Air-emissions inspections in Halifax County, Virginia, 2026
- 70Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Halifax County, Virginia during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Halifax County facility page.
Halifax County, Virginia, 2026
Air-emissions inspections in Halifax County, other years
Air-emissions inspections recorded in Halifax County, Virginia, 2026
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2026-08-28 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-08-27 | AQUATIC COMPANY | PCE Off-Site | State |
| 2026-08-27 | AQUATIC COMPANY | PCE Off-Site | State |
| 2026-08-27 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-08-17 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-08-17 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-08-14 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-08-11 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-08-04 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE On-Site | State |
| 2026-08-04 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | FCE On-Site | U.S. EPA |
| 2026-08-03 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-31 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-31 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-31 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-27 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-07-27 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-07-23 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-23 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-07-23 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-07-23 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-07-22 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-22 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-21 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-07-21 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-07-20 | VOESTALPINE HIGH PERFORMANCE METALS CORPORATION | PCE Off-Site | State |
| 2026-07-10 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-07-06 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-06-24 | PIEDMONT ASPHALT LLC | FCE On-Site | State |
| 2026-06-24 | VOESTALPINE HIGH PERFORMANCE METALS CORPORATION | FCE On-Site | State |
| 2026-06-05 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-06-02 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-06-01 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-26 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-13 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-13 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-07 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-05-05 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-04 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-05-04 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-04-29 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-04-23 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-04-14 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-04-13 | HITACHI ENERGY USA INC | PCE Off-Site | State |
| 2026-03-26 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-03-25 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-03-19 | HUBER ENGINEERED WOODS, LLC | FCE On-Site | State |
| 2026-03-16 | HITACHI ENERGY USA INC | PCE Off-Site | State |
| 2026-02-26 | AQUATIC COMPANY | PCE Off-Site | State |
| 2026-02-26 | AQUATIC COMPANY | PCE Off-Site | State |
| 2026-02-26 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-02-17 | HITACHI ENERGY USA INC | PCE Off-Site | State |
| 2026-02-17 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-02-12 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-02-12 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-02-10 | GENESIS PRODUCTS INC | PCE Off-Site | State |
| 2026-02-03 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-02-03 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-02-03 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-02-03 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-02-03 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-01-30 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-01-29 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-01-28 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-01-28 | DOMINION/ODEC - CLOVER POWER STATION — high-priority violation on file | PCE Off-Site | State |
| 2026-01-28 | NOVEC ENERGY PRODUCTION HALIFAX COUNTY BIOMASS | PCE Off-Site | State |
| 2026-01-16 | AQUATIC COMPANY | FCE On-Site | State |
| 2026-01-08 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-01-08 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
| 2026-01-06 | HITACHI ENERGY USA INC | PCE Off-Site | State |
| 2026-01-05 | HUBER ENGINEERED WOODS, LLC | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.