CANFOR SOUTHERN PINE - CAMDEN PLANT is on EPA’s ICIS-AIR register at 1281 SANDERS CREEK RD, Cassatt in Kershaw County, South Carolina: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 31 events on file is a compliance evaluation dated August 31, 2026.
  • Its events on file run from January 18, 2017 through August 31, 2026.
  • Of the 2 formal enforcement actions on file, 2 carry a filed penalty above zero. The largest on file is $21,700, filed May 5, 2017.
  • Of its 14 compliance evaluations on file, 5 are a full compliance evaluation.
  • 1 of the 5 violation determinations on file is high-priority.
  • The register holds 35 air-emissions sources in Kershaw County, South Carolina.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedCANFOR SOUTHERN PINE - CAMDEN PLANT
ICIS-AIR IDSC00013800025
EPA facility registry ID110000351869
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address1281 SANDERS CREEK RD, Cassatt, SC 29032
CountyKershaw County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Wood product manufacturing (NAICS 3211)
EPA region04

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 31, 2026FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 14, 2026PCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 26, 2025PCE Off-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 19, 2024PCE Off-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
August 13, 2024FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 8, 2024PCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 25, 2024PCE Off-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 28, 2024PCE Off-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 21, 2022FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 1, 2022PCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
November 8, 2019FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
October 29, 2019PCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 20, 2018FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 28, 2018PCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
March 26, 2025Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 30, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 29, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
April 2, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 22, 2017HPV day-zero determinationStateMACT Standards (40 CFR Part 63)

Enforcement and penalties

2 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
June 12, 2025Administrative OrderState$9,850
May 5, 2017Administrative OrderState$21,700

Informal enforcement

DateWhat EPA recordedAgency
March 26, 2025Notice of ViolationState
October 31, 2024Notice of ViolationState
April 14, 2017Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
May 14, 2024PassState
June 8, 2021PassState
October 15, 2020PassState
June 25, 2020PassState
June 19, 2018PassState
June 13, 2017PassState
January 18, 2017PassState

Watch CANFOR SOUTHERN PINE - CAMDEN PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000351869).

Other air sources in South Carolina beside CANFOR SOUTHERN PINE - CAMDEN PLANT

EPA ICIS-AIR download, loaded September 14, 2026.