Air-emissions inspections in Northwest Arctic County, Alaska, 2023

A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Northwest Arctic County, Alaska during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Northwest Arctic County facility page.

Northwest Arctic County, Alaska, 2023

Air-emissions inspections in Northwest Arctic County, other years

Air-emissions inspections recorded in Northwest Arctic County, Alaska, 2023

DateFacilityKindAgency
2023-12-29TECK ALASKA, INC. (TECK) / RED DOG MINE — high-priority violation on fileFCE Off-SiteState
2023-12-01TECK AMERICAN INCORPORATED / RED DOG MINE LIFE EXTENSION (RD MLE) (APCE Off-SiteState
2023-11-30TECK ALASKA, INC. (TECK) / DMTS PORT FACILITY — high-priority violation on filePCE Off-SiteState
2023-08-03TECK ALASKA, INC. (TECK) / RED DOG MINE — high-priority violation on filePCE Off-SiteState
2023-03-31CROWLEY FUELS LLC (FORMERLY CPD ALASKA / KOTZEBUE BULK TANK FARMPCE Off-SiteState
2023-02-24KOTZEBUE ELECTRIC ASSOCIATION / KOTZEBUE POWER PLANTFCE Off-SiteState
2023-02-21TECK AMERICAN INCORPORATED / RED DOG MINE LIFE EXTENSION (RD MLE) (APCE Off-SiteState
2023-02-09TECK ALASKA, INC. (TECK) / DMTS PORT FACILITY — high-priority violation on filePCE Off-SiteState
2023-02-07TECK ALASKA, INC. (TECK) / RED DOG MINE — high-priority violation on filePCE Off-SiteState
2023-02-03ALASKA VILLAGE ELECTRIC COOPERATIVE / NOORVIK POWER PLANTPCE Off-SiteState
2023-02-03ALASKA VILLAGE ELECTRIC COOPERATIVE / SELAWIK POWER PLANTPCE Off-SiteState
2023-02-03ALASKA VILLAGE ELECTRIC COOPERATIVE / NOATAK POWER PLANTPCE Off-SiteState
2023-02-03ALASKA VILLAGE ELECTRIC COOPERATIVE / SHUNGNAK POWER PLANTPCE Off-SiteState
2023-02-02ALASKA VILLAGE ELECTRIC COOPERATIVE / KIVALINA POWER PLANTPCE Off-SiteState
2023-02-02ALASKA VILLAGE ELECTRIC COOPERATIVE / KIANA POWER PLANTPCE Off-SiteState
2023-01-31ALASKA VILLAGE ELECTRIC COOPERATIVE / AMBLER POWER PLANTPCE Off-SiteState
2023-01-23KOTZEBUE ELECTRIC ASSOCIATION / KOTZEBUE POWER PLANTPCE Off-SiteState
2023-01-20KOTZEBUE ELECTRIC ASSOCIATION / KOTZEBUE POWER PLANTPCE Off-SiteState
2023-01-18TECK ALASKA, INC. (TECK) / RED DOG MINE — high-priority violation on filePCE Off-SiteState
2023-01-12TECK ALASKA, INC. (TECK) / DMTS PORT FACILITY — high-priority violation on filePCE Off-SiteState
2023-01-07KOTZEBUE ELECTRIC ASSOCIATION / KOTZEBUE POWER PLANTPCE Off-SiteState
2023-01-05TECK AMERICAN INCORPORATED / RED DOG MINE LIFE EXTENSION (RD MLE) (APCE Off-SiteState