ICIS-AIR PA000243395
EBENSBURG POWER CO/EBENSBURG COGENERATION PLT, Ebensburg, PA: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 61Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 3Formal enforcement actions since January 1, 2017
EBENSBURG POWER CO/EBENSBURG COGENERATION PLT is on EPA’s ICIS-AIR register at 2840 NEW GERMANY RD, Ebensburg in Cambria County, Pennsylvania: operating status operating, emissions classification major source, current violation status “No Violation Identified”. Cambria County is on EPA’s Green Book list of areas that do not meet a national air quality standard.
What stands out
- The newest of the 92 events on file is a compliance evaluation dated August 24, 2026.
- Of the 3 formal enforcement actions on file, 2 carry a filed penalty above zero. The largest on file is $3,050, filed June 17, 2019.
- Of its 61 compliance evaluations on file, 4 are a full compliance evaluation.
- The register holds 106 air-emissions sources in Cambria County, Pennsylvania.
Every line is computed by formula from the record’s stored figures; nothing is estimated.
Identity
| Facility as filed | EBENSBURG POWER CO/EBENSBURG COGENERATION PLT |
|---|---|
| ICIS-AIR ID | PA000243395 |
| EPA facility registry ID | 110000330632 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (HPV field) | No Violation Identified |
| Address | 2840 NEW GERMANY RD, Ebensburg, PA 15931-3505 |
| County | Cambria County |
| In a nonattainment county | Yes (EPA Green Book) |
| Industry (NAICS) | Utilities (NAICS 2211) |
| SIC code | 4911 |
| EPA region | 03 |
Programs and pollutants
The program, pollutant and Title V files are not loaded: what this page covers.
Compliance evaluations
- 61Evaluations since January 1, 2017
- 4Full compliance evaluations
The newest 50 of 61.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 24, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 13, 2026 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 4, 2025 | PCE On-Site Monitoring/Sampling | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 20, 2025 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 1, 2025 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 4, 2024 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| November 28, 2023 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 5, 2023 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 28, 2023 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 17, 2023 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 23, 2023 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 6, 2023 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 19, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| August 10, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 7, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 27, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 12, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 2, 2022 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 6, 2021 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 6, 2021 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 4, 2021 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 9, 2021 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| January 27, 2021 | FCE On-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| January 11, 2021 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 19, 2020 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 17, 2020 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 22, 2020 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 20, 2020 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| January 29, 2020 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 17, 2019 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 18, 2019 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 3, 2019 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| March 10, 2019 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 5, 2019 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| November 9, 2018 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 27, 2018 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 21, 2018 | PCE Off-Site | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
Violations
- 3Violation determinations since January 1, 2017
- 0Of them high-priority
What high-priority and federally reportable violations mean.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| November 28, 2023 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| February 5, 2019 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| July 27, 2018 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
Enforcement and penalties
2 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.
| Date | What EPA recorded | Agency | Penalty, as filed |
|---|---|---|---|
| June 17, 2019 | Administrative Order | State | $3,050 |
| May 21, 2019 | CAA 113A Admin Compliance Order (Non-Penalty) | U.S. EPA | $0 |
| October 29, 2018 | Administrative Order | State | $388 |
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| November 28, 2023 | Notice of Violation | State |
| October 5, 2023 | Notice of Violation | State |
| September 19, 2023 | Notice of Violation | State |
| July 28, 2023 | Notice of Violation | State |
Stack tests
- 21Stack tests since January 1, 2017
- 0Recorded as failed
| Date | What EPA recorded | Agency |
|---|---|---|
| September 3, 2025 | Pass | State |
| September 2, 2025 | Pass | State |
| March 18, 2025 | Pass | State |
| August 8, 2024 | Pass | State |
| August 9, 2023 | Pass | State |
| August 26, 2022 | Pass | State |
| June 22, 2022 | Pass | State |
| June 1, 2022 | Pass | State |
| March 23, 2022 | Pass | State |
| September 2, 2020 | Pass | State |
| September 8, 2019 | Pass | State |
| February 27, 2019 | Pass | State |
| December 4, 2018 | Pass | State |
| September 14, 2018 | Pass | State |
| August 15, 2018 | Pass | State |
| March 6, 2018 | Pass | State |
| November 21, 2017 | Pass | State |
| September 1, 2017 | Pass | State |
| August 31, 2017 | Pass | State |
| June 14, 2017 | Pass | State |
| January 25, 2017 | Pass | State |
Watch EBENSBURG POWER CO/EBENSBURG COGENERATION PLT
Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000330632).
Other air sources in Pennsylvania beside EBENSBURG POWER CO/EBENSBURG COGENERATION PLT
- EBENSBURG POWER CO/NANTY GLO REFUSE SITE EBENSBURG, Cambria County PA000630882
- EBERT COLLISION SOLUTIONS/ LOWER SOUTHAMPTON TWP LANGHORNE, Bucks County PA000639959
- EBY PAVING & CONST INC/SR0064 PLEASANT GAP PLT BELLEFONTE, Centre County PA000494748
- EC SNYDER INC/HARRISBURG HARRISBURG, Dauphin County PA000547590
- ECC BETHANY INC/BARRETT MINE HOMER CITY, Indiana County PA000888110
- ECC BETHANY INC/CRESSON B4 MAINS LILLY, Cambria County PA000870326
- ECC BETHANY INC/CRESSON B5 LEFT LILLY, Cambria County PA000870320
- ECC BETHANY/SW MAINS BH1 LILLY, Cambria County PA000881199
- ECC WINDSOR INC/BAILEY MINE SP01 WIND RIDGE, Greene County PA000883244
- ECC WINDSOR INC/BUCKLANDFLARE SITE WIND RIDGE, Greene County PA000850248
- ECKART AMERICA LLC/LINCOLN DR PLT TAMAQUA, Schuylkill County PA000510741
- ECKART AMERICA LLC/TIDEWOOD PLT TAMAQUA, Schuylkill County PA000549447
- ECKENRODE'S GARAGE EBENSBURG, Cambria County PA0000004202144015
- ECKHART AUTO BODY INC/HARLEYSVILLE HARLEYSVILLE, Montgomery County PA000640853
- ECLIPSE FLEET SVC/NANTICOKE NANTICOKE, Luzerne County PA000718624
- ECO-ENERGY DISTRIBUTION SERVICES PHILADELPHIA COUNTY, Philadelphia County PAPAM0004210110438
- ECON O DRY CLNR/GROVE CITY GROVE CITY, Mercer County PA000573450
- ECOPAX LLC/FORKS TWP EASTON, Northampton County PA000681509
- ECORE INTL INC/LANCASTER LANCASTER, Lancaster County PA000542108
- ECORE INTL INC/YORK YORK, York County PA000704657
- ECORE TIRE COLLECTION LLC/CHAMBERSBURG CHAMBERSBURG, Franklin County PA000510173
- ED SHULTS TOYOTA BRADFORD, McKean County PA0000004208340001
- ED SHULTZ, INC WARREN, Warren County PA0000004212340001
- EDDIES CLNR HANOVER/HANOVER HANOVER, York County PA000495523
- EDDINGTON THREAD MFG CO INC/BENSALEM TWP BENSALEM, Bucks County PA000812293
- EDDYSTONE MARINE & RAIL TERM CO/EDDYSTONE EDDYSTONE, Delaware County PA000758609
- EDEN MILLWORK/KNOX KNOX, Clarion County PA000513468
- EDGEMARC ENERGY (CRATTY WELL PAD) EMLENTON, Butler County PA000830221
- EDGEMARC ENERGY (DRACO WELL PAD) WEST SUNBURY, Butler County PA000830224
- EDGEMARC ENERGY (LYNX WELL PAD) WEST SUNBURY, Butler County PA000830223
- EDGEMARC ENERGY (MORROW WELL PAD) WEST SUNBURY, Butler County PA000830222
- EDGEMARC ENERGY (SCULPTOR WELL PAD) PARKER, Butler County PA000830225
- EDGEMARC ENERGY (URSA MINOR WELL PAD) WEST SUNBURY, Butler County PA000830198
- EDGEMONT SUNOCO EDGEMONT, Delaware County PA0000004204544025
- EDGEWOOD CLEANING COMPANY PITTSBURGH, Allegheny County PAACH0004200395043
- EDGEWOOD VILLAGE CLNR/FALLS TWP YARDLEY, Bucks County PA000760767
- EDINBORO CLNR/EDINBORO EDINBORO, Erie County PA000642775
- EDISON QUARRY/DOYLESTOWN DOYLESTOWN, Bucks County PA000262986
- EDMC DATA CENTER ROBINSON, TOWNSHIP OF, Allegheny County PAACH0004200302016
- EDS AUTO BODY INC/BROOKHAVEN BROOKHAVEN, Delaware County PA000640027
- EDWARD E GOLDBERG & SONS PHILADELPHIA, Philadelphia County PAPAM0004210105105
- EDWARD GREENE & SONS/SUSQUEHANNA SUSQUEHANNA, Susquehanna County PA000740338
- EDWIN L HEIM CO/HARRISBURG 14TH ST HARRISBURG, Dauphin County PA000868548
- EFFORT FOUNDRY INC/BATH BATH, Northampton County PA000494176
- EGER SUZUKI BRIDGEPORT, Montgomery County PA0000004209140007
- EIGHTY FOUR CONTAINER/ N STRABANE EIGHTY FOUR, Washington County PA000495595
- EINSTEIN MED CTR/EAST NORRITON EAST NORRITON, Montgomery County PA000738848
- EITER RESIDENCE BETHEL PARK, Allegheny County PAACH0004200301282
- ELEC MOTOR & SUPPLY/ALTOONA MOTOR REPAIR ALTOONA, Blair County PA000630658
- ELECTRALLOY GO CARLSON/OIL CITY OIL CITY, Venango County PA000247724
- ELECTRIC MOTOR SERVICE COMPANY DUQUESNE, Allegheny County PAACH0004200300713
- ELECTRO CHEM MFG LLC/EMMAUS EMMAUS, Lehigh County PA000567162
- ELECTRO SPACE FABRIC/TOPTON PLT TOPTON, Berks County PA000513744
- ELECTRO TECH INC/MEADVILLE MEADVILLE, Crawford County PA000549574
- ELEGANCE CLNR/MECHANICSBURG MECHANICSBURG, Cumberland County PA000565848
- ELEGANT CLNR/WILKES BARRE HANOVER TOWNSHIP, Luzerne County PA000650565
- ELEMENT MATERIALS TECH/NEWTOWN TWP NEWTOWN, Bucks County PA000829043
- ELG METALS, INC. MCKEESPORT, Allegheny County PAACH0004200302004
- ELIAS AMOCO #1476 MCKEES ROCKS, BOROUGH OF, Allegheny County PAACH0004200301124
- ELITE CLNR/LOWER PROVIDENCE TWP EAGLEVILLE, Montgomery County PA000784283