EPA Air · inspections by county and year
Air-emissions inspections in Haskell County, Oklahoma, 2018
- 19Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Haskell County, Oklahoma during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Haskell County facility page.
Air-emissions inspections in Haskell County, other years
Air-emissions inspections recorded in Haskell County, Oklahoma, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-12-12 | ABUNDANCE ENERGY SERVICES LLC / PENNY 2 32 PAD | FCE On-Site | State |
| 2018-11-21 | ET GATHERING PROCESSING LLC / NORTH RUSSELLVILLE COMPRESSOR STATION | PCE Off-Site | State |
| 2018-08-30 | ABUNDANCE ENERGY SERVICES LLC / CHLOE 2 1 PAD | PCE Off-Site | State |
| 2018-08-30 | ARKOMA OPERATIONS LLC / DEVIN 2 12 PAD | PCE Off-Site | State |
| 2018-07-05 | ARKOMA OPERATIONS LLC / BINGO 3 2 PAD | PCE Off-Site | State |
| 2018-07-05 | ABUNDANCE ENERGY SERVICES LLC / CHLOE 3 1 PAD | PCE Off-Site | State |
| 2018-07-05 | ARKOMA OPERATIONS LLC / DEVIN 2 12 PAD | PCE Off-Site | State |
| 2018-07-05 | ABUNDANCE ENERGY SERVICES LLC / MELISSA 3 5 PAD | PCE Off-Site | State |
| 2018-06-08 | ET GATHERING PROCESSING LLC / NORTH RUSSELLVILLE COMPRESSOR STATION | PCE Off-Site | State |
| 2018-06-05 | ABUNDANCE ENERGY SERVICES LLC / OLIVER COMMON POINT | PCE Off-Site | State |
| 2018-05-02 | ARKOMA OPERATIONS LLC / JAKE 1 20 PAD | PCE Off-Site | State |
| 2018-05-02 | ABUNDANCE ENERGY SERVICES LLC / PENNY 2 32 PAD | PCE Off-Site | State |
| 2018-05-02 | ABUNDANCE ENERGY SERVICES LLC / JAKE 2 20 PAD | PCE Off-Site | State |
| 2018-05-02 | ABUNDANCE ENERGY SERVICES LLC / DOMINO 2 22 CTP | PCE Off-Site | State |
| 2018-05-02 | ABUNDANCE ENERGY SERVICES LLC / STOCKTON 2 3 CTP PAD | PCE Off-Site | State |
| 2018-05-02 | ARKOMA OPERATIONS LLC / MAGGIE 2 2 PAD | PCE Off-Site | State |
| 2018-05-02 | ABUNDANCE ENERGY SERVICES LLC / MAX 1 9 PAD | PCE Off-Site | State |
| 2018-02-27 | ET GATHERING PROCESSING LLC / CARTERSVILLE COMPRESSOR STATION | PCE Off-Site | State |
| 2018-01-31 | ET GATHERING PROCESSING LLC / LEQUIRE COMPRESSOR STATION | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.