EPA Air · inspections by county and year
Air-emissions inspections in Alamance County, North Carolina, 2021
- 84Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Alamance County, North Carolina during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Alamance County facility page.
Alamance County, North Carolina, 2021
Air-emissions inspections in Alamance County, other years
Air-emissions inspections recorded in Alamance County, North Carolina, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-12-13 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-12-13 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-12-07 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-12-02 | ALAMANCE AGGREGATES, LLC | PCE On-Site | State |
| 2021-11-15 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-11-15 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-11-09 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-11-03 | MEREDITH-WEBB PRINTING COMPANY, INC. | PCE On-Site | State |
| 2021-11-02 | FLEXAUST, INC. | PCE Off-Site | State |
| 2021-10-28 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-10-28 | EDWARDS WOOD PRODUCTS, INC. | PCE On-Site | State |
| 2021-10-25 | ANDERSEN STERILIZERS INC. | PCE Off-Site | State |
| 2021-10-20 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-09-27 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-08-20 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-08-20 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-08-19 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-08-18 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-08-12 | SHAWMUT PARK AVENUE, LLC - SOUTH — high-priority violation on file | FCE On-Site | State |
| 2021-08-09 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-08-06 | ALAMANCE REGIONAL MEDICAL CENTER, INC. | PCE On-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-08-02 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-07-30 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-07-30 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-07-30 | FLEXAUST, INC. | PCE Off-Site | State |
| 2021-07-26 | KAYSER-ROTH CORPORATION - MEN'S FINISHING PLANT | PCE Off-Site | State |
| 2021-07-23 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-07-23 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-07-23 | ANDERSEN STERILIZERS INC. | PCE Off-Site | State |
| 2021-06-24 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | FCE On-Site | State |
| 2021-06-23 | FSC II, LLC - HAW RIVER ASPHALT PLANT | FCE On-Site | State |
| 2021-06-03 | CINTAS GRAHAM | FCE On-Site | State |
| 2021-05-26 | CITY OF BURLINGTON - EAST BURLINGTON WWTP | FCE On-Site | State |
| 2021-05-18 | STERICYCLE, INC. | FCE On-Site | State |
| 2021-04-29 | ANDERSEN STERILIZERS INC. | FCE On-Site | State |
| 2021-04-29 | FLEXAUST, INC. | PCE Off-Site | State |
| 2021-04-28 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-04-26 | ANDERSEN STERILIZERS INC. | PCE Off-Site | State |
| 2021-04-19 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-04-16 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-04-16 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-04-15 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-04-15 | MARTIN MARIETTA MATERIALS, INC. - BURLINGTON QUARRY | PCE On-Site | State |
| 2021-04-08 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-04-08 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-03-30 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-03-30 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-03-23 | APAC-ATLANTIC, INC. - PLANT #8 | FCE On-Site | State |
| 2021-03-17 | S. T. WOOTEN CORPORATION - HAW RIVER ASPHALT | FCE On-Site | State |
| 2021-03-04 | LIGGETT GROUP LLC | FCE On-Site | State |
| 2021-02-19 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-02-16 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-02-15 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-02-15 | STERICYCLE, INC. | PCE Off-Site | State |
| 2021-02-04 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-02-04 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-02-04 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | PCE Off-Site | State |
| 2021-02-04 | FSC II, LLC - HAW RIVER ASPHALT PLANT | PCE Off-Site | State |
| 2021-02-04 | FSC II, LLC - HAW RIVER ASPHALT PLANT | PCE Off-Site | State |
| 2021-02-01 | ANDERSEN STERILIZERS INC. | PCE Off-Site | State |
| 2021-02-01 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-02-01 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-01-30 | CANFOR SOUTHERN PINE - GRAHAM PLANT — high-priority violation on file | PCE Off-Site | State |
| 2021-01-29 | BURLINGTON INDUSTRIES LLC - BURLINGTON FINISHING PLANT | FCE On-Site | State |
| 2021-01-28 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-01-28 | CITY OF BURLINGTON - EAST BURLINGTON WWTP | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-27 | LIGGETT GROUP LLC | PCE Off-Site | State |
| 2021-01-26 | APAC-ATLANTIC, INC. - PLANT #8 | PCE Off-Site | State |
| 2021-01-22 | S. T. WOOTEN CORPORATION - HAW RIVER ASPHALT | PCE Off-Site | State |
| 2021-01-21 | KAYSER-ROTH CORPORATION - MEN'S FINISHING PLANT | PCE Off-Site | State |
| 2021-01-21 | KAYSER-ROTH CORPORATION - MEN'S FINISHING PLANT | PCE Off-Site | State |
| 2021-01-08 | SHAWMUT PARK AVENUE, LLC | PCE Off-Site | State |
| 2021-01-06 | LUXFER INC. - LUXFER GAS CYLINDERS DIVISION | PCE On-Site | State |
| 2021-01-06 | LOTUS BAKERIES USA MANUFACTURING, LLC | PCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.