A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Bartow County, Georgia during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Bartow County facility page.
Bartow County, Georgia, 2018
- Stack tests 63
Air-emissions inspections in Bartow County, other years
Air-emissions inspections recorded in Bartow County, Georgia, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-20 | VULCAN CONSTRUCTION MATERIALS LLC - ADAIRSVILLE QUARRY | FCE On-Site | State |
| 2018-12-19 | VULCAN CONSTRUCTION MATERIALS LLC - ADAIRSVILLE QUARRY | PCE On-Site Record/Report Review | State |
| 2018-12-18 | FALTEC AMERICA, INC. | FCE On-Site | State |
| 2018-11-30 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-11-30 | CETCO | FCE On-Site | State |
| 2018-11-20 | FALTEC AMERICA, INC. | PCE On-Site Record/Report Review | State |
| 2018-11-14 | SHAW INDUSTRIES GROUP INC PLANT 13 | FCE On-Site | State |
| 2018-11-14 | SHAW INDUSTRIES PLANT 12N/12S | FCE On-Site | State |
| 2018-11-07 | SHAW INDUSTRIES GROUP INC PLANT 13 | PCE On-Site Record/Report Review | State |
| 2018-11-07 | SHAW INDUSTRIES PLANT 12N/12S | PCE On-Site Record/Report Review | State |
| 2018-10-31 | CETCO | PCE On-Site Record/Report Review | State |
| 2018-09-25 | ECO-ENERGY DISTRIBUTION - ATLANTA | FCE On-Site | State |
| 2018-09-18 | ECO-ENERGY DISTRIBUTION - ATLANTA | PCE On-Site Record/Report Review | State |
| 2018-09-14 | BARTOW COUNTY MSW LANDFILL | PCE Off-Site | State |
| 2018-08-30 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-08-30 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-08-30 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-08-21 | ANHEUSER-BUSCH, LLC. | PCE Off-Site | State |
| 2018-08-10 | GERDAU AMERISTEEL US INC. | PCE Off-Site | State |
| 2018-07-31 | TRINITYRAIL MAINTENANCE SERVICES, INC. - PLANT 493 | PCE Off-Site | State |
| 2018-07-31 | TOYO TIRE NORTH AMERICA MANUFACTURING, INC. | PCE Off-Site | State |
| 2018-07-27 | GA POWER CO. - PLANT BOWEN | FCE On-Site | State |
| 2018-07-25 | SHAW INDUSTRIES PLANT 12N/12S | PCE Off-Site | State |
| 2018-07-24 | PANDEL INC | PCE Off-Site | State |
| 2018-07-20 | SHAW INDUSTRIES GROUP INC PLANT 13 | PCE Off-Site | State |
| 2018-07-20 | HOLCIM US, INC. | PCE Off-Site | State |
| 2018-07-16 | TYSON POULTRY, INC. - FAIRMOUNT | PCE Off-Site | State |
| 2018-07-11 | GERDAU AMERISTEEL US INC. | PCE Off-Site | State |
| 2018-06-29 | TRINITYRAIL MAINTENANCE SERVICES, INC. - PLANT 493 | FCE On-Site | State |
| 2018-06-27 | GA POWER CO. - PLANT BOWEN | PCE On-Site Record/Report Review | State |
| 2018-06-25 | ANHEUSER-BUSCH, LLC. | PCE On-Site Record/Report Review | State |
| 2018-06-25 | ANHEUSER-BUSCH, LLC. | FCE On-Site | State |
| 2018-06-13 | TRINITYRAIL MAINTENANCE SERVICES, INC. - PLANT 493 | PCE On-Site Record/Report Review | State |
| 2018-06-07 | VMC SPECIALTY ALLOYS | PCE Off-Site | State |
| 2018-05-31 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-05-22 | ANHEUSER-BUSCH, LLC. | PCE Off-Site | State |
| 2018-05-10 | MATTHEWS, C.W., PLT 06 | FCE On-Site | State |
| 2018-05-08 | TYSON POULTRY, INC. - FAIRMOUNT | FCE On-Site | State |
| 2018-05-07 | MATTHEWS, C.W., PLT 06 | PCE On-Site Record/Report Review | State |
| 2018-05-03 | TYSON POULTRY, INC. - FAIRMOUNT | PCE On-Site Record/Report Review | State |
| 2018-03-01 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-03-01 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-02-26 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-02-23 | ANHEUSER-BUSCH, LLC. | PCE Off-Site | State |
| 2018-02-23 | TOYO TIRE NORTH AMERICA MANUFACTURING, INC. | FCE On-Site | State |
| 2018-02-13 | SKYLINE STEEL, LLC | PCE Off-Site | State |
| 2018-02-12 | GERDAU AMERISTEEL US INC. | PCE Off-Site | State |
| 2018-02-12 | GERDAU AMERISTEEL US INC. | PCE Off-Site | State |
| 2018-02-08 | TOYO TIRE NORTH AMERICA MANUFACTURING, INC. | PCE On-Site Record/Report Review | State |
| 2018-02-01 | GA POWER CO. - PLANT BOWEN | PCE Off-Site | State |
| 2018-01-30 | SHAW INDUSTRIES GROUP INC PLANT 13 | PCE Off-Site | State |
| 2018-01-29 | PANDEL INC | PCE Off-Site | State |
| 2018-01-29 | SHAW INDUSTRIES PLANT 12N/12S | PCE Off-Site | State |
| 2018-01-26 | TRINITYRAIL MAINTENANCE SERVICES, INC. - PLANT 493 | PCE Off-Site | State |
| 2018-01-22 | TOYO TIRE NORTH AMERICA MANUFACTURING, INC. | PCE Off-Site | State |
| 2018-01-19 | BARTOW COUNTY MSW LANDFILL | PCE Off-Site | State |
| 2018-01-12 | TYSON POULTRY, INC. - FAIRMOUNT | PCE Off-Site | State |
| 2018-01-11 | GERDAU AMERISTEEL US INC. | PCE Off-Site | State |
| 2018-01-09 | HOLCIM US, INC. | PCE Off-Site | State |