections recorded in Denali County, Alaska, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-10-24 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2024-10-08 | UNITED STATES SPACE FORCE (USSF) / CLEAR SPACE FORCE STATION (CLEAR SFS) | PCE Off-Site | State |
| 2024-07-31 | USIBELLI COAL MINE, INC. / USIBELLI COAL PREPARATION PLANT | PCE Off-Site | State |
| 2024-05-15 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2024-04-26 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2024-03-01 | UNITED STATES SPACE FORCE (USSF) / CLEAR SPACE FORCE STATION (CLEAR SFS) | PCE Off-Site | State |