EPA Air · inspections by county and year
Air-emissions inspections in North Slope County, Alaska, 2021
- 177Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in North Slope County, Alaska during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the North Slope County facility page.
North Slope County, Alaska, 2021
Air-emissions inspections in North Slope County, other years
Air-emissions inspections recorded in North Slope County, Alaska, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-12-29 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | PCE Off-Site | State |
| 2021-12-29 | HILCORP ALASKA, LLC / PBU CENTRAL POWER STATION (CPS) | PCE Off-Site | State |
| 2021-12-28 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2021-12-27 | HILCORP ALASKA, LLC / PRUDHOE SEAWATER TREATMENT PLANT | PCE Off-Site | State |
| 2021-12-20 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2021-11-23 | CONOCOPHILLIPS ALASKA, INC. / ALPINE CENTRAL PROCESSING FACILITY | PCE Off-Site | State |
| 2021-11-19 | HILCORP ALASKA, LLC / MILNE POINT PRODUCTION FACILITY (MPU) | PCE Off-Site | State |
| 2021-11-19 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK RIVER UNIT TRANSPORTABLE DRILLI | PCE Off-Site | State |
| 2021-11-19 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | PCE Off-Site | State |
| 2021-11-18 | HILCORP ALASKA, LLC / SEAWATER INJECTION PLANT EAST (SIPE) | PCE Off-Site | State |
| 2021-11-16 | HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU) | PCE Off-Site | State |
| 2021-11-10 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | PCE Off-Site | State |
| 2021-11-10 | HILCORP ALASKA, LLC / GATHERING CENTER #1 (GC 1) | PCE Off-Site | State |
| 2021-11-10 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2021-11-09 | TDX POWER, LLC / TNSG NORTH POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-11-08 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | PCE Off-Site | State |
| 2021-11-08 | CONOCOPHILLIPS ALASKA, INC. / CPF 1, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-11-08 | HILCORP ALASKA, LLC / MILNE POINT L-PAD | PCE Off-Site | State |
| 2021-11-08 | HILCORP ALASKA, LLC / MILNE POINT UNIT C-PAD | PCE Off-Site | State |
| 2021-11-08 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK SEAWATER TREATMENT PLANT (STP) | PCE Off-Site | State |
| 2021-11-05 | HILCORP ALASKA, LLC / MILNE POINT UNIT C-PAD | PCE Off-Site | State |
| 2021-11-05 | CONOCOPHILLIPS ALASKA, INC. / CPF 3, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-11-04 | HILCORP ALASKA, LLC / PRUDHOE SEAWATER TREATMENT PLANT | PCE Off-Site | State |
| 2021-11-04 | HILCORP ALASKA, LLC / GATHERING CENTER #3 (GC 3) | PCE Off-Site | State |
| 2021-11-01 | CONOCOPHILLIPS ALASKA, INC. / CPF 2, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-11-01 | CONOCOPHILLIPS ALASKA, INC. / CPF 1, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-11-01 | TDX NORTH SLOPE GENERATING, LLC / TNSG SOUTH PLANT | PCE Off-Site | State |
| 2021-10-22 | HILCORP ALASKA, LLC / OOOGURUK DEVELOPMENT PROJECT | FCE Off-Site | State |
| 2021-10-20 | ALYESKA PIPELINE SERVICE COMPANY / PS #01, TAPS PUMP STATION | PCE Off-Site | State |
| 2021-10-15 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | PCE Off-Site | State |
| 2021-10-14 | ALYESKA PIPELINE SERVICE COMPANY / PS #03, TAPS PUMP STATION | PCE Off-Site | State |
| 2021-10-14 | ALYESKA PIPELINE SERVICE COMPANY / PS #04, TAPS PUMP STATION | PCE Off-Site | State |
| 2021-10-12 | HILCORP ALASKA, LLC / GRIND AND INJECT FACILITY (G & I) | PCE Off-Site | State |
| 2021-10-11 | HILCORP ALASKA, LLC / PRUDHOE BAY OPERATIONS CENTER / MAIN CO | PCE Off-Site | State |
| 2021-10-07 | HILCORP ALASKA, LLC / GATHERING CENTER #3 (GC 3) | PCE Off-Site | State |
| 2021-10-06 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | FCE Off-Site | State |
| 2021-10-04 | HILCORP ALASKA, LLC / LISBURNE PRODUCTION CENTER (LPC) | PCE Off-Site | State |
| 2021-09-29 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | PCE Off-Site | State |
| 2021-09-27 | NORTH SLOPE BOROUGH / ANAKTUVUK PASS POWER PLANT — high-priority violation on file | FCE Off-Site | State |
| 2021-09-24 | CONOCOPHILLIPS ALASKA, INC. / GREATER MOOSES TOOTH 1/MOOSES TOOTH 6 ( | PCE Off-Site | State |
| 2021-09-23 | CONOCOPHILLIPS ALASKA, INC. / GREATER MOOSES TOOTH UNIT | PCE Off-Site | State |
| 2021-09-20 | HILCORP ALASKA, LLC / CENTRAL GAS FACILITY (CGF) — high-priority violation on file | PCE Off-Site | State |
| 2021-09-20 | BARROW UTILITIES & ELECTRIC COOPERATIV / BARROW POWER PLANT | PCE Off-Site | State |
| 2021-09-20 | NORTH SLOPE BOROUGH / SERVICE AREA TEN HOTEL | FCE Off-Site | State |
| 2021-09-20 | HILCORP ALASKA, LLC / OOOGURUK DEVELOPMENT PROJECT | PCE Off-Site | State |
| 2021-09-17 | OIL SEARCH ALASKA, LLC, A SUBSIDIARY O / NANUSHUK DRILLSITE B | PCE Off-Site | State |
| 2021-09-15 | NORTH SLOPE BOROUGH / NUIQSUT POWER PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-09-15 | HILCORP ALASKA, LLC / NIKAITCHUQ DEVELOPMENT | FCE Off-Site | State |
| 2021-09-14 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / PBU CENTRAL POWER STATION (CPS) | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / PBU CENTRAL POWER STATION (CPS) | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2021-09-10 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2021-09-09 | HILCORP ALASKA, LLC / GATHERING CENTER #1 (GC 1) | PCE Off-Site | State |
| 2021-09-09 | HILCORP ALASKA, LLC / GATHERING CENTER #1 (GC 1) | PCE Off-Site | State |
| 2021-09-08 | HILCORP ALASKA, LLC / POINT THOMSON PRODUCTION FACILITY — high-priority violation on file | PCE Off-Site | State |
| 2021-09-02 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | PCE Off-Site | State |
| 2021-09-02 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | PCE Off-Site | State |
| 2021-09-02 | HILCORP ALASKA, LLC / FLOW STATION #2 (FS 2) | PCE Off-Site | State |
| 2021-09-02 | HILCORP ALASKA, LLC / GATHERING CENTER #1 (GC 1) | PCE Off-Site | State |
| 2021-09-01 | HILCORP ALASKA, LLC / GRIND AND INJECT FACILITY (G & I) | FCE Off-Site | State |
| 2021-08-31 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | FCE Off-Site | State |
| 2021-08-24 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2021-08-23 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | PCE Off-Site | State |
| 2021-08-20 | HILCORP ALASKA, LLC / MILNE POINT PRODUCTION FACILITY (MPU) | PCE Off-Site | State |
| 2021-08-18 | HILCORP ALASKA, LLC / TRANSPORTABLE DRILLING RIGS (DRILL RIGS | PCE Off-Site | State |
| 2021-08-18 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | FCE Off-Site | State |
| 2021-08-12 | NORTH SLOPE BOROUGH / POINT HOPE POWER PLANT | PCE Off-Site | State |
| 2021-08-12 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | PCE Off-Site | State |
| 2021-08-11 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2021-08-11 | HILCORP ALASKA, LLC / PRUDHOE BAY OPERATIONS CENTER / MAIN CO | PCE Off-Site | State |
| 2021-08-09 | HILCORP ALASKA, LLC / CENTRAL GAS FACILITY (CGF) — high-priority violation on file | PCE Off-Site | State |
| 2021-08-09 | HILCORP ALASKA, LLC / LISBURNE PRODUCTION CENTER (LPC) | PCE Off-Site | State |
| 2021-08-09 | NORTH SLOPE BOROUGH / BARROW TOS FACILITY | PCE Off-Site | State |
| 2021-08-09 | HILCORP ALASKA, LLC / NIKAITCHUQ DEVELOPMENT | PCE Off-Site | State |
| 2021-08-04 | CONOCOPHILLIPS ALASKA, INC. / CPF 2, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-08-04 | CONOCOPHILLIPS ALASKA, INC. / CPF 1, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-07-30 | CONOCOPHILLIPS ALASKA, INC. / CPF 3, KUPARUK CENTRAL PRODUCTION FACIL | PCE Off-Site | State |
| 2021-07-29 | CONOCOPHILLIPS ALASKA, INC. / ALPINE CENTRAL PROCESSING FACILITY | PCE Off-Site | State |
| 2021-07-29 | CONOCOPHILLIPS ALASKA, INC. / ALPINE SATELLITE DRILL PAD CD5 | PCE Off-Site | State |
| 2021-07-28 | NORTH SLOPE BOROUGH / KAKTOVIK POWER PLANT | PCE Off-Site | State |
| 2021-07-26 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2021-07-23 | CONOCOPHILLIPS ALASKA, INC. / KUPARUK SEAWATER TREATMENT PLANT (STP) | PCE Off-Site | State |
| 2021-07-21 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | PCE Off-Site | State |
| 2021-06-18 | HILCORP ALASKA, LLC / SEAWATER INJECTION PLANT EAST (SIPE) | PCE Off-Site | State |
| 2021-06-17 | HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU) | PCE Off-Site | State |
| 2021-06-16 | ALYESKA PIPELINE SERVICE COMPANY / PS #04, TAPS PUMP STATION | FCE Off-Site | State |
| 2021-06-08 | HILCORP ALASKA, LLC / PRUDHOE SEAWATER TREATMENT PLANT | PCE Off-Site | State |
| 2021-06-08 | ALYESKA PIPELINE SERVICE COMPANY / PS #03, TAPS PUMP STATION | FCE Off-Site | State |
| 2021-06-03 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | FCE Off-Site | State |
| 2021-06-01 | US AIR FORCE, PACAF REGIONAL SUPPORT C / CAPE LISBURNE LRRS | FCE Off-Site | State |
| 2021-05-28 | HILCORP ALASKA, LLC / FLOW STATION #1 (FS 1) — high-priority violation on file | PCE Off-Site | State |
| 2021-05-28 | HILCORP ALASKA, LLC / FLOW STATION #3 (FS 3) — high-priority violation on file | PCE Off-Site | State |
| 2021-05-24 | OIL SEARCH ALASKA, LLC, A SUBSIDIARY O / NANUSHUK DRILLSITE B | PCE Off-Site | State |
| 2021-05-21 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | PCE Off-Site | State |
| 2021-05-19 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | PCE Off-Site | U.S. EPA |
| 2021-05-19 | NANUQ INC. / ARCTIC WOLF CAMP | PCE Off-Site | State |
| 2021-05-17 | HILCORP ALASKA, LLC / PBU CENTRAL POWER STATION (CPS) | PCE Off-Site | State |
Page 1 of 2NextPage 2
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.