ICIS-AIR KS0000002018100005

GOODLAND MUN POWER PLANT (AIR), Goodland, KS: Clean Air Act compliance record, inspections, violations, penalties

GOODLAND MUN POWER PLANT (AIR) is on EPA’s ICIS-AIR register at 1701 CHERRY AVE., Goodland in Sherman County, Kansas: operating status operating, emissions classification synthetic minor source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 14 events on file is a compliance evaluation dated February 24, 2026.
  • Its events on file run from September 13, 2018 through February 24, 2026.
  • Of its 9 compliance evaluations on file, 8 are a full compliance evaluation.
  • The register holds 20 air-emissions sources in Sherman County, Kansas.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedGOODLAND MUN POWER PLANT (AIR)
ICIS-AIR IDKS0000002018100005
EPA facility registry ID110064153883
Operating statusOperating
Emissions classificationSynthetic minor source
Current violation status (HPV field)No Violation Identified
Address1701 CHERRY AVE., Goodland, KS 67735
CountySherman County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region07

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
February 24, 2026FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 24, 2026FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
January 24, 2025FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 5, 2024FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 2, 2023PCE Off-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
November 28, 2022FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
August 25, 2021FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
August 20, 2019FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 13, 2018FCE On-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
April 2, 2023Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
April 20, 2023Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
May 29, 2025PassState
May 29, 2025PassState
April 3, 2020PassState

Watch GOODLAND MUN POWER PLANT (AIR)

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110064153883).

Other air sources in Kansas beside GOODLAND MUN POWER PLANT (AIR)

EPA ICIS-AIR download, loaded September 14, 2026.