ICIS-AIR VA0000005116700003

AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT, Cleveland, VA: Clean Air Act compliance record, inspections, violations, penalties

AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT is on EPA’s ICIS-AIR register at 3464 POWER PLANT RD, Cleveland in Russell County, Virginia: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 120 events on file is a compliance evaluation dated October 20, 2026.
  • Of the 3 formal enforcement actions on file, 3 carry a filed penalty above zero. The largest on file is $26,895, filed June 13, 2023.
  • Of its 105 compliance evaluations on file, 5 are a full compliance evaluation.
  • 2 of the 8 stack tests on file are recorded as failed.
  • 2 of the 2 violation determinations on file are high-priority.
  • The register holds 60 air-emissions sources in Russell County, Virginia.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedAMERICAN ELECTRIC POWER-CLINCH RIVER PLANT
ICIS-AIR IDVA0000005116700003
EPA facility registry ID110000585581
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address3464 POWER PLANT RD, Cleveland, VA 24225
CountyRussell County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region03

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

The newest 50 of 105.

DateWhat EPA recordedAgencyPrograms
October 20, 2026PCE Off-SiteStateTitle V Permits
July 24, 2026PCE Off-SiteStateTitle V Permits
July 14, 2026PCE Off-SiteStateTitle V Permits
June 18, 2026FCE On-SiteStateTitle V Permits
June 15, 2026PCE Off-SiteStateTitle V Permits
May 11, 2026PCE Off-SiteStateTitle V Permits
April 20, 2026PCE Off-SiteStateTitle V Permits
January 21, 2026PCE Off-SiteStateTitle V Permits
January 15, 2026PCE Off-SiteStateTitle V Permits
October 27, 2025PCE Off-SiteStateTitle V Permits
August 22, 2025PCE Off-SiteStateTitle V Permits
August 15, 2025PCE Off-SiteStateTitle V Permits
August 6, 2025PCE Off-SiteStateTitle V Permits
May 5, 2025PCE Off-SiteStateTitle V Permits
February 24, 2025PCE Off-SiteStateTitle V Permits
January 28, 2025PCE Off-SiteStateTitle V Permits
January 16, 2025PCE Off-SiteStateTitle V Permits
August 29, 2024PCE Off-SiteStateTitle V Permits
July 22, 2024PCE Off-SiteStateTitle V Permits
July 3, 2024PCE Off-SiteStateTitle V Permits
May 30, 2024FCE On-SiteStateTitle V Permits
May 9, 2024PCE On-Site CEMS/CMS AuditStateTitle V Permits
May 1, 2024PCE Off-SiteStateTitle V Permits
February 22, 2024PCE Off-SiteStateTitle V Permits
January 25, 2024PCE Off-SiteStateTitle V Permits
October 23, 2023PCE Off-SiteStateTitle V Permits
September 1, 2023PCE Off-SiteStateTitle V Permits
August 31, 2023PCE Off-SiteStateTitle V Permits
June 29, 2023PCE Off-SiteStateTitle V Permits
April 17, 2023PCE Off-SiteStateTitle V Permits
February 28, 2023PCE Off-SiteStateTitle V Permits
January 27, 2023PCE Off-SiteStateTitle V Permits
January 25, 2023PCE Off-SiteStateTitle V Permits
September 6, 2022PCE Off-SiteStateTitle V Permits
August 8, 2022PCE Off-SiteStateTitle V Permits
August 1, 2022PCE Off-SiteStateTitle V Permits
June 30, 2022FCE On-SiteStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
June 6, 2022PCE Off-SiteStateTitle V Permits
March 28, 2022PCE Off-SiteStateTitle V Permits
February 7, 2022PCE Off-SiteStateTitle V Permits
November 30, 2021PCE Off-SiteStateTitle V Permits
August 12, 2021PCE Off-SiteStateTitle V Permits
August 11, 2021PCE Off-SiteStateTitle V Permits
July 9, 2021PCE Off-SiteStateTitle V Permits
April 30, 2021PCE Off-SiteStateTitle V Permits
February 22, 2021PCE Off-SiteStateTitle V Permits
January 29, 2021PCE Off-SiteStateTitle V Permits
October 30, 2020PCE Off-SiteStateTitle V Permits
September 14, 2020PCE Off-SiteStateTitle V Permits
July 28, 2020PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
July 26, 2022HPV day-zero determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
August 13, 2021HPV day-zero determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits

Enforcement and penalties

3 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
June 13, 2023Administrative OrderState$26,895
November 29, 2021Administrative OrderState$18,547
January 17, 2017Administrative OrderState$17,500

Informal enforcement

DateWhat EPA recordedAgency
July 26, 2022Notice of ViolationState
August 13, 2021Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
April 7, 2026PassState
November 21, 2024PassState
June 16, 2023PassState
June 30, 2022PassState
May 12, 2022FailState
July 7, 2021PassState
June 8, 2021FailState
June 7, 2017PassState

Watch AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000585581).

Other air sources in Virginia beside AMERICAN ELECTRIC POWER-CLINCH RIVER PLANT

EPA ICIS-AIR download, loaded September 14, 2026.