ARDAGH GLASS INC, Burlington, WI: Clean Air Act compliance record, inspections, violations, penalties

ARDAGH GLASS INC is on EPA’s ICIS-AIR register at 815 MCHENRY ST, Burlington in Richland County, Wisconsin: operating status operating, emissions classification major source, current violation status “Violation w/in 1 Year”.

What stands out

  • The newest of the 60 events on file is a compliance evaluation dated October 30, 2026.
  • Its events on file run from April 25, 2017 through October 30, 2026.
  • Of the 1 formal enforcement action on file, 0 carry a filed penalty above zero.
  • Of its 21 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 15 air-emissions sources in Richland County, Wisconsin.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedARDAGH GLASS INC
ICIS-AIR IDWI0000005510100022
EPA facility registry ID110040969805
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)Violation w/in 1 Year
Address815 MCHENRY ST, Burlington, WI 531058797
CountyRichland County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Nonmetallic mineral product manufacturing (NAICS 3272)
SIC code3221
EPA region05

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
October 30, 2026PCE Off-SiteStateTitle V Permits
August 10, 2026PCE Off-SiteStateTitle V Permits
August 10, 2026PCE Off-SiteStateTitle V Permits
July 6, 2026FCE On-SiteStateTitle V Permits
June 24, 2026PCE Off-SiteStateTitle V Permits
November 3, 2025PCE Off-SiteStateTitle V Permits
May 29, 2025PCE Off-SiteStateTitle V Permits
February 7, 2025PCE Off-SiteStateTitle V Permits
February 7, 2025PCE Off-SiteStateTitle V Permits
December 7, 2024PCE Off-SiteU.S. EPAMACT Standards (40 CFR Part 63)
November 8, 2024PCE Off-SiteStateTitle V Permits
September 27, 2024PCE Off-SiteStateTitle V Permits
September 27, 2024PCE Off-SiteStateTitle V Permits
July 29, 2024FCE On-SiteStateTitle V Permits
February 6, 2024PCE Off-SiteU.S. EPAMACT Standards (40 CFR Part 63)
November 10, 2022PCE Off-SiteStateMACT Standards (40 CFR Part 63); State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards; Title V Permits
November 3, 2022PCE Off-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 26, 2022FCE On-SiteStateTitle V Permits
August 18, 2020FCE On-SiteStateTitle V Permits
November 15, 2018PCE On-SiteU.S. EPAState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 18, 2018FCE On-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
May 15, 2026Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 15, 2026Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 15, 2026Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 15, 2026Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
May 29, 2024Earliest FRV determinationStateTitle V Permits
May 29, 2024Earliest FRV determinationStateMACT Standards (40 CFR Part 63)
May 29, 2024Earliest FRV determinationStateTitle V Permits
May 29, 2024Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
February 20, 2023Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
April 30, 2019Civil Judicial ActionU.S. EPA$0

Informal enforcement

DateWhat EPA recordedAgency
July 13, 2026Warning LetterState
October 30, 2024Notice of ViolationState
June 9, 2023Warning LetterState

Stack tests

DateWhat EPA recordedAgency
June 2, 2026PassState
April 9, 2026N/AState
November 4, 2025PassState
June 10, 2025PassState
April 2, 2025PassState
December 3, 2024PassState
October 15, 2024PassState
August 27, 2024PassState
May 30, 2024PassState
December 19, 2023PassState
September 6, 2023N/AState
June 20, 2023PassState
November 1, 2022PassState
September 19, 2022PassState
June 13, 2022PassState
October 18, 2021PassState
June 16, 2021PassState
April 6, 2021PassState
June 16, 2020PassState
October 23, 2019PassState
June 11, 2019PassState
June 13, 2018PassState
June 12, 2018PassState
February 23, 2018N/AState
April 26, 2017PassState
April 25, 2017PassState

Watch ARDAGH GLASS INC

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110040969805).

Other air sources in Wisconsin beside ARDAGH GLASS INC

EPA ICIS-AIR download, loaded September 14, 2026.