Air-emissions inspections in Wilkinson County, Georgia, 2018
- 27Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Wilkinson County, Georgia during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Wilkinson County facility page.
Wilkinson County, Georgia, 2018
Air-emissions inspections in Wilkinson County, other years
Air-emissions inspections recorded in Wilkinson County, Georgia, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-18 | BASF CORPORATION, EDGAR PLANT | PCE On-Site Record/Report Review | State |
| 2018-09-05 | KAMIN LLC - GORDON PLANT | PCE Off-Site | State |
| 2018-09-05 | BASF CORPORATION, EDGAR PLANT | PCE Off-Site | State |
| 2018-09-05 | KAMIN LLC - TODDVILLE PLANT | PCE Off-Site | State |
| 2018-09-05 | CARBO CERAMICS, INC. - TOOMSBORO PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-09-04 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-08-20 | OLD HICKORY CLAY COMPANY | FCE On-Site | State |
| 2018-08-02 | KAMIN LLC - TODDVILLE PLANT | PCE Off-Site | State |
| 2018-08-01 | COVIA CLAY LLC - MCINTYRE PLANT | PCE Off-Site | State |
| 2018-07-30 | OLD HICKORY CLAY COMPANY | PCE On-Site Record/Report Review | State |
| 2018-07-30 | ACTIVE MINERALS INTERNATIONAL - MAIN PLANT | PCE Off-Site | State |
| 2018-07-25 | EAGLE RAILCAR SERVICES - GORDON, GA, LLC | PCE Off-Site | State |
| 2018-04-26 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | FCE On-Site | State |
| 2018-04-26 | CARBO CERAMICS, INC. - TOOMSBORO PLANT — high-priority violation on file | FCE On-Site | State |
| 2018-04-17 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | PCE On-Site Record/Report Review | State |
| 2018-04-17 | CARBO CERAMICS, INC. - TOOMSBORO PLANT — high-priority violation on file | PCE On-Site Record/Report Review | State |
| 2018-03-05 | CARBO CERAMICS, INC. - MCINTYRE PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-03-02 | KAMIN LLC - GORDON PLANT | PCE Off-Site | State |
| 2018-03-02 | BASF CORPORATION, EDGAR PLANT | PCE Off-Site | State |
| 2018-03-02 | KAMIN LLC - TODDVILLE PLANT | PCE Off-Site | State |
| 2018-03-02 | CARBO CERAMICS, INC. - TOOMSBORO PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-02-12 | KAMIN LLC - GORDON PLANT | PCE Off-Site | State |
| 2018-02-07 | CARBO CERAMICS, INC. - TOOMSBORO PLANT — high-priority violation on file | PCE Off-Site | State |
| 2018-01-31 | COVIA CLAY LLC - MCINTYRE PLANT | PCE Off-Site | State |
| 2018-01-31 | EAGLE RAILCAR SERVICES - GORDON, GA, LLC | PCE Off-Site | State |
| 2018-01-19 | OLD HICKORY CLAY COMPANY | PCE Off-Site | State |
| 2018-01-19 | ACTIVE MINERALS INTERNATIONAL - MAIN PLANT | PCE Off-Site | State |