Velarion Records

The 340B register and hospital finances — joined, watched daily, delivered.

EPA Air · inspections by state, industry and year

Utilities (NAICS 2211): inspections in Kentucky, 2017

A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row is one inspection recorded during 2017 at a Kentucky source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.

Utilities (NAICS 2211) in Kentucky, other years

Other industries in Kentucky, 2017

Air-emissions inspections recorded in Kentucky, 2017

DateFacilityWhereKindAgency
2017-12-13TENNESSEE VALLEY AUTHORITY (TVA) - SHAWNEE FOSSIL PLANTWEST PADUCAH, McCracken, KYFCE On-SiteState
2017-12-08EAST KY POWER COOP - SPURLOCK STATIONMAYSVILLE, Mason, KYFCE On-SiteState
2017-11-28LOUISVILLE GAS & ELECTRIC CO - TRIMBLE CO GENERATING STATIONBEDFORD, Trimble, KYFCE On-SiteState
2017-11-16BIG RIVERS ELECTRIC CORP - DB WILSON STATION — high-priority violation on fileCENTERTOWN, Ohio, KYFCE On-SiteState
2017-11-15BIG RIVERS ELECTRIC CORP - REID HMP&L STATION 2ROBARDS, Webster, KYFCE On-SiteState
2017-11-15BIG RIVERS ELECTRIC CORP - RD GREEN STATIONROBARDS, Webster, KYFCE On-SiteState
2017-11-09EAST KY POWER - J K SMITH STATIONWINCHESTER, Clark, KYFCE On-SiteState
2017-11-02FARMERS RURAL ELECTRIC COOP CORPGLASGOW, Barren, KYFCE On-SiteState
2017-10-20DUKE ENERGY KY EAST BENDUNION, Boone, KYFCE On-SiteState
2017-09-11KY UTILITIES CO - GHENT STATIONGHENT, Carroll, KYFCE On-SiteState
2017-09-06EAST KY POWER COOP - BAVARIAN LGTEWALTON, Boone, KYFCE On-SiteState
2017-08-30PADUCAH POWER SYSTEM - PPS POWER PLANT # 1PADUCAH, McCracken, KYFCE On-SiteState
2017-08-23LOUISVILLE GAS AND ELECTRIC COMPANY CANE RUN GENERATING STATIONLOUISVILLE, Jefferson, KYFCE On-SiteLocal
2017-08-16LOUISVILLE GAS & ELECTRIC, PADDY'S RUNLOUISVILLE, Jefferson, KYFCE On-SiteLocal
2017-07-20TVA - KGEN MARSHALL LLCCALVERT CITY, Marshall, KYFCE On-SiteState
2017-07-18EAST KY POWER CORP - GREEN VALLEY LANDFILLASHLAND, Greenup, KYFCE On-SiteState
2017-07-17KENTUCKY POWER CO-BIG SANDY PLANTLOUISA, Lawrence, KYFCE On-SiteState
2017-07-13TENNESSEE VALLEY AUTHORITY - PARADISE FOSSIL PLANTDRAKESBORO, Muhlenberg, KYFCE On-SiteState
2017-06-16EAST KY POWER COOP - COOPER STATIONSOMERSET, Pulaski, KYFCE On-SiteState
2017-05-30EAST KENTUCKY POWER COOPERATIVE INC - CAGLESALBANY, Clinton, KYFCE On-SiteState
2017-05-25TENNESSEE VALLEY AUTHORITY (TVA) - SHAWNEE FOSSIL PLANTWEST PADUCAH, McCracken, KYFCE On-SiteState
2017-03-13EAST KY POWER COOP - HARDIN CO CONTAINED LANDFILLELIZABETHTOWN, Hardin, KYFCE On-SiteState
2017-02-13RIVERSIDE GENERATING CO LLCCATLETTSBURG, Lawrence, KYFCE On-SiteState
2017-02-02EAST KY POWER COOP - SPURLOCK STATIONMAYSVILLE, Mason, KYFCE On-SiteState
2017-02-02BIG RIVERS ELECTRIC CORP - DB WILSON STATION — high-priority violation on fileCENTERTOWN, Ohio, KYFCE On-SiteState
2017-01-25BIG RIVERS ELECTRIC CORP - REID HMP&L STATION 2ROBARDS, Webster, KYFCE On-SiteState
2017-01-25BIG RIVERS ELECTRIC CORP - RD GREEN STATIONROBARDS, Webster, KYFCE On-SiteState

Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.