OXBOW CREEK ENERGY LLC/ FACTORYVILLE, Factoryville, PA: Clean Air Act compliance record, inspections, violations, penalties

OXBOW CREEK ENERGY LLC/ FACTORYVILLE is on EPA’s ICIS-AIR register at BOB HENRY RD, Factoryville in Wyoming County, Pennsylvania: operating status operating, emissions classification minor source, current violation status “No Violation Identified”. Wyoming County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 24 events on file is a compliance evaluation dated August 31, 2026.
  • Its events on file run from January 3, 2020 through August 31, 2026.
  • Of the 1 formal enforcement action on file, 1 carries a filed penalty above zero. The largest on file is $27,620, filed March 24, 2026.
  • Of its 12 compliance evaluations on file, 2 are a full compliance evaluation.
  • 2 of the 4 stack tests on file are recorded as failed.
  • The register holds 47 air-emissions sources in Wyoming County, Pennsylvania.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedOXBOW CREEK ENERGY LLC/ FACTORYVILLE
ICIS-AIR IDPA000770262
EPA facility registry ID110060029259
Operating statusOperating
Emissions classificationMinor source
Current violation status (HPV field)No Violation Identified
AddressBOB HENRY RD, Factoryville, PA 18419
CountyWyoming County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region03

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 31, 2026PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 11, 2026PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 24, 2025FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
August 26, 2025PCE On-Site Monitoring/SamplingStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
January 16, 2025PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
July 18, 2024PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 2, 2024FCE On-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 6, 2024PCE On-Site Monitoring/SamplingStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 5, 2024PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 10, 2022PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 16, 2022PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 19, 2021PCE Off-SiteStateMACT Standards (40 CFR Part 63); New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
July 18, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 6, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 16, 2022Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Enforcement and penalties

1 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
March 24, 2026Administrative OrderState$27,620

Informal enforcement

DateWhat EPA recordedAgency
January 8, 2025Notice of ViolationState
July 30, 2024Notice of ViolationState
March 12, 2024Notice of ViolationState
February 16, 2022Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
January 16, 2025PassState
September 6, 2024FailState
February 1, 2023FailState
January 3, 2020PassState

Watch OXBOW CREEK ENERGY LLC/ FACTORYVILLE

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110060029259).

Other air sources in Pennsylvania beside OXBOW CREEK ENERGY LLC/ FACTORYVILLE

EPA ICIS-AIR download, loaded September 14, 2026.