EPA Air · inspections by county and year
Air-emissions inspections in Clark County, Nevada, 2024
- 40Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Clark County, Nevada during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Clark County facility page.
Clark County, Nevada, 2024
Air-emissions inspections in Clark County, other years
Air-emissions inspections recorded in Clark County, Nevada, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-12-31 | PANWEST NCA2 HOLDINGS, LLC | FCE On-Site | Local |
| 2024-12-17 | WYNN LAS VEGAS ENCORE AT WYNN LAS VEGAS | FCE On-Site | Local |
| 2024-12-10 | APEX REGIONAL LANDFILL — high-priority violation on file | FCE On-Site | U.S. EPA |
| 2024-12-06 | NOVVA DATA CENTERS | FCE On-Site | Local |
| 2024-12-03 | BLUE DIAMOND HILL GYPSUM — high-priority violation on file | PCE Off-Site | Local |
| 2024-11-27 | CALNEV PIPE LINE, LLC | FCE On-Site | U.S. EPA |
| 2024-10-23 | COSTCO GASOLINE #1320 | FCE On-Site | Local |
| 2024-10-22 | LHOIST NORTH AMERICA OF ARIZONA - APEX PLANT — high-priority violation on file | PCE Off-Site | Local |
| 2024-09-23 | SWITCH LTD | PCE Off-Site | Local |
| 2024-09-19 | APEX REGIONAL LANDFILL — high-priority violation on file | PCE Off-Site | Local |
| 2024-09-19 | HIGH DESERT STATE PRISON — high-priority violation on file | FCE On-Site | Local |
| 2024-09-03 | DESERT STAR ENERGY CENTER | FCE On-Site | Local |
| 2024-09-03 | APEX GENERATING STATION | FCE On-Site | Local |
| 2024-08-20 | CLARK GENERATING STATION | FCE On-Site | Local |
| 2024-08-20 | HARRY ALLEN GENERATING STATION | FCE On-Site | Local |
| 2024-08-06 | CALNEV PIPE LINE, LLC | FCE On-Site | Local |
| 2024-08-06 | JENSEN ENTERPRISES, INCORPORATED | FCE On-Site | Local |
| 2024-07-27 | CHUCK LENZIE GENERATING STATION | PCE Off-Site | Local |
| 2024-07-08 | CAESARS ENTERTAINMENT INCORPORATED - CAESARS CONSOLIDATED PROPERTIES | FCE On-Site | Local |
| 2024-07-03 | AMRIZE SOUTHWEST, INC. — high-priority violation on file | PCE On-Site | Local |
| 2024-07-01 | CHUCK LENZIE GENERATING STATION | FCE On-Site | Local |
| 2024-06-12 | CERTAINTEED GYPSUM MANUFACTURING, INC. | FCE On-Site | Local |
| 2024-06-12 | HARRY ALLEN GENERATING STATION | PCE Off-Site | Local |
| 2024-06-11 | AMRIZE SOUTHWEST, INC. — high-priority violation on file | FCE On-Site | Local |
| 2024-06-05 | FIBERGLASS SPECIALTIES, INC. | FCE On-Site | Local |
| 2024-06-05 | AMRIZE SOUTHWEST, INC. — high-priority violation on file | PCE On-Site | Local |
| 2024-06-03 | PABCO GYPSUM | FCE On-Site | Local |
| 2024-05-29 | LHOIST NORTH AMERICA OF ARIZONA - APEX PLANT — high-priority violation on file | PCE Off-Site | Local |
| 2024-05-22 | BLUE DIAMOND HILL GYPSUM — high-priority violation on file | FCE On-Site | Local |
| 2024-05-13 | TITANIUM METALS CORPORATION HENDERSON FACILITY | FCE On-Site | Local |
| 2024-04-29 | LHOIST NORTH AMERICA OF ARIZONA - APEX PLANT — high-priority violation on file | PCE On-Site | Local |
| 2024-04-08 | LAS VEGAS GENERATING STATION | FCE On-Site | Local |
| 2024-03-28 | HARRY ALLEN GENERATING STATION | PCE Off-Site | Local |
| 2024-03-27 | APEX REGIONAL LANDFILL — high-priority violation on file | FCE On-Site | U.S. EPA |
| 2024-03-25 | CROWN CORK AND SEAL MESQUITE — high-priority violation on file | FCE On-Site | Local |
| 2024-03-20 | LHOIST NORTH AMERICA OF ARIZONA - APEX PLANT — high-priority violation on file | PCE Off-Site | Local |
| 2024-03-20 | AMRIZE SOUTHWEST, INC. — high-priority violation on file | PCE On-Site | Local |
| 2024-03-18 | ARMOROCK, LLC — high-priority violation on file | FCE On-Site | Local |
| 2024-03-05 | SILVERHAWK GENERATING STATION | FCE On-Site | Local |
| 2024-02-06 | FISHER SAND AND GRAVEL COMPANY | FCE Off-Site | Local |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.