Velarion Records
Follow this air source
Unsubscribe any time.

ICIS-AIR AK0000000218500141

TDX POWER, LLC / TNSG NORTH POWER PLANT, North Slope Borough, AK: Clean Air Act compliance record, inspections, violations, penalties

TDX POWER, LLC / TNSG NORTH POWER PLANT is on EPA’s ICIS-AIR register at TRACT 72, ASL NO. 76-227, North Slope Borough in North Slope County, Alaska: operating status operating, emissions classification major source, current violation status “Violation w/in 1 Year”.

What stands out

  • The newest of the 45 events on file is a compliance evaluation dated September 25, 2026.
  • Its events on file run from June 2, 2017 through September 25, 2026.
  • Of its 27 compliance evaluations on file, 6 are a full compliance evaluation.
  • The register holds 76 air-emissions sources in North Slope County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedTDX POWER, LLC / TNSG NORTH POWER PLANT
ICIS-AIR IDAK0000000218500141
EPA facility registry ID110057109043
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)Violation w/in 1 Year
AddressTRACT 72, ASL NO. 76-227, North Slope Borough, AK 99734
CountyNorth Slope County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
September 25, 2026FCE Off-SiteStateTitle V Permits
September 23, 2026PCE Off-SiteStateTitle V Permits
February 12, 2026PCE Off-SiteStateTitle V Permits
August 5, 2025PCE Off-SiteStateTitle V Permits
March 3, 2025PCE Off-SiteStateTitle V Permits
August 30, 2024FCE Off-SiteStateTitle V Permits
August 29, 2024PCE Off-SiteStateTitle V Permits
April 19, 2024PCE Off-SiteStateTitle V Permits
August 8, 2023PCE Off-SiteStateTitle V Permits
February 6, 2023PCE Off-SiteStateTitle V Permits
November 22, 2022PCE Off-SiteStateTitle V Permits
September 26, 2022FCE On-SiteStateTitle V Permits
May 13, 2022PCE Off-SiteStateTitle V Permits
November 9, 2021PCE Off-SiteStateTitle V Permits
March 25, 2021PCE Off-SiteStateTitle V Permits
December 18, 2020FCE Off-SiteStateTitle V Permits
October 22, 2020PCE Off-SiteStateTitle V Permits
April 27, 2020PCE Off-SiteStateTitle V Permits
September 5, 2019PCE Off-SiteStateTitle V Permits
May 6, 2019PCE Off-SiteStateTitle V Permits
March 21, 2019FCE On-SiteState40 CFR Part 63 Area Sources; New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
December 26, 2018PCE Off-SiteStateTitle V Permits
May 10, 2018PCE Off-SiteStateTitle V Permits
May 10, 2018PCE Off-SiteStateTitle V Permits
December 27, 2017PCE Off-SiteStateTitle V Permits
June 29, 2017FCE On-SiteState40 CFR Part 63 Area Sources; New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
June 2, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
January 29, 2026Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
September 25, 2026Warning LetterState
April 13, 2026Warning LetterState
April 8, 2026Warning LetterState
April 3, 2025Warning LetterState
November 10, 2022Warning LetterState
November 8, 2022Warning LetterState
September 26, 2022Warning LetterState
June 10, 2022Warning LetterState

Stack tests

DateWhat EPA recordedAgency
January 23, 2026PassState
March 7, 2024PassState
January 19, 2023N/AState
February 19, 2022PassState
January 15, 2020PassState
January 21, 2018PendingState
January 21, 2018PassState
January 20, 2018PassState
January 20, 2018N/AState

Watch TDX POWER, LLC / TNSG NORTH POWER PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110057109043).

Other air sources in Alaska beside TDX POWER, LLC / TNSG NORTH POWER PLANT

EPA ICIS-AIR download, loaded September 14, 2026.