ICIS-AIR WA0000005301500003
NIPPON DYNAWAVE PACKAGING COMPANY LLC, Longview, WA: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Major sourceEmissions classification
- Violation w/in 1 YearCurrent violation status, as filed
- 15Compliance evaluations since January 1, 2017
- 4High-priority violations since January 1, 2017
- 10Formal enforcement actions since January 1, 2017
NIPPON DYNAWAVE PACKAGING COMPANY LLC is on EPA’s ICIS-AIR register at 3401 INDUSTRIAL WAY, Longview in Cowlitz County, Washington: operating status operating, emissions classification major source, current violation status “Violation w/in 1 Year”.
What stands out
- The newest of the 245 events on file is a compliance evaluation dated September 16, 2026.
- Of the 10 formal enforcement actions on file, 7 carry a filed penalty above zero. The largest on file is $9,000, filed June 25, 2018.
- Of its 15 compliance evaluations on file, 5 are a full compliance evaluation.
- 3 of the 142 stack tests on file are recorded as failed.
- 4 of the 37 violation determinations on file are high-priority.
- The register holds 17 air-emissions sources in Cowlitz County, Washington.
Every line is computed by formula from the record’s stored figures; nothing is estimated.
Identity
| Facility as filed | NIPPON DYNAWAVE PACKAGING COMPANY LLC |
|---|---|
| ICIS-AIR ID | WA0000005301500003 |
| EPA facility registry ID | 110000490898 |
| Operating status | Operating |
| Emissions classification | Major source |
| Current violation status (HPV field) | Violation w/in 1 Year |
| Address | 3401 INDUSTRIAL WAY, Longview, WA 98632 |
| County | Cowlitz County |
| In a nonattainment county | No (EPA Green Book) |
| Industry (NAICS) | Paper manufacturing (NAICS 3221) |
| SIC code | 2611 |
| EPA region | 10 |
Programs and pollutants
The program, pollutant and Title V files are not loaded: what this page covers.
Compliance evaluations
- 15Evaluations since January 1, 2017
- 5Full compliance evaluations
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| September 16, 2026 | FCE On-Site | State | Title V Permits |
| May 12, 2026 | PCE On-Site | State | MACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| March 24, 2026 | PCE On-Site | State | MACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| October 24, 2024 | PCE On-Site | U.S. EPA | MACT Standards (40 CFR Part 63); New Source Performance Standards; Operating Permits |
| September 10, 2024 | FCE On-Site | State | Title V Permits |
| September 7, 2023 | PCE On-Site | State | Title V Permits |
| September 13, 2022 | FCE On-Site | State | Title V Permits |
| September 9, 2020 | FCE On-Site | State | Title V Permits |
| August 28, 2019 | PCE On-Site | State | Title V Permits |
| September 28, 2018 | FCE On-Site | State | MACT Standards (40 CFR Part 63); New Source Performance Standards; Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| July 10, 2018 | PCE On-Site | State | Title V Permits |
| June 19, 2018 | PCE On-Site | State | Title V Permits |
| May 31, 2018 | PCE On-Site | State | Title V Permits |
| August 29, 2017 | PCE On-Site | State | Title V Permits |
| April 6, 2017 | PCE On-Site | State | Title V Permits |
Violations
- 37Violation determinations since January 1, 2017
- 4Of them high-priority
What high-priority and federally reportable violations mean.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| June 15, 2026 | Earliest FRV determination | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards |
| May 22, 2026 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| May 18, 2026 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 12, 2025 | Earliest FRV determination | State | National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 12, 2025 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality |
| May 13, 2025 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 12, 2024 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| December 6, 2024 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| August 30, 2024 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| June 22, 2023 | Earliest FRV determination | State | Title V Permits |
| April 5, 2023 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| February 16, 2023 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| November 23, 2022 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| September 20, 2022 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| June 21, 2022 | Earliest FRV determination | State | Title V Permits |
| March 29, 2022 | Earliest FRV determination | State | National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); Title V Permits |
| January 18, 2022 | Earliest FRV determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 18, 2021 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| October 18, 2021 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| July 13, 2021 | Earliest FRV determination | State | New Source Performance Standards; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| May 14, 2021 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| June 15, 2020 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| April 15, 2020 | Earliest FRV determination | State | New Source Performance Standards; Title V Permits |
| January 2, 2020 | Earliest FRV determination | State | Title V Permits |
| December 18, 2018 | Earliest FRV determination | State | Title V Permits |
| September 25, 2018 | HPV day-zero determination | State | Title V Permits |
| July 17, 2018 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| July 3, 2018 | HPV day-zero determination | State | State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits |
| January 17, 2018 | HPV day-zero determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| December 19, 2017 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| December 19, 2017 | Earliest FRV determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| November 3, 2017 | HPV day-zero determination | State | MACT Standards (40 CFR Part 63); Title V Permits |
| October 17, 2017 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| August 18, 2017 | Earliest FRV determination | State | Title V Permits |
| June 20, 2017 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| February 21, 2017 | Earliest FRV determination | State | Prevention of Significant Deterioration of Air Quality; Title V Permits |
| January 20, 2017 | Earliest FRV determination | Local | Title V Permits |
Enforcement and penalties
7 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.
| Date | What EPA recorded | Agency | Penalty, as filed |
|---|---|---|---|
| March 17, 2026 | Administrative Order | State | $5,500 |
| August 6, 2024 | Administrative Order | State | $4,500 |
| February 27, 2019 | Administrative Order | State | $5,000 |
| February 1, 2019 | Administrative Order | State | $8,200 |
| August 8, 2018 | Administrative Order | State | $0 |
| June 25, 2018 | Administrative Order | State | $0 |
| June 25, 2018 | Administrative Order | State | $9,000 |
| February 1, 2018 | Administrative Order | State | $2,500 |
| January 24, 2018 | Administrative Order | State | $0 |
| February 3, 2017 | Administrative Order | State | $9,000 |
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| August 26, 2026 | Notice of Violation | State |
| April 10, 2026 | Warning Letter | State |
| January 12, 2026 | Notice of Violation | State |
| October 15, 2025 | Notice of Violation | State |
| September 8, 2025 | Notice of Violation | State |
| July 18, 2024 | Notice of Violation | State |
| July 18, 2024 | Notice of Violation | State |
| March 8, 2024 | Notice of Violation | State |
| February 14, 2023 | Notice of Violation | State |
| February 14, 2023 | Notice of Violation | State |
| January 12, 2023 | Warning Letter | State |
| August 26, 2022 | Notice of Violation | State |
| August 26, 2022 | Notice of Violation | State |
| August 26, 2022 | Notice of Violation | State |
| August 19, 2022 | Notice of Violation | State |
| July 14, 2022 | Notice of Violation | State |
| July 19, 2021 | Notice of Violation | State |
| February 24, 2021 | Notice of Violation | State |
| February 24, 2021 | Notice of Violation | State |
| February 24, 2021 | Notice of Violation | State |
| December 18, 2019 | Notice of Violation | State |
| February 1, 2019 | Notice of Violation | State |
| December 4, 2018 | Notice of Violation | State |
| October 12, 2018 | Notice of Violation | State |
| September 27, 2018 | Notice of Violation | State |
| August 29, 2018 | Notice of Violation | State |
| August 8, 2018 | Notice of Violation | State |
| February 2, 2018 | Notice of Violation | State |
| January 12, 2018 | Notice of Violation | State |
| December 8, 2017 | Notice of Violation | State |
| November 20, 2017 | Notice of Violation | State |
| November 14, 2017 | Notice of Violation | State |
| November 14, 2017 | Warning Letter | State |
| October 12, 2017 | Notice of Violation | State |
| October 5, 2017 | Notice of Violation | State |
| September 11, 2017 | Notice of Violation | State |
| August 2, 2017 | Notice of Violation | State |
| April 14, 2017 | Notice of Violation | State |
| March 15, 2017 | Notice of Violation | State |
| February 9, 2017 | Notice of Violation | State |
| February 9, 2017 | Notice of Violation | State |
Stack tests
- 142Stack tests since January 1, 2017
- 3Recorded as failed
The newest 50 of 142.
| Date | What EPA recorded | Agency |
|---|---|---|
| May 12, 2026 | Pass | State |
| May 12, 2026 | Pass | State |
| March 24, 2026 | Pass | State |
| November 11, 2025 | Pass | State |
| July 11, 2025 | Pass | State |
| July 10, 2025 | Pass | State |
| July 9, 2025 | Pass | State |
| July 8, 2025 | Pass | State |
| May 30, 2025 | Pass | State |
| May 29, 2025 | Pass | State |
| May 29, 2025 | Pass | State |
| May 28, 2025 | Pass | State |
| March 28, 2025 | Pass | State |
| March 26, 2025 | Pass | State |
| March 25, 2025 | Pass | State |
| December 17, 2024 | Pass | State |
| August 8, 2024 | Pass | State |
| August 7, 2024 | Pass | State |
| August 6, 2024 | Pass | State |
| August 5, 2024 | Pass | State |
| May 10, 2024 | Pass | State |
| May 10, 2024 | Pass | State |
| May 10, 2024 | Pass | State |
| May 10, 2024 | Pass | State |
| April 17, 2024 | Pass | State |
| April 16, 2024 | Pass | State |
| February 28, 2024 | Pass | State |
| February 27, 2024 | Pass | State |
| December 1, 2023 | Pass | State |
| November 29, 2023 | Pass | State |
| September 15, 2023 | Pass | State |
| September 14, 2023 | Pass | State |
| September 13, 2023 | Pass | State |
| September 12, 2023 | Pass | State |
| September 11, 2023 | Pass | State |
| May 19, 2023 | Pass | State |
| May 19, 2023 | Pass | State |
| May 19, 2023 | Pass | State |
| May 19, 2023 | Pass | State |
| May 19, 2023 | Pass | State |
| May 18, 2023 | Pass | State |
| March 15, 2023 | Pass | State |
| March 14, 2023 | Pass | State |
| December 21, 2022 | Pass | State |
| December 15, 2022 | Pass | State |
| August 26, 2022 | Pass | State |
| August 25, 2022 | Pass | State |
| August 24, 2022 | Pass | State |
| August 23, 2022 | Pass | State |
| June 8, 2022 | Pass | State |
Watch NIPPON DYNAWAVE PACKAGING COMPANY LLC
Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000490898).
Other air sources in Washington beside NIPPON DYNAWAVE PACKAGING COMPANY LLC
- NORDIC TUGS, INC. BURLINGTON, Skagit County WANCA0005305700050
- NORTH END AUTO BODY TOPPENISH, Yakima County WA00000053077T0067
- NORTH KITSAP LANDSCAPE SUPPLY & RECYCL SUQUAMISH, Kitsap County WA00000053035T0017
- NORTH PACIFIC PAPER CORP. LONGVIEW, Cowlitz County WASWC000530150712
- NORTH STAR CASTEEL PRODUCTS, INC. SEATTLE, King County WAPSC0005303312334
- NORTHSIDE LANDFILL SPOKANE, Spokane County WASPC0005306300125
- NORTHWEST AGGREGATES CO ENUMCLAW, King County WAPSC0005303311929
- NORTHWEST CASTINGS INC SEATTLE, King County WAPSC0000000011659
- NORTHWEST CLOSETS AND WALLBEDS AUBURN, King County WAPSC0005303301015
- NORTHWEST HARDWOODS - CENTRALIA CENTRALIA, Lewis County WASWC0005304100011
- NORTHWEST HARDWOODS / LONGVIEW LONGVIEW, Cowlitz County WASWC0005301500064
- NORTHWEST PAVING OKANOGAN, Okanogan County WA00000053047T0012
- NORTHWEST PIPELINE CORP CHEHALIS CHEHALIS, Lewis County WASWC0005304100051
- NORTHWEST PIPELINE CORP PLYMOUTH PLANT PLYMOUTH, Benton County WABCA0005300500016
- NORTHWEST PIPELINE CORP SUMAS SUMAS, Whatcom County WANCA0005307300031
- NORTHWEST PIPELINE CORP WASHOUGAL WASHOUGAL, Clark County WASWC0005301100144
- NORTHWEST PIPELINE CORP.- WILLARD WILLARD, Skamania County WASWC0005305900015
- NORTHWEST PIPELINE GOLDENDALE GOLDENDALE, Klickitat County WA0000005303900032
- NORTHWEST PIPELINE GP SUMNER SUMNER, Pierce County WAPSC0005305300548
- NORTHWEST PIPELINE LLC SNOHOMISH SNOHOMISH, Snohomish County WAPSC0005306100763
- NORTHWEST PIPELINE LLC- MOUNT VERNON MOUNT VERNON, Skagit County WANCA0005305700044
- NUCOR STEEL SEATTLE INC SEATTLE, King County WAPSC0005303300006
- NUMATIC FINISHING CORPORATION AUBURN, King County WAPSC0005303300081
- NUSTAR TERMINAL OPERATIONS PTSHIP-ANNEX VANCOUVER, Clark County WASWC0005301100151
- NUSTAR TERMINALS SERVICE, INC - MAIN VANCOUVER, Clark County WASWC0005301100068
- NUTRIEN KENNEWICK, Benton County WABCA0005300500002
- OATH HOLDINGS INCORPORATED DATA CENTER QUINCY, Grant County WA0000000005309001
- OCEAN COLD LLC WESTPORT, Grays Harbor County 1000000053027C0001
- OCEAN GOLD SEAFOODS INC - SEAFOOD PROCESSING FACILITY WESTPORT, Grays Harbor County 1000000053027C0002
- OCEANUS PLASTICS, INC. CUSTER, Whatcom County WANCA0005307300060
- OKANOGAN FIRE DEPARTMENT OKANOGAN, Okanogan County 100000005304700022
- OMAK ELEMENTARY SCHOOL OMAK, Okanogan County WA00000053047T0002
- OVERLAKE HOSPITAL MEDICAL CENTER BELLEVUE, King County WAPSC0005303316083
- OYSTER & CLAM VENTURE BELLINGHAM, Whatcom County WA00000053073T0003
- PABCO ROOFING PRODUCTS TACOMA, Pierce County WAPSC0005305310428
- PACCAR TECHNICAL CENTER MOUNT VERNON, Skagit County WANCA0005305700088
- PACE INTERNATIONAL LLC WAPATO, Yakima County WA0000005307700075
- PACIFIC CALCIUM (CAR) TONASKET, Okanogan County WA0000005304700005
- PACIFIC CREST INDUSTRIES, INC. DBA BELLMONT CABINETS COMPANY SUMNER, Pierce County WAPSC0005305328982
- PACIFIC NORTHWEST TERMINALS INC TACOMA, Pierce County WAPSC0005305312230
- PACIFIC PROPELLER INTERNATIONAL LLC KENT, King County WAPSC0005303316088
- PACIFIC TOPSOILS INC WOODINVILLE, Snohomish County WAPSC0000000018478
- PACIFIC TOPSOILS, INC. EVERETT, Snohomish County WAPSC0005306129459
- PACIFIC WOODTECH CORPORATION BURLINGTON, Skagit County WANCA0005305700055
- PACKAGING CORPORATION OF AMERICA WALLULA, Walla Walla County WA0000005307100003
- PANELTECH HOQUIAM, Grays Harbor County WAORC0005302700080
- PAR MONTANA, LLC SPOKANE, Spokane County WASPC0005306300002
- PHILLIPS 66 FERNDALE, Whatcom County WANCA0005307300005
- PHILLIPS 66 COMPANY - RENTON TERMINAL RENTON, King County WAPSC0005303321413
- PHILLIPS 66 COMPANY - TACOMA TERMINAL TACOMA, Pierce County WAPSC0005305320939
- PHILLIPS 66 COMPANY (PARKWATER) SPOKANE, Spokane County WASPC0005306300001
- PIERCE CO RECYCLING COMPOSTING AND DISPOSAL LLC PUYALLUP, Pierce County WAPSC0005305300097
- PIERCE CO RECYCLING COMPOSTING AND DISPOSAL, LLC DBA LRI GRAHAM, Pierce County WAPSC0005305311993
- PONDERAY NEWSPRINT CO USK, Pend Oreille County WA0000005305100003
- PORT OF LONGVIEW LONGVIEW, Cowlitz County WASWC0005301500059
- PORT ORCHARD SAND & GRAVEL SIDNEY PORT ORCHARD, Kitsap County WAPSC0000000012615
- PORT TOWNSEND PAPER CORPORATION PORT TOWNSEND, Jefferson County WA0000005303100001
- POST POINT WWTP SEWAGE SLUDGE INCINERATOR WHATCOM COUNTY, Whatcom County WANCA1318
- POWERSCREEN OF WASHINGTON KENT, King County WAPSC0005306129051
- PRAIRIE GRAIN, INC. TEKOA, Whitman County WA00000053075T0001