Clean Air Act stationary source · ICIS-AIR AK0000000229060003

ALYESKA PIPELINE SERVICE COMPANY / PS #05, TAPS PUMP STATION, Galena, AK: Clean Air Act compliance record, inspections, violations, penalties

ALYESKA PIPELINE SERVICE COMPANY / PS #05, TAPS PUMP STATION, at SECTIONS 18 & 19, T23N, R14W FAIRBANKS M, Galena in Yukon-Koyukuk (CA) County, Alaska, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.

What stands out

  • The newest of the 29 events on file is a compliance evaluation dated July 24, 2026.
  • Its events on file run from March 2, 2017 through July 24, 2026.
  • Of its 25 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 24 air-emissions sources in Yukon-Koyukuk (CA) County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedALYESKA PIPELINE SERVICE COMPANY / PS #05, TAPS PUMP STATION
ICIS-AIR IDAK0000000229060003
EPA facility registry ID110054088107
Operating statusOperating
Emissions classificationMajor source
Current violation status (ICIS-AIR high-priority violation field)No Violation Identified
AddressSECTIONS 18 & 19, T23N, R14W FAIRBANKS M, Galena, AK 99726
CountyYukon-Koyukuk (CA) County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Pipeline transportation (NAICS 4861)
EPA region10

Cited to the EPA ICIS-AIR facility file (ECHO download).

Programs and pollutants

Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs ALYESKA PIPELINE SERVICE COMPANY / PS #05, TAPS PUMP STATION is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
July 24, 2026PCE Off-SiteStateTitle V Permits
April 3, 2026PCE Off-SiteStateTitle V Permits
September 25, 2025PCE Off-SiteStateTitle V Permits
April 14, 2025PCE Off-SiteStateTitle V Permits
December 10, 2024FCE Off-SiteStateTitle V Permits
October 4, 2024PCE Off-SiteStateTitle V Permits
August 7, 2024PCE Off-SiteStateTitle V Permits
October 31, 2023PCE Off-SiteStateTitle V Permits
April 13, 2023PCE Off-SiteStateTitle V Permits
December 14, 2022FCE On-SiteStateTitle V Permits
October 25, 2022PCE Off-SiteStateTitle V Permits
April 5, 2022PCE Off-SiteStateTitle V Permits
October 13, 2021PCE Off-SiteStateTitle V Permits
March 24, 2021PCE Off-SiteStateTitle V Permits
December 3, 2020FCE On-SiteStateTitle V Permits
October 12, 2020PCE Off-SiteStateTitle V Permits
May 5, 2020PCE Off-SiteStateTitle V Permits
October 14, 2019PCE Off-SiteStateTitle V Permits
March 5, 2019FCE On-SiteState40 CFR Part 63 Area Sources; National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); New Source Performance Standards; Title V Permits
February 11, 2019PCE Off-SiteStateTitle V Permits
August 16, 2018PCE Off-SiteStateTitle V Permits
March 30, 2018PCE Off-SiteStateTitle V Permits
November 20, 2017PCE Off-SiteStateTitle V Permits
June 7, 2017FCE On-SiteStateTitle V Permits
March 2, 2017PCE Off-SiteStateTitle V Permits

Violations

A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.

DateWhat EPA recordedAgencyPrograms
December 10, 2024Earliest FRV determinationStateTitle V Permits
June 6, 2017Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.

Informal enforcement

DateWhat EPA recordedAgency
December 11, 2024Warning LetterState
June 7, 2017Warning LetterState

Stack tests

EPA’s stack test file holds no test at ICIS-AIR AK0000000229060003 since January 1, 2017.

Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.

Watch this source

One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, AK0000000229060003.

Start the watch

How often?
  • One source — $99/month
  • One county — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110054088107 there.

Nearby on the register

Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.

What this page shows

This page of the Velarion Records public-records register covers the Clean Air Act compliance record of ALYESKA PIPELINE SERVICE COMPANY / PS #05, TAPS PUMP STATION in Galena, AK. It lists 25 compliance evaluations since January 1, 2017, with 0 high-priority violations and 0 formal enforcement actions since January 1, 2017. The facility is listed as an operating major source with a current violation status of No Violation Identified.