EPA Air · inspections by county and year
Air-emissions inspections in Carroll County, New Hampshire, 2022
- 11Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Carroll County, New Hampshire during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Carroll County facility page.
Air-emissions inspections in Carroll County, other years
Air-emissions inspections recorded in Carroll County, New Hampshire, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-12-29 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-12-29 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-09-22 | WHITE LAKE STATION | FCE On-Site | State |
| 2022-09-14 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-09-14 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-07-18 | PIKE INDUSTRIES, INC. - OSSIPEE HMA | FCE On-Site | State |
| 2022-06-01 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-06-01 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-06-01 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-03-10 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
| 2022-03-10 | NE RENEWABLE POWER TAMWORTH — high-priority violation on file | PCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.