EPA Air · inspections by county and year
Air-emissions inspections in Lorain County, Ohio, 2021
- 21Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Lorain County, Ohio during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Lorain County facility page.
Lorain County, Ohio, 2021
- Stack tests 19
Air-emissions inspections in Lorain County, other years
Air-emissions inspections recorded in Lorain County, Ohio, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-09-30 | GREEN CIRCLE GROWERS — high-priority violation on file | FCE On-Site | State |
| 2021-09-23 | UNITED INITIATORS, INC. | FCE Off-Site | State |
| 2021-09-22 | FORD MOTOR COMPANY - OHIO ASSEMBLY PLANT — high-priority violation on file | FCE On-Site | State |
| 2021-09-20 | TMS INTERNATIONAL, LLC | FCE Off-Site | State |
| 2021-09-13 | KOKOSING MATERIALS, INC. - PLANT NO 530 | FCE On-Site | State |
| 2021-09-07 | ROSS INCINERATION SERVICES, INC. | FCE On-Site | State |
| 2021-09-02 | TMS INTERNATIONAL, LLC | PCE Off-Site | State |
| 2021-08-30 | PLANT FACTORY INC | FCE Off-Site | State |
| 2021-08-24 | ROSS INCINERATION SERVICES, INC. | PCE On-Site | State |
| 2021-08-24 | REPUBLIC STEEL, F/K/A REPUBLIC ENGINEERED PRODUCTS, INC — high-priority violation on file | FCE On-Site | State |
| 2021-08-18 | UNITED INITIATORS, INC. | PCE Off-Site | State |
| 2021-08-17 | KOKOSING MATERIALS, INC. - PLANT NO 530 | PCE On-Site | State |
| 2021-08-04 | FORD MOTOR COMPANY - OHIO ASSEMBLY PLANT — high-priority violation on file | PCE On-Site | State |
| 2021-08-03 | REPUBLIC STEEL, F/K/A REPUBLIC ENGINEERED PRODUCTS, INC — high-priority violation on file | PCE On-Site | State |
| 2021-07-28 | U. S. STEEL SEAMLESS TUBULAR OPERATIONS, LLC - LORAIN | FCE Off-Site | State |
| 2021-07-28 | GREEN CIRCLE GROWERS — high-priority violation on file | PCE On-Site | State |
| 2021-07-19 | ELYRIA FOUNDRY | FCE Off-Site | State |
| 2021-06-24 | ELYRIA FOUNDRY | PCE Off-Site | State |
| 2021-06-22 | OBERLIN MUNICIPAL LIGHT & POWER SYSTEM | FCE Off-Site | State |
| 2021-06-16 | OBERLIN MUNICIPAL LIGHT & POWER SYSTEM | PCE Off-Site | State |
| 2021-04-21 | PLANT FACTORY INC | PCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.