EPA Air · inspections by county and year
Air-emissions inspections in Genesee County, Michigan, 2021
- 29Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Genesee County, Michigan during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Genesee County facility page.
Genesee County, Michigan, 2021
Air-emissions inspections in Genesee County, other years
Air-emissions inspections recorded in Genesee County, Michigan, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-12-10 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-11-12 | MONROE TRUCK EQUIPMENT | PCE On-Site | State |
| 2021-10-28 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-10-27 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-10-12 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-10-06 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-09-30 | ASCENSION GENESYS HOSPITAL | FCE On-Site | State |
| 2021-09-22 | GFX SOLUTIONS | FCE On-Site | State |
| 2021-09-21 | GREAT LAKES GAS TRANSMISSION STATION #13 | FCE On-Site | State |
| 2021-09-14 | ASCENSION GENESYS HOSPITAL | PCE Off-Site | State |
| 2021-09-03 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-08-30 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-08-19 | GREAT LAKES GAS TRANSMISSION STATION #13 | PCE On-Site | State |
| 2021-08-18 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-08-18 | UNIVERSAL COATING INC. | PCE On-Site | State |
| 2021-08-16 | BRENT RUN LANDFILL | PCE On-Site | U.S. EPA |
| 2021-08-13 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-08-11 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-08-04 | BRENT RUN LANDFILL | FCE On-Site | State |
| 2021-07-14 | NORTHERN STEEL SERVICES | PCE On-Site | State |
| 2021-07-01 | BRENT RUN LANDFILL | PCE On-Site | State |
| 2021-06-16 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-06-16 | GFX SOLUTIONS | PCE On-Site | State |
| 2021-04-14 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-04-12 | UNIVERSITY OF MICHIGAN FLINT | FCE On-Site | State |
| 2021-03-19 | UNIVERSITY OF MICHIGAN FLINT | PCE Off-Site | State |
| 2021-03-19 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-03-05 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
| 2021-01-29 | GENESEE POWER STATION LIMITED PARTNERSHIP | PCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.