Velarion Records
Follow this air source
Unsubscribe any time.

ICIS-AIR AK0000000212200006

KENAI LNG LLC / KENAI LIQUEFIED NATURAL GAS (LNG) PLANT, Kenai, AK: Clean Air Act compliance record, inspections, violations, penalties

KENAI LNG LLC / KENAI LIQUEFIED NATURAL GAS (LNG) PLANT is on EPA’s ICIS-AIR register at MILE 21.5 KENAI SPUR HWY, Kenai in Kenai Peninsula County, Alaska: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 55 events on file is a compliance evaluation dated August 25, 2026.
  • Its events on file run from March 22, 2017 through August 25, 2026.
  • Of its 49 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 53 air-emissions sources in Kenai Peninsula County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedKENAI LNG LLC / KENAI LIQUEFIED NATURAL GAS (LNG) PLANT
ICIS-AIR IDAK0000000212200006
EPA facility registry ID110007919501
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
AddressMILE 21.5 KENAI SPUR HWY, Kenai, AK 99611
CountyKenai Peninsula County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Oil and gas extraction (NAICS 2111)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 25, 2026PCE Off-SiteStateTitle V Permits
August 25, 2026PCE Off-SiteStateTitle V Permits
July 2, 2026PCE Off-SiteStateTitle V Permits
February 17, 2026PCE Off-SiteStateTitle V Permits
February 17, 2026PCE Off-SiteStateTitle V Permits
November 24, 2025PCE Off-SiteStateTitle V Permits
August 7, 2025PCE Off-SiteStateTitle V Permits
June 18, 2025FCE On-SiteStateTitle V Permits
June 16, 2025PCE Off-SiteStateTitle V Permits
February 27, 2025PCE Off-SiteStateTitle V Permits
November 15, 2024PCE Off-SiteStateTitle V Permits
November 15, 2024PCE Off-SiteStateTitle V Permits
August 19, 2024PCE Off-SiteStateTitle V Permits
May 10, 2024PCE Off-SiteStateTitle V Permits
April 15, 2024PCE Off-SiteStateTitle V Permits
November 30, 2023PCE Off-SiteStateTitle V Permits
September 22, 2023PCE Off-SiteStateTitle V Permits
May 9, 2023PCE Off-SiteStateTitle V Permits
March 28, 2023FCE On-SiteStateTitle V Permits
January 31, 2023PCE Off-SiteStateTitle V Permits
December 29, 2022PCE Off-SiteStateTitle V Permits
November 14, 2022PCE Off-SiteStateTitle V Permits
June 14, 2022PCE Off-SiteStateTitle V Permits
March 1, 2022PCE Off-SiteStateTitle V Permits
December 16, 2021PCE Off-SiteStateTitle V Permits
October 12, 2021PCE Off-SiteStateTitle V Permits
October 7, 2021PCE Off-SiteStateTitle V Permits
May 14, 2021FCE On-SiteStateTitle V Permits
April 20, 2021PCE Off-SiteStateTitle V Permits
April 20, 2021PCE Off-SiteStateTitle V Permits
December 17, 2020PCE Off-SiteStateTitle V Permits
October 14, 2020PCE Off-SiteStateTitle V Permits
May 28, 2020PCE Off-SiteStateTitle V Permits
November 27, 2019PCE Off-SiteStateTitle V Permits
August 14, 2019PCE Off-SiteStateTitle V Permits
July 3, 2019FCE On-SiteStateTitle V Permits
June 27, 2019PCE Off-SiteStateTitle V Permits
March 19, 2019PCE Off-SiteStateTitle V Permits
January 14, 2019PCE Off-SiteStateTitle V Permits
January 14, 2019PCE Off-SiteStateTitle V Permits
October 31, 2018PCE Off-SiteStateTitle V Permits
June 29, 2018PCE Off-SiteStateTitle V Permits
April 19, 2018PCE Off-SiteStateTitle V Permits
February 5, 2018PCE Off-SiteStateTitle V Permits
November 8, 2017PCE Off-SiteStateTitle V Permits
September 22, 2017FCE On-SiteStateTitle V Permits
August 17, 2017PCE Off-SiteStateTitle V Permits
June 8, 2017PCE Off-SiteStateTitle V Permits
March 22, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
June 30, 2025Earliest FRV determinationStateTitle V Permits
February 28, 2022Earliest FRV determinationStateTitle V Permits
October 12, 2021Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
July 7, 2026Warning LetterState
June 30, 2025Warning LetterState
April 11, 2025Warning LetterState

Stack tests

EPA’s stack test file holds no test at ICIS-AIR AK0000000212200006 since January 1, 2017.

Watch KENAI LNG LLC / KENAI LIQUEFIED NATURAL GAS (LNG) PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110007919501).

Other air sources in Alaska beside KENAI LNG LLC / KENAI LIQUEFIED NATURAL GAS (LNG) PLANT

EPA ICIS-AIR download, loaded September 14, 2026.