ICIS-AIR IN0000001804500001

FOUNTAIN FOUNDRY, Veedersburg, IN: Clean Air Act compliance record, inspections, violations, penalties

FOUNTAIN FOUNDRY is on EPA’s ICIS-AIR register at 215 E VAN BUREN ST, Veedersburg in Fountain County, Indiana: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 35 events on file is a compliance evaluation dated July 30, 2025.
  • Its events on file run from April 13, 2017 through July 30, 2025.
  • Of the 3 formal enforcement actions on file, 3 carry a filed penalty above zero. The largest on file is $15,938, filed March 9, 2018.
  • Of its 6 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 7 air-emissions sources in Fountain County, Indiana.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedFOUNTAIN FOUNDRY
ICIS-AIR IDIN0000001804500001
EPA facility registry ID110001322042
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address215 E VAN BUREN ST, Veedersburg, IN 47987-1661
CountyFountain County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Primary metal manufacturing (NAICS 3315)
SIC code3321
EPA region05

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
July 30, 2025FCE On-SiteStateTitle V Permits
November 30, 2022FCE On-SiteStateTitle V Permits
November 10, 2021PCE On-SiteU.S. EPAMACT Standards (40 CFR Part 63)
April 15, 2021FCE On-SiteStateTitle V Permits
February 13, 2019FCE On-SiteStateTitle V Permits
June 1, 2017FCE On-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
May 1, 2025Earliest FRV determinationStateTitle V Permits
July 12, 2023Earliest FRV determinationStateTitle V Permits
February 1, 2023Earliest FRV determinationStateTitle V Permits
July 1, 2020Earliest FRV determinationStateTitle V Permits
July 1, 2020Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
July 1, 2019Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

3 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
April 23, 2024Administrative OrderState$500
March 9, 2018Administrative OrderState$15,938
May 26, 2017Administrative OrderState$500

Informal enforcement

DateWhat EPA recordedAgency
December 6, 2023Notice of ViolationState
December 15, 2017Notice of ViolationState
April 13, 2017Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
February 10, 2023PassState
February 10, 2023PassState
February 10, 2023PassState
February 10, 2023PassState
February 10, 2023PassState
February 10, 2023PassState
May 16, 2018PassState
May 16, 2018PassState
May 16, 2018PassState
May 15, 2018PassState
May 15, 2018PassState
May 15, 2018PassState
February 15, 2018PassState
February 14, 2018PassState
February 14, 2018PassState
February 13, 2018PassState
February 13, 2018PassState

Watch FOUNTAIN FOUNDRY

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110001322042).

Other air sources in Indiana beside FOUNTAIN FOUNDRY

EPA ICIS-AIR download, loaded September 14, 2026.