EPA Air · inspections by state, industry and year
Utilities (NAICS 2211): inspections in Nebraska, 2020
- 47Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row is one inspection recorded during 2020 at a Nebraska source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Nebraska, other years
Other industries in Nebraska, 2020
- Administration of environmental programs (NAICS 9241) 109
- Merchant wholesalers, nondurable goods (NAICS 4245) 29
- Educational services (NAICS 6113) 23
- Nonmetallic mineral product manufacturing (NAICS 3273) 22
- Transportation equipment manufacturing (NAICS 3369) 21
- Food manufacturing (NAICS 3112) 20
- Plastics and rubber products manufacturing (NAICS 3262) 15
- Hospitals (NAICS 6221) 14
- Gasoline stations (NAICS 4471) 11
- Chemical manufacturing (NAICS 3254) 10
- Personal and laundry services (NAICS 8122) 10
- Utilities (NAICS 2213) 9
- Food manufacturing (NAICS 3111) 8
- Support activities for transportation (NAICS 4881) 8
- Primary metal manufacturing (NAICS 3315) 7
- Rail transportation (NAICS 4821) 7
- Pipeline transportation (NAICS 4869) 6
- Pipeline transportation (NAICS 4862) 5
- Chemical manufacturing (NAICS 3251) 5
- Petroleum and coal products manufacturing (NAICS 3241) 5
- Merchant wholesalers, nondurable goods (NAICS 4247) 5
- Nonmetallic mineral product manufacturing (NAICS 3271) 4
- Fabricated metal product manufacturing (NAICS 3323) 4
- Fabricated metal product manufacturing (NAICS 3328) 4
- Personal and laundry services (NAICS 8123) 4
- Repair and maintenance (NAICS 8111) 4
- Waste management and remediation (NAICS 5622) 3
- Chemical manufacturing (NAICS 3255) 3
- Professional, scientific and technical services (NAICS 5419) 3
- Mining and quarrying (NAICS 2123) 3
- Hospitals (NAICS 6222) 3
- Food manufacturing (NAICS 3116) 3
- Publishing industries (NAICS 5111) 3
- Fabricated metal product manufacturing (NAICS 3324) 3
- Transportation equipment manufacturing (NAICS 3363) 3
- Heavy and civil engineering construction (NAICS 2373) 3
- Plastics and rubber products manufacturing (NAICS 3261) 3
- Transportation equipment manufacturing (NAICS 3364) 3
Air-emissions inspections recorded in Nebraska, 2020
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2020-12-21 | FALLS CITY POWER PLANT — high-priority violation on file | FALLS CITY, Richardson, NE | FCE Off-Site | State |
| 2020-12-04 | OPPD NORTH OMAHA POWER STATION | OMAHA, Douglas, NE | FCE On-Site | Local |
| 2020-11-23 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE On-Site | Local |
| 2020-11-17 | MADISON LIGHT & POWER PLANT | MADISON, Madison, NE | FCE Off-Site | State |
| 2020-10-23 | OPPD JONES ST GENERATING STA | OMAHA, Douglas, NE | FCE On-Site | Local |
| 2020-10-22 | NPPD MC COOK PEAKING UNIT | MCCOOK, Red Willow, NE | FCE Off-Site | State |
| 2020-10-22 | NPPD HEBRON PEAKING UNIT | HEBRON, Thayer, NE | FCE Off-Site | State |
| 2020-10-08 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE On-Site | Local |
| 2020-09-29 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-09-29 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE On-Site Visible Emission Observation | Local |
| 2020-09-17 | NPPD GERALD GENTLEMAN STATION | SUTHERLAND, Lincoln, NE | FCE On-Site | State |
| 2020-08-18 | RED CLOUD MUNICIPAL PLANT | RED CLOUD, Webster, NE | FCE On-Site | State |
| 2020-08-10 | WHELAN ENERGY CENTER — high-priority violation on file | HASTINGS, Adams, NE | FCE On-Site | State |
| 2020-07-30 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-07-30 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | State |
| 2020-07-30 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | State |
| 2020-07-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | State |
| 2020-07-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | State |
| 2020-07-30 | LES TERRY BUNDY GENERATING STATION | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-07-30 | LES TERRY BUNDY GENERATING STATION | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-07-29 | WHELAN ENERGY CENTER — high-priority violation on file | HASTINGS, Adams, NE | FCE On-Site | State |
| 2020-07-28 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-07-28 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-07-21 | C W BURDICK GENERATING STATION | GRAND ISLAND, Hall, NE | FCE Off-Site | State |
| 2020-07-13 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE On-Site | Local |
| 2020-06-17 | PLATTE GENERATING STATION | GRAND ISLAND, Hall, NE | FCE Off-Site | State |
| 2020-06-17 | PLATTE GENERATING STATION | GRAND ISLAND, Hall, NE | FCE Off-Site | State |
| 2020-06-17 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE On-Site Visible Emission Observation | Local |
| 2020-05-27 | LON D WRIGHT POWER PLANT | FREMONT, Dodge, NE | FCE Off-Site | State |
| 2020-05-06 | WAYNE MUNICIPAL POWER PLANT | WAYNE, Wayne, NE | FCE Off-Site | State |
| 2020-03-25 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-02-20 | OPPD NORTH OMAHA POWER STATION | OMAHA, Douglas, NE | FCE On-Site | Local |
| 2020-02-20 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-02-16 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-02-03 | OPPD NEBRASKA CITY STATION | NEBRASKA CITY, Otoe, NE | FCE On-Site | State |
| 2020-01-31 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES EIGHT & J STREET POWER PLANT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES ROKEBY PEAKING UNIT | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES TERRY BUNDY GENERATING STATION | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-30 | LES TERRY BUNDY GENERATING STATION | LINCOLN, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-29 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-13 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
| 2020-01-13 | NPPD SHELDON STATION | HALLAM, Lancaster, NE | PCE Off-Site | Local |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.