EPA Air · inspections by state, industry and year
Utilities (NAICS 2211): inspections in Alaska, 2025
- 251Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row is one inspection recorded during 2025 at a Alaska source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Alaska, other years
Other industries in Alaska, 2025
- Oil and gas extraction (NAICS 2111) 262
- Heavy and civil engineering construction (NAICS 2373) 87
- Merchant wholesalers, nondurable goods (NAICS 4247) 48
- National security and international affairs (NAICS 9281) 42
- Mining and quarrying (NAICS 2123) 38
- Food manufacturing (NAICS 3117) 30
- Mining and quarrying (NAICS 2122) 27
- Pipeline transportation (NAICS 4861) 14
- Petroleum and coal products manufacturing (NAICS 3241) 11
- Waste management and remediation (NAICS 5622) 11
- Educational services (NAICS 6113) 9
- Mining support (NAICS 2131) 9
- Support activities for transportation (NAICS 4883) 6
- Utilities (NAICS 2213) 4
- Hospitals (NAICS 6221) 3
- Waste management and remediation (NAICS 5629) 3
- Mining and quarrying (NAICS 2121) 3
- Warehousing and storage (NAICS 4931) 3
- Air transportation (NAICS 4812) 3
Air-emissions inspections recorded in Alaska, 2025
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2025-12-23 | MIDDLE KUSKOKWIM ELECTRIC COOPERATIVE, / RED DEVIL POWER PLANT | BETHEL, Bethel (CA), AK | FCE Off-Site | State |
| 2025-12-12 | CHUGACH ELECTRIC ASSOCIATION / BELUGA RIVER POWER PLANT | KENAI, Kenai Peninsula, AK | FCE Off-Site | State |
| 2025-12-12 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / BERNICE LAKE COMBUSTION TURBINE (BCT) P | KENAI, Kenai Peninsula, AK | FCE Off-Site | State |
| 2025-12-02 | ALASKA POWER & TELEPHONE / GUSTAVUS GENERATING STATION | ALASKA, Undetermined, AK | PCE Off-Site | State |
| 2025-11-20 | CITY OF UNALASKA / DUTCH HARBOR POWER PLANT (DHPP) — high-priority violation on file | DUTCH HARBOR, Aleutians West (CA), AK | FCE Off-Site | State |
| 2025-10-29 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | HEALY, Denali, AK | PCE Off-Site | State |
| 2025-10-28 | NORTH SLOPE BOROUGH / NUIQSUT POWER PLANT — high-priority violation on file | NORTH SLOPE BOROUGH, North Slope, AK | FCE Off-Site | State |
| 2025-10-27 | UNALAKLEET VALLEY ELECTRIC CO-OP / UNALAKLEET POWER PLANT | NOME, Nome (CA), AK | FCE Off-Site | State |
| 2025-10-24 | KETCHIKAN PUBLIC UTILITIES / BAILEY POWERHOUSE | KETCHIKAN, Ketchikan Gateway, AK | FCE On-Site | State |
| 2025-10-22 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-22 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-20 | KOTZEBUE ELECTRIC ASSOCIATION / KOTZEBUE POWER PLANT | KOTZEBUE, Northwest Arctic, AK | PCE Off-Site | State |
| 2025-10-16 | GOLDEN VALLEY ELECTRIC ASSOCIATION / DELTA POWER PLANT | DELTA JUNCTION, Southeast Fairbanks (CA), AK | PCE Off-Site | State |
| 2025-10-16 | TANANA POWER COMPANY, INC. / TANANA POWER PLANT | GALENA, Yukon-Koyukuk (CA), AK | FCE On-Site | State |
| 2025-10-15 | AURORA ENERGY LLC / CHENA POWER PLANT — high-priority violation on file | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-15 | AURORA ENERGY LLC / CHENA POWER PLANT — high-priority violation on file | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-15 | GOLDEN VALLEY ELECTRIC ASSOCIATION / NORTH POLE POWER PLANT | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-15 | GOLDEN VALLEY ELECTRIC ASSOCIATION / NORTH POLE POWER PLANT | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-10-13 | BARROW UTILITIES & ELECTRIC COOPERATIV / BARROW POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-10-10 | CITY OF GALENA / GALENA ELECTRIC UTILITY | GALENA, Yukon-Koyukuk (CA), AK | PCE Off-Site | State |
| 2025-10-07 | ALASKA VILLAGE ELECTRIC COOPERATIVE / KASIGLUK POWER PLANT | BETHEL, Bethel (CA), AK | FCE Off-Site | State |
| 2025-10-07 | ALASKA VILLAGE ELECTRIC COOPERATIVE / TOKSOOK BAY POWER PLANT | BETHEL, Bethel (CA), AK | FCE Off-Site | State |
| 2025-10-07 | ALASKA VILLAGE ELECTRIC COOPERATIVE / TOGIAK POWER PLANT | DILLINGHAM, Dillingham (CA), AK | FCE Off-Site | State |
| 2025-10-07 | ALASKA VILLAGE ELECTRIC COOPERATIVE / STEBBINS POWER PLANT | NOME, Nome (CA), AK | FCE Off-Site | State |
| 2025-10-07 | ALASKA VILLAGE ELECTRIC COOPERATIVE / WALES POWER PLANT | NOME, Nome (CA), AK | FCE Off-Site | State |
| 2025-10-03 | COPPER VALLEY ELECTRIC ASSOCIATION / CVEA COGENERATION PROJECT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-10-01 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / BERNICE LAKE COMBUSTION TURBINE (BCT) P | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-09-26 | CITY OF SAINT PAUL / ST. PAUL POWER PLANT | DUTCH HARBOR, Aleutians West (CA), AK | FCE Off-Site | State |
| 2025-09-26 | KODIAK ELECTRIC ASSOCIATION / NYMAN POWER PLANT | KODIAK, Kodiak Island, AK | PCE Off-Site | State |
| 2025-09-26 | KODIAK ELECTRIC ASSOCIATION / KODIAK (TAGURA) GENERATING STATION | KODIAK, Kodiak Island, AK | PCE Off-Site | State |
| 2025-09-26 | COPPER VALLEY ELECTRIC ASSOCIATION / GLENNALLEN DIESEL PLANT | VALDEZ, Valdez-Cordova (CA), AK | FCE Off-Site | State |
| 2025-09-25 | CORDOVA ELECTRIC COOPERATIVE / ORCA POWER PLANT — high-priority violation on file | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-09-22 | CITY OF EGEGIK / EGEGIK POWERPLANT | NEWHALEN, Lake and Peninsula, AK | FCE Off-Site | State |
| 2025-09-22 | COPPER VALLEY ELECTRIC ASSOCIATION / GLENNALLEN DIESEL PLANT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-09-22 | COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-09-19 | COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT | VALDEZ, Valdez-Cordova (CA), AK | FCE Off-Site | State |
| 2025-09-17 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / NIKISKI COMBINED CYCLE PLANT | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-09-11 | DOYON UTILITIES, LLC / DU-JBER-ELECTRIC, GAS, DRINKING WATER A | ANCHORAGE, Anchorage Municipality, AK | FCE Off-Site | State |
| 2025-09-09 | CITY OF UNALASKA / DUTCH HARBOR POWER PLANT (DHPP) — high-priority violation on file | DUTCH HARBOR, Aleutians West (CA), AK | PCE Off-Site | State |
| 2025-09-09 | HILCORP ALASKA, LLC / SUSAN DIONNE (SD) PAD, NINILCHIK | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-08-26 | CHUGACH ELECTRIC ASSOCIATION / GEORGE SULLIVAN PLANT TWO | ANCHORAGE, Anchorage Municipality, AK | PCE Off-Site | State |
| 2025-08-26 | CHUGACH ELECTRIC ASSOCIATION / HANK NIKKELS PLANT ONE | ANCHORAGE, Anchorage Municipality, AK | PCE Off-Site | State |
| 2025-08-26 | CHUGACH ELECTRIC ASSOCIATION / BELUGA RIVER POWER PLANT | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-08-25 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | ANCHORAGE, Anchorage Municipality, AK | FCE On-Site | State |
| 2025-08-25 | NUSHAGAK ELECTRIC COOPERATIVE, INC / DILLINGHAM POWER PLANT | DILLINGHAM, Dillingham (CA), AK | PCE Off-Site | State |
| 2025-08-22 | CITY OF SAINT PAUL / ST. PAUL POWER PLANT | DUTCH HARBOR, Aleutians West (CA), AK | PCE Off-Site | State |
| 2025-08-22 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | ANCHORAGE, Anchorage Municipality, AK | PCE Off-Site | State |
| 2025-08-22 | NOME JOINT UTILITY SYSTEM / SNAKE RIVER POWER PLANT | NOME, Nome (CA), AK | PCE Off-Site | State |
| 2025-08-22 | NORTH SLOPE BOROUGH / POINT HOPE POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-08-21 | MATANUSKA ELECTRIC ASSOCIATION, INC / EKLUTNA GENERATION STATION | ANCHORAGE, Anchorage Municipality, AK | PCE Off-Site | State |
| 2025-08-21 | ALASKA VILLAGE ELECTRIC COOPERATIVE / BETHEL POWER PLANT | BETHEL, Bethel (CA), AK | PCE Off-Site | State |
| 2025-08-13 | DOYON UTILITIES, LLC / DU-JBER-ELECTRIC, GAS, DRINKING WATER A | ANCHORAGE, Anchorage Municipality, AK | PCE Off-Site | State |
| 2025-08-13 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-08-13 | NORTH SLOPE BOROUGH / KAKTOVIK POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-08-12 | NORTH SLOPE BOROUGH / NUIQSUT POWER PLANT — high-priority violation on file | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-08-07 | NAKNEK ELECTRIC ASSOCIATION, INC. / NAKNEK POWER PLANT | KING SALMON, Bristol Bay, AK | PCE Off-Site | State |
| 2025-08-06 | ALASKA POWER & TELEPHONE / HAINES POWER GENERATING STATION | HAINES, Haines, AK | FCE Off-Site | State |
| 2025-08-05 | TDX POWER, LLC / TNSG NORTH POWER PLANT — high-priority violation on file | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-08-04 | ALASKA ELECTRIC LIGHT & POWER / LEMON CREEK STANDBY GENERATION STATION | JUNEAU, Juneau City and Borough, AK | PCE Off-Site | State |
| 2025-08-04 | ALASKA POWER & TELEPHONE / HAINES POWER GENERATING STATION | HAINES, Haines, AK | PCE Off-Site | State |
| 2025-08-04 | KETCHIKAN PUBLIC UTILITIES / BAILEY POWERHOUSE | KETCHIKAN, Ketchikan Gateway, AK | PCE Off-Site | State |
| 2025-08-04 | KETCHIKAN PUBLIC UTILITIES / BAILEY POWERHOUSE | KETCHIKAN, Ketchikan Gateway, AK | PCE Off-Site | State |
| 2025-08-01 | ALASKA ELECTRIC LIGHT & POWER / AUKE BAY STANDBY GENERATION STATION | JUNEAU, Juneau City and Borough, AK | PCE Off-Site | State |
| 2025-08-01 | ALASKA ELECTRIC LIGHT & POWER / INDUSTRIAL POWER PLANT (JUNEAU) | JUNEAU, Juneau City and Borough, AK | PCE Off-Site | State |
| 2025-07-31 | ALASKA ELECTRIC LIGHT & POWER / INDUSTRIAL POWER PLANT (JUNEAU) | JUNEAU, Juneau City and Borough, AK | FCE On-Site | State |
| 2025-07-29 | DOYON UTILITIES, LLC / FORT GREELY NATIONAL SECURITY (PRIVATIZ | DELTA JUNCTION, Southeast Fairbanks (CA), AK | PCE Off-Site | State |
| 2025-07-28 | ALASKA ELECTRIC LIGHT & POWER / AUKE BAY STANDBY GENERATION STATION | JUNEAU, Juneau City and Borough, AK | PCE Off-Site | State |
| 2025-07-28 | ALASKA ELECTRIC LIGHT & POWER / AUKE BAY STANDBY GENERATION STATION | JUNEAU, Juneau City and Borough, AK | PCE Off-Site | State |
| 2025-07-28 | ALASKA POWER & TELEPHONE / TOK POWER GENERATING STATION | DELTA JUNCTION, Southeast Fairbanks (CA), AK | PCE Off-Site | State |
| 2025-07-25 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT | KENAI, Kenai Peninsula, AK | FCE Off-Site | State |
| 2025-07-25 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-07-15 | CITY & BOROUGH OF SITKA / JARVIS ST. DIESEL PLANT | SITKA, Sitka City and Borough, AK | PCE Off-Site | State |
| 2025-07-14 | ALASKA VILLAGE ELECTRIC COOPERATIVE / YAKUTAT POWER PLANT | ALASKA, Undetermined, AK | PCE Off-Site | State |
| 2025-07-09 | ALASKA VILLAGE ELECTRIC COOPERATIVE / SHUNGNAK POWER PLANT | KOTZEBUE, Northwest Arctic, AK | FCE Off-Site | State |
| 2025-07-09 | ALASKA VILLAGE ELECTRIC COOPERATIVE / GRAYLING GENERATING STATION | GALENA, Yukon-Koyukuk (CA), AK | FCE Off-Site | State |
| 2025-07-08 | INSIDE PASSAGE ELECTRIC COOPERATIVE (I / HOONAH FACILITY | ALASKA, Undetermined, AK | PCE Off-Site | State |
| 2025-06-27 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | HEALY, Denali, AK | FCE On-Site | State |
| 2025-06-26 | NORTH SLOPE BOROUGH / KAKTOVIK POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | FCE On-Site | State |
| 2025-06-17 | NORTH SLOPE BOROUGH / WAINWRIGHT POWER PLANT | NORTH SLOPE BOROUGH, North Slope, AK | FCE On-Site | State |
| 2025-06-16 | GOLDEN VALLEY ELECTRIC ASSOCIATION / DELTA POWER PLANT | DELTA JUNCTION, Southeast Fairbanks (CA), AK | FCE Off-Site | State |
| 2025-06-10 | MATANUSKA ELECTRIC ASSOCIATION, INC / EKLUTNA GENERATION STATION | ANCHORAGE, Anchorage Municipality, AK | FCE Off-Site | State |
| 2025-06-03 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-06-03 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-05-30 | ALASKA POWER & TELEPHONE / HEALY LAKE GENERATING STATION | DELTA JUNCTION, Southeast Fairbanks (CA), AK | PCE Off-Site | State |
| 2025-05-30 | ALASKA POWER & TELEPHONE / SLANA POWER GENERATION PLANT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-05-29 | CITY OF ST. GEORGE / CITY OF ST. GEORGE | BETHEL, Bethel (CA), AK | PCE Off-Site | State |
| 2025-05-21 | INSIDE PASSAGE ELECTRIC COOPERATIVE (I / ANGOON POWER PLANT | ALASKA, Undetermined, AK | FCE Off-Site | State |
| 2025-05-21 | ALASKA POWER & TELEPHONE / ALLAKAKET GENERATING STATION | GALENA, Yukon-Koyukuk (CA), AK | PCE Off-Site | State |
| 2025-05-20 | ALASKA POWER & TELEPHONE / NORTHWAY GENERATING STATION | DELTA JUNCTION, Southeast Fairbanks (CA), AK | PCE Off-Site | State |
| 2025-05-15 | MCGRATH LIGHT & POWER / MCGRATH LIGHT AND POWER | GALENA, Yukon-Koyukuk (CA), AK | PCE Off-Site | State |
| 2025-05-13 | CORDOVA ELECTRIC COOPERATIVE / ORCA POWER PLANT — high-priority violation on file | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-05-13 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / BERNICE LAKE COMBUSTION TURBINE (BCT) P | KENAI, Kenai Peninsula, AK | PCE Off-Site | State |
| 2025-05-13 | COPPER VALLEY ELECTRIC ASSOCIATION / GLENNALLEN DIESEL PLANT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-05-13 | COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT | VALDEZ, Valdez-Cordova (CA), AK | PCE Off-Site | State |
| 2025-05-02 | GOLDEN VALLEY ELECTRIC ASSOCIATION / HEALY POWER PLANT — high-priority violation on file | HEALY, Denali, AK | PCE Off-Site | State |
| 2025-05-01 | GOLDEN VALLEY ELECTRIC ASSOCIATION / NORTH POLE POWER PLANT | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |
| 2025-05-01 | KODIAK ELECTRIC ASSOCIATION / KODIAK (TAGURA) GENERATING STATION | KODIAK, Kodiak Island, AK | PCE Off-Site | State |
| 2025-05-01 | KODIAK ELECTRIC ASSOCIATION / KODIAK (TAGURA) GENERATING STATION | KODIAK, Kodiak Island, AK | PCE Off-Site | State |
| 2025-05-01 | NORTH SLOPE BOROUGH / NUIQSUT POWER PLANT — high-priority violation on file | NORTH SLOPE BOROUGH, North Slope, AK | PCE Off-Site | State |
| 2025-04-25 | GOLDEN VALLEY ELECTRIC ASSOCIATION / ZEHNDER FACILITY | FAIRBANKS, Fairbanks North Star, AK | PCE Off-Site | State |