A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Allegheny County, Pennsylvania during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Allegheny County facility page.
Allegheny County, Pennsylvania, 2023
Air-emissions inspections in Allegheny County, other years
Air-emissions inspections recorded in Allegheny County, Pennsylvania, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-12-15 | USS/CLAIRTON WORKS — high-priority violation on file | PCE Off-Site | Local |
| 2023-12-13 | LINDY PAVING INC/NEVILLE ISLAND | FCE On-Site | Local |
| 2023-12-05 | USS/CLAIRTON WORKS — high-priority violation on file | PCE Off-Site | Local |
| 2023-10-19 | USS/CLAIRTON WORKS — high-priority violation on file | PCE Off-Site | Local |
| 2023-10-05 | LINDY PAVING INC/2ND AVE PLT | FCE On-Site | Local |
| 2023-09-29 | MAGNUS PRODUCTS, LLC AT US STEEL - EDGAR THOMSON — high-priority violation on file | FCE On-Site | Local |
| 2023-09-12 | NRG POWER MIDWEST L.P../BRUNOT ISLE POWE | FCE On-Site | Local |
| 2023-09-06 | UNIVERSAL STAINLESS & ALLOY PROD/BRIDGEV — high-priority violation on file | FCE On-Site | Local |
| 2023-08-29 | LHT NEVILLE ISLAND TERMINALS - DE LLC | FCE On-Site | Local |
| 2023-08-29 | ALLIED WASTE SVC OF PA/MSW LDFL | FCE On-Site | Local |
| 2023-08-29 | FORTISTAR / IMPERIAL LANDFILL GAS COMPANY | FCE On-Site | Local |
| 2023-08-08 | KELLY RUN SANI/MSW LDFL | FCE On-Site | Local |
| 2023-08-03 | ALLEGHENY ENERGY SUPPLY/SPRINGDALE | FCE On-Site | Local |
| 2023-07-26 | PPG IND INC/SPRINGDALE | FCE On-Site | Local |
| 2023-07-14 | BUCKEYE PIPE LINE CO/CORAOPOLIS | FCE On-Site | Local |
| 2023-07-06 | ALLEGHENY LUDLUM LLC/BRACKENRIDGE | PCE On-Site Record/Report Review | Local |
| 2023-06-15 | USS/CLAIRTON WORKS — high-priority violation on file | FCE On-Site | Local |
| 2023-06-14 | AKJ STEEL INDUSTRIES, INC. | FCE On-Site | Local |
| 2023-06-06 | CHAMBERS DEV CO INC/MONROEVILLE | FCE On-Site | Local |
| 2023-06-02 | NRG ENERGY CTR PGH LLC/PGH | FCE On-Site | Local |
| 2023-03-23 | USS CORP/EDGAR THOMSON WORKS — high-priority violation on file | PCE On-Site | U.S. EPA |
| 2023-03-23 | USS CORP/EDGAR THOMSON WORKS — high-priority violation on file | FCE On-Site | Local |
| 2023-03-22 | USS/CLAIRTON WORKS — high-priority violation on file | PCE On-Site | U.S. EPA |
| 2023-03-22 | US STEEL CORP/IRVIN PLT | PCE On-Site | U.S. EPA |
| 2023-03-16 | LIBERTY PULTRUSIONS/WEST MIFFLIN | FCE On-Site | Local |