Air-emissions inspections in Washington County, Virginia, 2026
- 41Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Washington County, Virginia during 2026. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Washington County facility page.
Air-emissions inspections in Washington County, other years
Air-emissions inspections recorded in Washington County, Virginia, 2026
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2026-09-02 | STRONGWELL HIGHLANDS | PCE Off-Site | State |
| 2026-09-02 | STRONGWELL HIGHLANDS | PCE Off-Site | State |
| 2026-09-01 | APPALACHIAN PLASTICS INCORPORATED | PCE Off-Site | State |
| 2026-08-28 | MOUNTAIN LAUREL CREMATION SERVICES | PCE Off-Site | State |
| 2026-08-14 | EMORY & HENRY COLLEGE | PCE Off-Site | State |
| 2026-08-14 | JOHNSTON MEMORIAL HOSPITAL | PCE Off-Site | State |
| 2026-08-14 | APPALACHIAN AGGREGATES LLC - GLADE STONE PLANT | FCE On-Site | State |
| 2026-08-13 | FEDERAL PACIFIC SWITCHGEAR FACILITY | FCE On-Site | State |
| 2026-08-07 | WOLF HILLS ENERGY | PCE Off-Site | State |
| 2026-08-07 | APPALACHIAN AGGREGATES LLC - GLADE STONE PLANT | PCE On-Site | State |
| 2026-08-06 | APPALACHIAN PLASTICS INCORPORATED | PCE Off-Site | State |
| 2026-08-05 | FARRIS CREMATION & FUNERAL CENTER, INC. | FCE On-Site | State |
| 2026-07-29 | WOLF HILLS ENERGY | PCE Off-Site | State |
| 2026-07-15 | HAPCO/DIVISION OF KEARNEY NATIONAL INCORPORATED | FCE On-Site | State |
| 2026-06-12 | HAPCO/DIVISION OF KEARNEY NATIONAL INCORPORATED | PCE On-Site | State |
| 2026-06-10 | SALTVILLE GAS STORAGE CO LLC-SALTVILLE STATION | FCE On-Site | State |
| 2026-06-10 | SALTVILLE GAS STORAGE CO LLC-EARLY GROVE STATION | FCE On-Site | State |
| 2026-05-28 | HOME PRIDE INCORPORATED | FCE On-Site | State |
| 2026-05-14 | HOME PRIDE INCORPORATED | PCE On-Site | State |
| 2026-05-07 | STUART RUSH | FCE On-Site | State |
| 2026-05-04 | WOLF HILLS ENERGY | PCE Off-Site | State |
| 2026-04-30 | LAKESIDE READY MIX INC. - PLANT NO 1 | FCE On-Site | State |
| 2026-04-23 | JD WATSON & ASSOCIATES INC | FCE On-Site | State |
| 2026-04-22 | APPALACHIAN CAST PRODUCTS | FCE On-Site | State |
| 2026-04-01 | UTILITY TRAILER MANUFACTURING COMPANY - GLADE SPRING | PCE Off-Site | State |
| 2026-03-26 | RIMEX INC | FCE On-Site | State |
| 2026-03-19 | GENERAL ENGINEERING CO | FCE On-Site | State |
| 2026-03-12 | WOLF HILLS ENERGY | PCE Off-Site | State |
| 2026-03-12 | CONTECH ENGINEERED SOLUTIONS | FCE On-Site | State |
| 2026-03-05 | UNIVERSAL FIBERS INC. | PCE Off-Site | State |
| 2026-03-05 | STRONGWELL HIGHLANDS | PCE Off-Site | State |
| 2026-03-05 | STRONGWELL HIGHLANDS | PCE Off-Site | State |
| 2026-02-23 | APPALACHIAN PLASTICS INCORPORATED | PCE Off-Site | State |
| 2026-02-10 | WOLF HILLS ENERGY | PCE Off-Site | State |
| 2026-02-03 | EMORY & HENRY COLLEGE | PCE Off-Site | State |
| 2026-02-02 | APPALACHIAN PLASTICS INCORPORATED | PCE Off-Site | State |
| 2026-01-12 | APPALACHIAN PLASTICS INCORPORATED | FCE On-Site | State |
| 2026-01-07 | CARDINAL CG ABINGDON | PCE Off-Site | State |
| 2026-01-07 | JOHNSTON MEMORIAL HOSPITAL | PCE Off-Site | State |
| 2026-01-06 | JD WATSON & ASSOCIATES INC | PCE Off-Site | State |
| 2026-01-06 | CARDINAL CG ABINGDON | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.