A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Houston County, Georgia during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Houston County facility page.
Houston County, Georgia, 2018
- Stack tests 23
Air-emissions inspections in Houston County, other years
Air-emissions inspections recorded in Houston County, Georgia, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-11-30 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-11-09 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-11-08 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-09-27 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | FCE On-Site | State |
| 2018-09-18 | ROBINS AIR FORCE BASE | FCE On-Site | State |
| 2018-09-06 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-08-30 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | PCE Off-Site | State |
| 2018-08-30 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | PCE Off-Site | State |
| 2018-08-30 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | PCE On-Site Record/Report Review | State |
| 2018-08-30 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-08-30 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-08-30 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-08-28 | MID-GEORGIA COGEN LP | FCE On-Site | State |
| 2018-08-28 | CG PS HOUSTON, LLC | PCE Off-Site | State |
| 2018-08-23 | MID-GEORGIA COGEN LP | PCE On-Site Record/Report Review | State |
| 2018-08-22 | ROBINS AIR FORCE BASE | PCE On-Site Record/Report Review | State |
| 2018-08-20 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-08-20 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-08-13 | HOUSTON COUNTY MSW LANDFILL | PCE Off-Site | State |
| 2018-08-02 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-07-30 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-07-27 | FLINT EMC - WALMART | PCE Off-Site | State |
| 2018-07-20 | GRAPHIC PACKAGING INTERNATIONAL, LLC (PERRY CARTON FACILITY) | PCE Off-Site | State |
| 2018-07-18 | PERDUE FOODS LLC | PCE Off-Site | State |
| 2018-07-17 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-07-17 | FRITO-LAY, INC., KATHLEEN FACILITY | PCE Off-Site | State |
| 2018-07-13 | EMORY HOSPITAL WARNER ROBINS | PCE Off-Site | State |
| 2018-06-06 | GA POWER CO. - ROBINS | FCE On-Site | State |
| 2018-05-31 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-05-24 | GA POWER CO. - ROBINS | PCE On-Site Record/Report Review | State |
| 2018-05-08 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-05-02 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-03-01 | INTERFOR U.S. INC. - PERRY MILL — high-priority violation on file | PCE Off-Site | State |
| 2018-03-01 | ANCHOR GLASS CONTAINER CORPORATION - WARNER ROBINS PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-03-01 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-03-01 | GA POWER CO. - ROBINS | PCE Off-Site | State |
| 2018-03-01 | CG PS HOUSTON, LLC | PCE Off-Site | State |
| 2018-02-28 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-02-28 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-02-28 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-02-28 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-02-22 | HOUSTON COUNTY MSW LANDFILL | PCE Off-Site | State |
| 2018-02-02 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-02-02 | MID-GEORGIA COGEN LP | PCE Off-Site | State |
| 2018-01-31 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-01-31 | EMORY HOSPITAL WARNER ROBINS | PCE Off-Site | State |
| 2018-01-30 | PERDUE FOODS LLC | PCE Off-Site | State |
| 2018-01-29 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-01-29 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-01-29 | ROBINS AIR FORCE BASE | PCE Off-Site | State |
| 2018-01-26 | FRITO-LAY, INC., KATHLEEN FACILITY | PCE Off-Site | State |
| 2018-01-25 | GRAPHIC PACKAGING INTERNATIONAL, LLC (PERRY CARTON FACILITY) | FCE On-Site | State |
| 2018-01-24 | FLINT EMC - WALMART | PCE Off-Site | State |
| 2018-01-23 | GRAPHIC PACKAGING INTERNATIONAL, LLC (PERRY CARTON FACILITY) | PCE On-Site Record/Report Review | State |
| 2018-01-23 | HOUSTON COUNTY MSW LANDFILL | PCE Off-Site | State |
| 2018-01-19 | GRAPHIC PACKAGING INTERNATIONAL, LLC (PERRY CARTON FACILITY) | PCE Off-Site | State |
| 2018-01-18 | CEMEX SOUTHEAST, LLC | PCE Off-Site | State |
| 2018-01-10 | PERDUE FOODS LLC | PCE Off-Site | State |