Clean Air Act stationary source · ICIS-AIR WAPSC0000000025994
CEDAR GROVE COMPOST CO, Maple Valley, WA: Clean Air Act compliance record, inspections, violations, penalties
- OperatingOperating status
- Minor sourceEmissions classification
- No Violation IdentifiedCurrent violation status, as filed
- 844Compliance evaluations since January 1, 2017
- 0High-priority violations since January 1, 2017
- 7Formal enforcement actions since January 1, 2017
CEDAR GROVE COMPOST CO, at 17825 CEDAR GROVE RD, Maple Valley in King County, Washington, is an operating minor source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “No Violation Identified”. King County is on EPA’s Green Book list of areas that do not meet a national air quality standard. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.
Identity
| Facility as filed | CEDAR GROVE COMPOST CO |
|---|---|
| ICIS-AIR ID | WAPSC0000000025994 |
| EPA facility registry ID | 110005405285 |
| Operating status | Operating |
| Emissions classification | Minor source |
| Current violation status (ICIS-AIR high-priority violation field) | No Violation Identified |
| Address | 17825 CEDAR GROVE RD, Maple Valley, WA 98038 |
| County | King County |
| In a nonattainment county | Yes (EPA Green Book) |
| Industry (NAICS) | Chemical manufacturing (NAICS 3253) |
| EPA region | 10 |
| Local air agency | Puget Sound Clean Air Agency |
Cited to the EPA ICIS-AIR facility file (ECHO download).
Programs and pollutants
Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs CEDAR GROVE COMPOST CO is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.
Compliance evaluations
- 844Evaluations since January 1, 2017
- 0Full compliance evaluations
The newest 50 of 844.
| Date | What EPA recorded | Agency | Programs |
|---|---|---|---|
| July 21, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| July 9, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| June 24, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 11, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| May 8, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| March 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| March 13, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| March 13, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| February 27, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 19, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| February 19, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 18, 2026 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
| February 5, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| January 26, 2026 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| December 16, 2025 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| December 16, 2025 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| December 12, 2025 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| November 20, 2025 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| November 20, 2025 | PCE Off-Site | Local | MACT Standards (40 CFR Part 63) |
| October 24, 2025 | PCE On-Site Record/Report Review | Local | MACT Standards (40 CFR Part 63) |
Violations
- 0Violation determinations since January 1, 2017
- 0Of them high-priority
A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.
EPA’s violation history file holds no violation for ICIS-AIR WAPSC0000000025994 since January 1, 2017.
Enforcement and penalties
7 formal enforcement actions since January 1, 2017, 5 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.
| Date | What EPA recorded | Agency | Penalty, as filed |
|---|---|---|---|
| December 2, 2020 | Administrative Order | Local | $12,000 |
| December 2, 2020 | Administrative Order | Local | $12,000 |
| March 4, 2020 | Administrative Order | Local | $12,000 |
| March 4, 2020 | Administrative Order | Local | $0 |
| March 4, 2020 | Administrative Order | Local | $12,000 |
| March 4, 2020 | Administrative Order | Local | $12,000 |
| March 4, 2020 | Administrative Order | Local | $0 |
Informal enforcement
| Date | What EPA recorded | Agency |
|---|---|---|
| June 30, 2026 | Notice of Violation | Local |
| June 30, 2026 | Notice of Violation | Local |
| March 11, 2026 | Notice of Violation | Local |
| March 11, 2026 | Notice of Violation | Local |
| March 11, 2026 | Notice of Violation | Local |
| March 11, 2026 | Notice of Violation | Local |
| October 29, 2025 | Warning Letter | Local |
| September 12, 2025 | Warning Letter | Local |
| July 14, 2025 | Notice of Violation | Local |
| January 8, 2025 | Notice of Violation | Local |
| December 26, 2024 | Notice of Violation | Local |
| November 7, 2024 | Notice of Violation | Local |
| May 31, 2024 | Notice of Violation | Local |
| September 29, 2023 | Notice of Violation | Local |
| July 6, 2023 | Notice of Violation | Local |
| April 20, 2023 | Notice of Violation | Local |
| February 21, 2023 | Notice of Violation | Local |
| February 21, 2023 | Notice of Violation | Local |
| February 17, 2023 | Notice of Violation | Local |
| June 24, 2022 | Warning Letter | Local |
| September 14, 2021 | Notice of Violation | Local |
| August 2, 2021 | Notice of Violation | Local |
| June 15, 2021 | Notice of Violation | State |
| March 22, 2021 | Notice of Violation | Local |
| July 24, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 20, 2020 | Notice of Violation | Local |
| July 2, 2020 | Notice of Violation | Local |
| March 12, 2020 | Notice of Violation | Local |
| February 28, 2020 | Notice of Violation | Local |
| February 27, 2020 | Notice of Violation | Local |
| February 24, 2020 | Warning Letter | Local |
Stack tests
- 31Stack tests since January 1, 2017
- 26Recorded as failed
| Date | What EPA recorded | Agency |
|---|---|---|
| February 20, 2026 | Pass | Local |
| February 20, 2026 | Pass | Local |
| October 6, 2025 | Pass | Local |
| October 6, 2025 | Pass | Local |
| February 3, 2025 | Fail | Local |
| February 3, 2025 | Fail | Local |
| November 6, 2024 | Fail | Local |
| November 6, 2024 | Fail | Local |
| August 7, 2024 | Fail | Local |
| August 7, 2024 | Fail | Local |
| May 8, 2024 | Fail | Local |
| May 8, 2024 | Fail | Local |
| February 7, 2024 | Fail | Local |
| February 7, 2024 | Fail | Local |
| November 8, 2023 | Fail | Local |
| November 8, 2023 | Fail | Local |
| August 3, 2023 | Pass | Local |
| August 2, 2023 | Fail | Local |
| May 10, 2023 | Fail | Local |
| May 10, 2023 | Fail | Local |
| February 20, 2023 | Fail | Local |
| December 6, 2022 | Fail | Local |
| August 10, 2022 | Fail | Local |
| May 4, 2022 | Fail | Local |
| February 9, 2022 | Fail | Local |
| November 2, 2021 | Fail | Local |
| August 3, 2021 | Fail | Local |
| May 4, 2021 | Fail | Local |
| February 2, 2021 | Fail | Local |
| November 10, 2020 | Fail | Local |
| August 6, 2020 | Fail | Local |
Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.
Watch this source
One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, WAPSC0000000025994.
Start the watch
- One source — $99/month
- One county — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110005405285 there.
Nearby on the register
- Air-emissions sources in King County
- Every source record in King County, A to Z
- Air-emissions sources in Washington
- Every source record in Washington, A to Z
Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.