EPA Air · inspections by county and year
Air-emissions inspections in Penobscot County, Maine, 2022
- 45Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Penobscot County, Maine during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Penobscot County facility page.
Penobscot County, Maine, 2022
- Stack tests 21
Air-emissions inspections in Penobscot County, other years
Air-emissions inspections recorded in Penobscot County, Maine, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-11-02 | ND OTM LLC | PCE Off-Site | State |
| 2022-10-31 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-10-28 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-09-20 | EAGLE POINT ENERGY CENTER, LLC | FCE Off-Site | State |
| 2022-09-08 | ND OTM LLC | FCE Off-Site | State |
| 2022-08-22 | ND OTM LLC | PCE On-Site | State |
| 2022-08-02 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-08-02 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-08-02 | ND OTM LLC | PCE Off-Site | State |
| 2022-08-02 | ND OTM LLC | PCE Off-Site | State |
| 2022-08-02 | STATE OF MAINE AND NEWSME LANDFILL OPERATIONS, LLC D/B/A JUNIPER RIDGE LANDFILL | PCE Off-Site | State |
| 2022-08-01 | BUCKEYE TERMINALS, LLC | PCE Off-Site | State |
| 2022-07-29 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-07-29 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-07-29 | COSTIGAN CHIP LLC | PCE Off-Site | State |
| 2022-07-29 | COLD BROOK ENERGY, INC. | PCE Off-Site | State |
| 2022-07-28 | EASTERN MAINE MEDICAL CENTER | PCE Off-Site | State |
| 2022-07-18 | THE UNIVERSITY OF MAINE SYSTEM | PCE Off-Site | State |
| 2022-07-08 | CASCO BAY ENERGY COMPANY, LLC | PCE Off-Site | State |
| 2022-07-08 | CASCO BAY ENERGY COMPANY, LLC | PCE Off-Site | State |
| 2022-07-01 | HUSSON UNIVERSITY | PCE Off-Site | State |
| 2022-05-26 | COSTIGAN CHIP LLC | PCE On-Site | State |
| 2022-05-04 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-05-02 | ND OTM LLC | PCE Off-Site | State |
| 2022-04-22 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-04-08 | CASCO BAY ENERGY COMPANY, LLC | PCE Off-Site | State |
| 2022-03-30 | ND OTM LLC | PCE On-Site | State |
| 2022-03-22 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE On-Site CEMS/CMS Audit | State |
| 2022-03-22 | NE RENEWABLE POWER WEST ENFIELD, LLC | FCE On-Site | State |
| 2022-02-11 | STATE OF MAINE AND NEWSME LANDFILL OPERATIONS, LLC D/B/A JUNIPER RIDGE LANDFILL | PCE Off-Site | State |
| 2022-02-03 | ND OTM LLC | PCE Off-Site | State |
| 2022-02-03 | ND OTM LLC | PCE Off-Site | State |
| 2022-02-02 | BUCKEYE TERMINALS, LLC | PCE Off-Site | State |
| 2022-01-31 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-01-31 | NE RENEWABLE POWER WEST ENFIELD, LLC | PCE Off-Site | State |
| 2022-01-31 | EASTERN MAINE MEDICAL CENTER | PCE Off-Site | State |
| 2022-01-31 | COSTIGAN CHIP LLC | PCE Off-Site | U.S. EPA |
| 2022-01-31 | COSTIGAN CHIP LLC | PCE Off-Site | State |
| 2022-01-28 | COLD BROOK ENERGY, INC. | PCE Off-Site | State |
| 2022-01-20 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-01-19 | THE UNIVERSITY OF MAINE SYSTEM | PCE Off-Site | State |
| 2022-01-12 | EAGLE POINT ENERGY CENTER, LLC | PCE Off-Site | State |
| 2022-01-11 | HUSSON UNIVERSITY | PCE Off-Site | State |
| 2022-01-11 | CASCO BAY ENERGY COMPANY, LLC | PCE Off-Site | State |
| 2022-01-11 | CASCO BAY ENERGY COMPANY, LLC | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.