A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Porter County, Indiana during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Porter County facility page.
Porter County, Indiana, 2017
- Stack tests 48
Air-emissions inspections in Porter County, other years
Air-emissions inspections recorded in Porter County, Indiana, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-21 | INDIANA FLAME SERVICE CONTRACTOR OF CLEVELAND-CLIFFS BURNS H | FCE On-Site | State |
| 2017-12-05 | BEEMSTERBOER SLAG CORPORATION A CONTRACTOR OF CLEVELAND-CLIF | FCE On-Site | State |
| 2017-11-14 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-10-20 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-08-11 | PVS TECHNOLOGIES INC — high-priority violation on file | FCE On-Site | State |
| 2017-08-08 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-07-18 | RIETH RILEY CONSTRUCTION COMPANY OAQ PORTABLE | FCE On-Site | State |
| 2017-07-14 | NLMK INDIANA — high-priority violation on file | PCE Off-Site | U.S. EPA |
| 2017-06-14 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-05-30 | MONOSOL LLC | FCE On-Site | State |
| 2017-05-17 | U S STEEL MIDWEST PLANT | PCE On-Site | U.S. EPA |
| 2017-05-10 | NLMK INDIANA — high-priority violation on file | FCE On-Site | State |
| 2017-04-20 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-04-06 | JET CORR INC/PRATT PAPER (IN) LLC — high-priority violation on file | PCE On-Site | U.S. EPA |
| 2017-03-27 | POWDER PROCESSING TECHNOLOGY LLC — high-priority violation on file | FCE On-Site | State |
| 2017-03-23 | PORTSIDE ENERGY LLC | FCE On-Site | State |
| 2017-03-22 | SMS MILL SERVICES LLC A CONTRACTOR OF NLMK INDIANA | FCE On-Site | State |
| 2017-03-22 | FRITZ ENTERPRISES INCORPORATED CONTRACTOR OF CLEVELAND-CLIFF | FCE On-Site | State |
| 2017-03-09 | AOC LLC | PCE On-Site | U.S. EPA |
| 2017-02-28 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-02-13 | U S STEEL MIDWEST PLANT | FCE On-Site | State |
| 2017-02-02 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-01-05 | CLEVELAND-CLIFFS BURNS HARBOR LLC — high-priority violation on file | PCE On-Site | State |
| 2017-01-04 | PRECOAT METALS | FCE On-Site | State |