EPA Air · inspections by county and year
Air-emissions inspections in Frio County, Texas, 2019
- 13Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Frio County, Texas during 2019. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Frio County facility page.
Frio County, Texas, 2019
- Stack tests 12
Air-emissions inspections in Frio County, other years
- 2018 7
Air-emissions inspections recorded in Frio County, Texas, 2019
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2019-12-20 | PEARSALL POWER PLANT | FCE On-Site | State |
| 2019-04-24 | LANCASTER RANCH COMPRESSOR STATION AND TREATING FACILITY — high-priority violation on file | FCE Off-Site | State |
| 2019-02-01 | VENADO OPERATING-WELDON SCHORP 1 PRODUCTION FACILITY | PCE Off-Site | U.S. EPA |
| 2019-02-01 | VENADO OPERATING-THOMPSON RANCH 1H | PCE Off-Site | U.S. EPA |
| 2019-02-01 | VENADO OPERATING-SCHORP WHITE RANCH 101H PRODUCTION FACILITY | PCE Off-Site | U.S. EPA |
| 2019-02-01 | VENADO OPERATING-JAY HARPOLE 1H 2H TANK BATTERY | PCE Off-Site | U.S. EPA |
| 2019-02-01 | CARRIZO OIL & GAS-JENNINGS 10 H | PCE Off-Site | U.S. EPA |
| 2019-02-01 | SN OPERATING-HAUSSER D PAD | PCE Off-Site | U.S. EPA |
| 2019-02-01 | SN OPERATING-HAUSSER G PAD | PCE Off-Site | U.S. EPA |
| 2019-02-01 | SN OPERATING-HAUSSER J PAD | PCE Off-Site | U.S. EPA |
| 2019-02-01 | U.S. ENERGY DEVELOPMENT CORPORATION-HIDEAWAY RANCH B PAD | PCE Off-Site | U.S. EPA |
| 2019-02-01 | U.S. ENERGY DEVELOPMENT CORPORATION-HIDEAWAY RANCH C PAD | PCE Off-Site | U.S. EPA |
| 2019-02-01 | VIRTEX OPERATING COMPANY-BEEVER S C1 AND LITTLE DUKES TANK BATTERY | PCE Off-Site | U.S. EPA |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.