EPA Air · inspections by county and year
Air-emissions inspections in Upson County, Georgia, 2022
- 17Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Upson County, Georgia during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Upson County facility page.
Upson County, Georgia, 2022
- Stack tests 16
Air-emissions inspections in Upson County, other years
Air-emissions inspections recorded in Upson County, Georgia, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-11-29 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | PCE Off-Site | State |
| 2022-11-16 | EDWARD L. ADDISON GENERATING PLANT | PCE Off-Site | State |
| 2022-09-30 | TENCATE PROTECTIVE FABRICS | FCE On-Site | State |
| 2022-09-26 | TENCATE PROTECTIVE FABRICS | PCE On-Site Record/Report Review | State |
| 2022-09-13 | TENCATE PROTECTIVE FABRICS | PCE Off-Site | State |
| 2022-09-06 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | FCE On-Site | State |
| 2022-08-31 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | PCE On-Site Record/Report Review | State |
| 2022-08-30 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | PCE Off-Site | State |
| 2022-08-12 | EDWARD L. ADDISON GENERATING PLANT | PCE Off-Site | State |
| 2022-08-12 | EDWARD L. ADDISON GENERATING PLANT | PCE Off-Site | State |
| 2022-08-01 | SOUTHERN NATURAL GAS COMPANY, LLC - THOMASTON COMPRESSOR STATION | PCE Off-Site | State |
| 2022-05-31 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | PCE Off-Site | State |
| 2022-05-09 | EDWARD L. ADDISON GENERATING PLANT | PCE Off-Site | State |
| 2022-03-28 | TENCATE PROTECTIVE FABRICS | PCE Off-Site | State |
| 2022-03-01 | INTERFOR U.S. INC. - THOMASTON MILL — high-priority violation on file | PCE Off-Site | State |
| 2022-02-17 | EDWARD L. ADDISON GENERATING PLANT | PCE Off-Site | State |
| 2022-02-01 | SOUTHERN NATURAL GAS COMPANY, LLC - THOMASTON COMPRESSOR STATION | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.