ICIS-AIR TX0000004824500020

PORT ARTHUR REFINERY, Port Arthur, TX: Clean Air Act compliance record, inspections, violations, penalties

PORT ARTHUR REFINERY is on EPA’s ICIS-AIR register at 2555 SAVANNAH AVE, Port Arthur in Jefferson County, Texas: operating status operating, emissions classification major source, current violation status “Violation w/in 1 Year”. Jefferson County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 272 events on file is a stack test dated October 14, 2026.
  • Of the 14 formal enforcement actions on file, 14 carry a filed penalty above zero. The largest on file is $284,148, filed April 8, 2022.
  • Of its 3 compliance evaluations on file, 2 are a full compliance evaluation.
  • 2 of the 242 stack tests on file are recorded as failed.
  • 1 of the 12 violation determinations on file is high-priority.
  • The register holds 125 air-emissions sources in Jefferson County, Texas.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedPORT ARTHUR REFINERY
ICIS-AIR IDTX0000004824500020
EPA facility registry ID110000464024
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)Violation w/in 1 Year
Address2555 SAVANNAH AVE, Port Arthur, TX 77640
CountyJefferson County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region06

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
March 26, 2025FCE On-SiteStateTitle V Permits
February 19, 2020FCE On-SiteStateTitle V Permits
July 31, 2018PCE Off-SiteU.S. EPAFederally-Enforceable Requirement, Non Specified; New Source Performance Standards

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
August 19, 2026Earliest FRV determinationStateTitle V Permits
May 16, 2025Earliest FRV determinationStateTitle V Permits
January 7, 2025Earliest FRV determinationStateTitle V Permits
August 30, 2022Earliest FRV determinationStateTitle V Permits
April 30, 2020Earliest FRV determinationStateTitle V Permits
February 28, 2020Earliest FRV determinationStateTitle V Permits
October 30, 2019Earliest FRV determinationStateTitle V Permits
August 22, 2019Earliest FRV determinationStateTitle V Permits
February 28, 2019Earliest FRV determinationStateTitle V Permits
May 22, 2018HPV day-zero determinationStateTitle V Permits
April 7, 2017Earliest FRV determinationStateTitle V Permits
January 5, 2017Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

14 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
April 22, 2026Administrative OrderState$14,250
March 18, 2026Administrative OrderState$13,125
May 7, 2025Administrative OrderState$15,000
April 29, 2022Civil Judicial ActionState$271,500
April 8, 2022Administrative OrderState$284,148
June 29, 2021Administrative OrderState$7,125
February 1, 2021Administrative OrderState$34,565
April 27, 2020Administrative OrderState$26,251
November 18, 2019Administrative OrderState$182,314
July 1, 2019Administrative OrderState$32,813
October 8, 2018Administrative OrderState$157,500
February 14, 2018Administrative OrderState$8,000
May 11, 2017Administrative OrderState$20,688
March 29, 2017CAA 113D1 Action For PenaltyU.S. EPA$56,000

Informal enforcement

DateWhat EPA recordedAgency
August 19, 2026Notice of ViolationState

Stack tests

The newest 50 of 242.

DateWhat EPA recordedAgency
October 14, 2026PassState
January 20, 2026PassState
November 14, 2025PassState
November 3, 2025PassState
September 15, 2025PassState
September 3, 2025PassState
August 29, 2025PassState
August 29, 2025PassState
August 28, 2025PassState
August 28, 2025PassState
August 28, 2025PassState
August 27, 2025PassState
August 15, 2025PassState
August 15, 2025PassState
August 15, 2025PassState
August 15, 2025PassState
August 13, 2025PassState
August 13, 2025PassState
April 4, 2025PassState
February 14, 2025PassState
February 14, 2025PassState
February 14, 2025PassState
February 14, 2025PassState
February 13, 2025PassState
February 13, 2025PassState
February 13, 2025PassState
February 13, 2025PassState
December 12, 2024PassState
November 22, 2024PassState
November 4, 2024PassState
October 10, 2024PassState
October 10, 2024PassState
October 7, 2024PassState
August 29, 2024PassState
August 29, 2024PassState
August 23, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
August 22, 2024PassState
June 25, 2024PassState
June 25, 2024PassState
June 25, 2024PassState
June 25, 2024PassState
June 25, 2024PassState
June 25, 2024PassState

Watch PORT ARTHUR REFINERY

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000464024).

Other air sources in Texas beside PORT ARTHUR REFINERY

EPA ICIS-AIR download, loaded September 14, 2026.