Air-emissions inspections in Fairbanks North Star County, Alaska, 2017
- 45Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Fairbanks North Star County, Alaska during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Fairbanks North Star County facility page.
Fairbanks North Star County, Alaska, 2017
Air-emissions inspections in Fairbanks North Star County, other years
Air-emissions inspections recorded in Fairbanks North Star County, Alaska, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-14 | GREAT NORTHWEST, INC. / CHENA METRO CRUSHER | PCE Off-Site | State |
| 2017-12-13 | GREAT NORTHWEST, INC. / CHENA METRO CRUSHER | PCE Off-Site | State |
| 2017-12-12 | BRICE, INC / BROWN S HILL QUARRY PORTABLE CRUSHER #6 | PCE Off-Site | State |
| 2017-12-11 | COLASKA INC, DBA QAP / HP#9 CMI 500 | PCE Off-Site | State |
| 2017-12-05 | US ARMY (FORT WAINWRIGHT) / FORT WAINWRIGHT | PCE Off-Site | State |
| 2017-12-05 | UNIVERSITY OF ALASKA / UNIVERSITY OF ALASKA FAIRBANKS CAMPUS — high-priority violation on file | PCE Off-Site | State |
| 2017-11-16 | GOLDEN VALLEY ELECTRIC ASSOCIATION / NORTH POLE POWER PLANT | PCE Off-Site | State |
| 2017-11-13 | AURORA ENERGY LLC / CHENA POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2017-11-13 | MPC ALASKA TERMINAL COMPANY, LLC (MPC) / NORTH POLE FACILITY | PCE Off-Site | State |
| 2017-11-02 | PETRO STAR, INC. / NORTH POLE REFINERY | PCE Off-Site | State |
| 2017-10-20 | DOYON UTILITIES, LLC / FORT WAINWRIGHT (PRIVATIZED EMISSION UN | PCE Off-Site | State |
| 2017-09-26 | MPC ALASKA TERMINAL COMPANY, LLC (MPC) / NORTH POLE FACILITY | FCE On-Site | State |
| 2017-09-25 | US AIR FORCE (EIELSON) / EIELSON AIR FORCE BASE — high-priority violation on file | PCE Off-Site | State |
| 2017-09-13 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | PCE Off-Site | State |
| 2017-09-13 | FAIRBANKS NORTH STAR BOROUGH/DEPARTMEN / FNSB SOLID WASTE FACILITY | FCE On-Site | State |
| 2017-09-05 | US ECOLOGY ALASKA LLC (FORMERLY NRC AL / MOOSE CREEK FACILITY | PCE Off-Site | State |
| 2017-08-30 | MPC ALASKA TERMINAL COMPANY, LLC (MPC) / NORTH POLE FACILITY | PCE Off-Site | State |
| 2017-08-16 | FAIRBANKS NORTH STAR BOROUGH/DEPARTMEN / FNSB SOLID WASTE FACILITY | PCE Off-Site | State |
| 2017-08-07 | FAIRBANKS GOLD MINING INC / FORT KNOX MINE | PCE Off-Site | State |
| 2017-08-03 | FAIRBANKS GOLD MINING INC / FORT KNOX MINE | PCE Off-Site | State |
| 2017-07-12 | COLASKA INC, DBA QAP / HP#9 CMI 500 | FCE Off-Site | State |
| 2017-05-23 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FCE On-Site | State |
| 2017-05-19 | BRICE, INC / BROWN S HILL QUARRY PORTABLE CRUSHER #6 | PCE Off-Site | State |
| 2017-05-09 | GREAT NORTHWEST, INC. / CHENA METRO CRUSHER | PCE On-Site Record/Report Review | State |
| 2017-04-17 | US AIR FORCE (EIELSON) / EIELSON AIR FORCE BASE — high-priority violation on file | PCE Off-Site | State |
| 2017-04-17 | GREAT NORTHWEST, INC. / CHENA METRO CRUSHER | PCE Off-Site | State |
| 2017-04-10 | GOLDEN VALLEY ELECTRIC ASSOCIATION / NORTH POLE POWER PLANT | PCE Off-Site | State |
| 2017-04-05 | FAIRBANKS GOLD MINING INC / FORT KNOX MINE | PCE Off-Site | State |
| 2017-04-05 | FAIRBANKS GOLD MINING INC / FORT KNOX MINE | PCE Off-Site | State |
| 2017-04-05 | FAIRBANKS GOLD MINING INC / FORT KNOX MINE | PCE Off-Site | State |
| 2017-03-31 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | PCE Off-Site | State |
| 2017-03-28 | PETRO STAR, INC. / NORTH POLE REFINERY | PCE Off-Site | State |
| 2017-03-24 | UNIVERSITY OF ALASKA / UNIVERSITY OF ALASKA FAIRBANKS CAMPUS — high-priority violation on file | FCE On-Site | State |
| 2017-03-24 | COLASKA INC, DBA QAP / HP#9 CMI 500 | PCE Off-Site | State |
| 2017-03-23 | AURORA ENERGY LLC / CHENA POWER PLANT — high-priority violation on file | FCE On-Site | State |
| 2017-03-22 | US ARMY (FORT WAINWRIGHT) / FORT WAINWRIGHT | PCE Off-Site | State |
| 2017-03-20 | DOYON UTILITIES, LLC / FORT WAINWRIGHT (PRIVATIZED EMISSION UN | PCE Off-Site | State |
| 2017-03-15 | PETRO STAR, INC. / SOURDOUGH FUEL BULK PLANT | PCE Off-Site | State |
| 2017-03-02 | US ECOLOGY ALASKA LLC (FORMERLY NRC AL / MOOSE CREEK FACILITY | PCE Off-Site | State |
| 2017-03-02 | FAIRBANKS NORTH STAR BOROUGH/DEPARTMEN / FNSB SOLID WASTE FACILITY | PCE Off-Site | State |
| 2017-02-23 | MPC ALASKA TERMINAL COMPANY, LLC (MPC) / NORTH POLE FACILITY | PCE Off-Site | State |
| 2017-02-23 | MPC ALASKA TERMINAL COMPANY, LLC (MPC) / NORTH POLE FACILITY | PCE Off-Site | State |
| 2017-02-14 | AURORA ENERGY LLC / CHENA POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2017-02-06 | UNIVERSITY OF ALASKA / UNIVERSITY OF ALASKA FAIRBANKS CAMPUS — high-priority violation on file | PCE Off-Site | State |
| 2017-02-02 | UNIVERSITY OF ALASKA / UNIVERSITY OF ALASKA FAIRBANKS CAMPUS — high-priority violation on file | PCE Off-Site | State |