ICIS-AIR NJ0000003401100089

CALPINE NEW JERSEY GENERATION (FORMERLY: CONECTIV ATL GEN, LLC), Millville, NJ: Clean Air Act compliance record, inspections, violations, penalties

CALPINE NEW JERSEY GENERATION (FORMERLY: CONECTIV ATL GEN, LLC) is on EPA’s ICIS-AIR register at CUMBERLAND ENERGY CENTER, Millville in Cumberland County, New Jersey: operating status operating, emissions classification major source, current violation status “No Violation Identified”. Cumberland County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 31 events on file is a formal enforcement action dated May 24, 2024.
  • Its events on file run from March 8, 2017 through May 24, 2024.
  • Of the 6 formal enforcement actions on file, 6 carry a filed penalty above zero. The largest on file is $59,280, filed May 9, 2024.
  • All 3 of its compliance evaluations on file are full compliance evaluations.
  • The register holds 177 air-emissions sources in Cumberland County, New Jersey.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedCALPINE NEW JERSEY GENERATION (FORMERLY: CONECTIV ATL GEN, LLC)
ICIS-AIR IDNJ0000003401100089
EPA facility registry ID110023772229
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
AddressCUMBERLAND ENERGY CENTER, Millville, NJ 08332
CountyCumberland County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region02

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
September 29, 2023FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 27, 2020FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
May 8, 2018FCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
February 22, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 20, 2023Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
August 4, 2021Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
April 8, 2021Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 27, 2020Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 27, 2020Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
September 27, 2020Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
February 26, 2020Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
October 2, 2019Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
August 23, 2018Earliest FRV determinationLocalState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits

Enforcement and penalties

6 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
May 24, 2024Administrative OrderState$4,400
May 9, 2024Administrative OrderState$59,280
November 14, 2020Administrative OrderState$5,500
October 19, 2020Administrative OrderState$8,500
January 6, 2020Administrative OrderState$450
August 5, 2019Administrative OrderState$2,000

Informal enforcement

DateWhat EPA recordedAgency
April 8, 2024Notice of ViolationState
March 14, 2024Notice of ViolationState
August 9, 2021Notice of ViolationState
October 5, 2018Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
September 7, 2023PassState
September 9, 2022PassState
July 9, 2020PassState
July 7, 2020PassState
July 7, 2020PassState
October 20, 2017PassState
July 11, 2017PassState
March 8, 2017PassState

Watch CALPINE NEW JERSEY GENERATION (FORMERLY: CONECTIV ATL GEN, LLC)

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110023772229).

Other air sources in New Jersey beside CALPINE NEW JERSEY GENERATION (FORMERLY: CONECTIV ATL GEN, LLC)

EPA ICIS-AIR download, loaded September 14, 2026.