A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Lynchburg (city) County, Virginia during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Lynchburg (city) County facility page.
Air-emissions inspections in Lynchburg (city) County, other years
Air-emissions inspections recorded in Lynchburg (city) County, Virginia, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-12-26 | FLOWERS BAKING CO OF LYNCHBURG LLC | PCE Off-Site | State |
| 2023-11-29 | GUARDIAN RAIL | FCE On-Site | State |
| 2023-10-24 | DAVIS FROST INC | FCE On-Site | State |
| 2023-10-23 | BELVAC PRODUCTION MACHINERY | FCE On-Site | State |
| 2023-10-23 | HANWHA AZDEL INC | PCE On-Site | State |
| 2023-10-06 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-10-05 | 700 MAIN ST LLC | PCE Off-Site | State |
| 2023-08-28 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-08-15 | FLOWERS BAKING CO OF LYNCHBURG LLC | PCE Off-Site | State |
| 2023-08-07 | FRITO LAY INCORPORATED | PCE Off-Site | State |
| 2023-08-04 | LYNCHBURG GENERAL HOSPITAL | PCE Off-Site | State |
| 2023-07-25 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-07-05 | SEVEN HILLS PAPERBOARD LLC | PCE Off-Site | State |
| 2023-06-26 | 700 MAIN ST LLC | FCE On-Site | State |
| 2023-05-19 | 700 MAIN ST LLC | PCE Off-Site | State |
| 2023-04-25 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-04-05 | GUARDIAN RAIL | PCE On-Site | State |
| 2023-03-16 | SCI VIRGINIA FUNERAL SERVICES LLC | PCE Off-Site | State |
| 2023-02-27 | 700 MAIN ST LLC | PCE Off-Site | State |
| 2023-02-16 | SCI VIRGINIA FUNERAL SERVICES LLC | PCE Off-Site | State |
| 2023-02-13 | SCI VIRGINIA FUNERAL SERVICES LLC | PCE Off-Site | State |
| 2023-02-03 | CHOICE ADHESIVES CORPORATION | PCE Off-Site | State |
| 2023-02-02 | GRIFFIN PIPE PRODUCTS CO LLC | FCE On-Site | State |
| 2023-01-31 | LYNCHBURG GENERAL HOSPITAL | PCE Off-Site | State |
| 2023-01-31 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-01-30 | FRITO LAY INCORPORATED | PCE Off-Site | State |
| 2023-01-26 | FLOWERS BAKING CO OF LYNCHBURG LLC | PCE Off-Site | State |
| 2023-01-18 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-01-18 | GRIFFIN PIPE PRODUCTS CO LLC | PCE Off-Site | State |
| 2023-01-17 | LYNCHBURG GENERAL HOSPITAL | PCE Off-Site | State |
| 2023-01-04 | SEVEN HILLS PAPERBOARD LLC | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.