GRAND DESIGN RV, Middlebury, IN: Clean Air Act compliance record, inspections, violations, penalties

GRAND DESIGN RV is on EPA’s ICIS-AIR register at 11333 CR 2, Middlebury in Elkhart County, Indiana: operating status operating, emissions classification major source, current violation status “No Violation Identified”. Elkhart County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 20 events on file is a compliance evaluation dated March 3, 2026.
  • Its events on file run from August 1, 2017 through March 3, 2026.
  • Of the 4 formal enforcement actions on file, 4 carry a filed penalty above zero. The largest on file is $144,950, filed July 11, 2022.
  • All 5 of its compliance evaluations on file are full compliance evaluations.
  • 4 of the 7 violation determinations on file are high-priority.
  • The register holds 155 air-emissions sources in Elkhart County, Indiana.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedGRAND DESIGN RV
ICIS-AIR IDIN0000001803900747
EPA facility registry ID110059696137
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address11333 CR 2, Middlebury, IN 46540-9632
CountyElkhart County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Transportation equipment manufacturing (NAICS 3362)
SIC code3792
EPA region05

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
March 3, 2026FCE On-SiteStateTitle V Permits
August 12, 2024FCE On-SiteStateTitle V Permits
July 13, 2022FCE On-SiteStateTitle V Permits
September 1, 2020FCE On-SiteStateTitle V Permits
September 13, 2018FCE On-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
October 11, 2022HPV day-zero determinationStateTitle V Permits
July 13, 2022Earliest FRV determinationStateTitle V Permits
May 11, 2022HPV day-zero determinationStateTitle V Permits
February 22, 2022Earliest FRV determinationStateTitle V Permits
August 1, 2021HPV day-zero determinationStateTitle V Permits
June 24, 2021Earliest FRV determinationStateTitle V Permits
May 3, 2018HPV day-zero determinationStateTitle V Permits

Enforcement and penalties

4 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
August 20, 2025Administrative OrderState$10,600
July 11, 2022Administrative OrderState$144,950
November 20, 2019Administrative OrderState$19,950
August 14, 2017Administrative OrderState$11,250

Informal enforcement

DateWhat EPA recordedAgency
July 11, 2025Notice of ViolationState
June 9, 2022Notice of ViolationState
September 19, 2019Notice of ViolationState
August 1, 2017Notice of ViolationState

Stack tests

EPA’s stack test file holds no test at ICIS-AIR IN0000001803900747 since January 1, 2017.

Watch GRAND DESIGN RV

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110059696137).

Other air sources in Indiana beside GRAND DESIGN RV

EPA ICIS-AIR download, loaded September 14, 2026.