ICIS-AIR MO0000002907100003

AMEREN MISSOURI LABADIE ENERGY CENTER, Labadie, MO: Clean Air Act compliance record, inspections, violations, penalties

AMEREN MISSOURI LABADIE ENERGY CENTER is on EPA’s ICIS-AIR register at 226 LABADIE POWER PLANT ROAD, Labadie in Franklin County, Missouri: operating status operating, emissions classification major source, current violation status “No Violation Identified”. Franklin County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 86 events on file is a compliance evaluation dated April 2, 2026.
  • Of the 2 formal enforcement actions on file, 1 carries a filed penalty above zero. The largest on file is $9,977, filed April 8, 2024.
  • All 8 of its compliance evaluations on file are full compliance evaluations.
  • The register holds 103 air-emissions sources in Franklin County, Missouri.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedAMEREN MISSOURI LABADIE ENERGY CENTER
ICIS-AIR IDMO0000002907100003
EPA facility registry ID110000440470
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address226 LABADIE POWER PLANT ROAD, Labadie, MO 63055
CountyFranklin County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region07

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
April 2, 2026FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; New Source Review Permit Requirements; State or Local rule or regulation that is not federally-enforceable; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
November 26, 2024FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
August 15, 2023FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
June 1, 2022FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
July 21, 2021FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 3, 2020FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
April 9, 2019FCE On-SiteStateMACT Standards (40 CFR Part 63); National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
March 7, 2018FCE On-SiteStateMACT Standards (40 CFR Part 63); National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
December 5, 2024Earliest FRV determinationStateNational Emission Standards for Hazardous Air Pollutants (40 CFR Part 61)
November 26, 2024Earliest FRV determinationStateNew Source Review Permit Requirements
August 14, 2023Earliest FRV determinationStateMACT Standards (40 CFR Part 63); Title V Permits

Enforcement and penalties

1 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
April 8, 2024Administrative OrderState$9,977
September 30, 2019Civil Judicial ActionU.S. EPA$0

Informal enforcement

DateWhat EPA recordedAgency
April 4, 2025State/local ActionState
March 6, 2025State/local ActionState
December 26, 2024Warning LetterState
August 14, 2023Notice of ViolationState

Stack tests

The newest 50 of 69.

DateWhat EPA recordedAgency
February 27, 2025PassState
February 27, 2025PassState
February 27, 2025PassState
February 27, 2025PassState
December 20, 2024PassState
December 20, 2024PassState
December 20, 2024PassState
August 9, 2024PassState
August 9, 2024PassState
August 9, 2024PassState
August 9, 2024PassState
May 3, 2024PassState
May 3, 2024PassState
May 3, 2024PassState
May 3, 2024PassState
March 8, 2024PassState
March 8, 2024PassState
March 8, 2024PassState
March 8, 2024PassState
May 17, 2023PassState
May 17, 2023PassState
May 17, 2023PassState
May 17, 2023PassState
February 24, 2021PendingU.S. EPA
October 28, 2020PendingU.S. EPA
August 13, 2018PendingState
August 9, 2018PendingState
August 8, 2018PendingState
August 7, 2018PendingState
June 8, 2018PendingState
May 10, 2018PendingState
May 9, 2018PendingState
May 8, 2018PendingState
March 9, 2018PendingState
March 1, 2018PendingState
February 28, 2018PendingState
February 27, 2018PendingState
February 23, 2018PendingState
February 23, 2018PendingState
February 22, 2018PendingState
February 22, 2018PendingState
January 25, 2018PendingState
January 24, 2018PendingState
January 24, 2018PendingState
January 23, 2018PendingState
November 2, 2017PendingState
November 2, 2017PendingState
November 1, 2017PendingState
October 31, 2017PendingState
August 23, 2017PendingState

Watch AMEREN MISSOURI LABADIE ENERGY CENTER

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000440470).

Other air sources in Missouri beside AMEREN MISSOURI LABADIE ENERGY CENTER

EPA ICIS-AIR download, loaded September 14, 2026.