Air-emissions inspections in Otsego County, Michigan, 2019
- 41Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Otsego County, Michigan during 2019. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Otsego County facility page.
Otsego County, Michigan, 2019
Air-emissions inspections in Otsego County, other years
Air-emissions inspections recorded in Otsego County, Michigan, 2019
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2019-12-27 | RIVERSIDE - ELMIRA 23 CPF | FCE On-Site | State |
| 2019-12-27 | RIVERSIDE - ELMIRA 23 CPF | PCE On-Site | State |
| 2019-11-21 | RIVERSIDE - LIVINGSTON 17 CPF | PCE On-Site | State |
| 2019-11-21 | RIVERSIDE - LIVINGSTON 17 CPF | FCE On-Site | State |
| 2019-11-12 | CORE ANTRIM COMPANY LLC BOTT CPF | FCE On-Site | State |
| 2019-11-05 | RIVERSIDE - HAYES 34 CPF | PCE On-Site | State |
| 2019-11-05 | RIVERSIDE - HAYES 34 CPF | FCE On-Site | State |
| 2019-10-28 | CORE ANTRIM COMPANY LLC BOTT CPF | PCE On-Site | State |
| 2019-10-16 | RIVERSIDE - SOUTH CHESTER - BIG BASS LAKE BOOSTER | FCE On-Site | State |
| 2019-10-15 | MUSKEGON OPERATING LLC - DOVER FACILITY | PCE On-Site | State |
| 2019-10-15 | MUSKEGON DEVELOPMENT, PIGEON RIVER FACILITY | PCE On-Site | State |
| 2019-10-15 | RIVERSIDE - SOUTH CHESTER - BIG BASS LAKE BOOSTER | PCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - VIENNA CHARLTON | PCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - VIENNA CHARLTON | FCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - MAYER | PCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - MAYER | FCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - SCV | FCE On-Site | State |
| 2019-10-10 | VCP MICHIGAN - SCV | PCE On-Site | State |
| 2019-10-09 | DCP ANTRIM GAS LLC | FCE On-Site | State |
| 2019-10-07 | DCP ANTRIM GAS LLC | PCE On-Site | State |
| 2019-10-03 | MUSKEGON OPERATING COMPANY, LLC - GINGEL LAKE | PCE On-Site | State |
| 2019-09-30 | JORDAN DEVELOPMENT COMPANY, L.L.C. - SCHROEDER | FCE On-Site | State |
| 2019-09-18 | LAMBDA ENERGY RESOURCES, LLC - CHARLTON 12 | PCE On-Site | State |
| 2019-09-18 | LAMBDA ENERGY RESOURCES, LLC - CHARLTON 12 | FCE On-Site | State |
| 2019-09-18 | LAMBDA ENERGY RESOURCES, LLC - CHARLTON 4 | PCE On-Site | State |
| 2019-09-18 | LAMBDA ENERGY RESOURCES, LLC - CHARLTON 4 | FCE On-Site | State |
| 2019-08-19 | JORDAN DEVELOPMENT COMPANY, L.L.C. - SCHROEDER | PCE On-Site | State |
| 2019-06-19 | RIVERSIDE ENERGY MICHIGAN LLC - WILDERNESS CO2, HAYES 29 CPF | PCE On-Site | State |
| 2019-06-19 | RIVERSIDE ENERGY MICHIGAN LLC - WILDERNESS CO2, HAYES 29 CPF | FCE On-Site | State |
| 2019-06-19 | RIVERSIDE - ELVIRA 11 PHASE 2 | FCE On-Site | State |
| 2019-06-19 | RIVERSIDE - OLD VANDY EAST CPF | PCE On-Site | State |
| 2019-06-18 | WOLVERINE POWER, GAYLORD GENERATING STATION | PCE On-Site | State |
| 2019-06-18 | WOLVERINE POWER, GAYLORD GENERATING STATION | FCE On-Site | State |
| 2019-06-05 | CORE ENERGY LLC - BAGLEY 11 | PCE On-Site | State |
| 2019-03-14 | ANR PIPELINE - CENTRAL CHARLTON COMPRESSOR STATION | FCE On-Site | State |
| 2019-03-14 | ANR PIPELINE - CENTRAL CHARLTON COMPRESSOR STATION | PCE On-Site | State |
| 2019-02-21 | WOLVERINE POWER SUPPLY COOPERATIVE INC. - ALPINE POWER PLANT | FCE On-Site | State |
| 2019-02-21 | WOLVERINE POWER SUPPLY COOPERATIVE INC. - ALPINE POWER PLANT | PCE On-Site | State |
| 2019-01-11 | VCP MICHIGAN - LIVINGSTON 34 | FCE On-Site | State |
| 2019-01-10 | JORDAN DEVELOPMENT COMPANY, LLC - PIGEON RIVER | FCE On-Site | State |
| 2019-01-04 | VCP MICHIGAN - CHARLTON 18 | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.