ICIS-AIR WY0000005600300015

LOVELL GRINDING PLANT (BENTONITE PERFORMANCE MINERALS), Lovell, WY: Clean Air Act compliance record, inspections, violations, penalties

LOVELL GRINDING PLANT (BENTONITE PERFORMANCE MINERALS) is on EPA’s ICIS-AIR register at 789 HIGHWAY 14A EAST, Lovell in Big Horn County, Wyoming: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 23 events on file is a stack test dated September 9, 2026.
  • Its events on file run from August 15, 2017 through September 9, 2026.
  • Of the 1 formal enforcement action on file, 0 carry a filed penalty above zero.
  • All 5 of its compliance evaluations on file are full compliance evaluations.
  • 1 of the 15 stack tests on file is recorded as failed.
  • 1 of the 1 violation determinations on file is high-priority.
  • The register holds 15 air-emissions sources in Big Horn County, Wyoming.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedLOVELL GRINDING PLANT (BENTONITE PERFORMANCE MINERALS)
ICIS-AIR IDWY0000005600300015
EPA facility registry ID110007347004
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address789 HIGHWAY 14A EAST, Lovell, WY 82431
CountyBig Horn County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Mining and quarrying (NAICS 2123)
SIC code1459
EPA region08

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 20, 2025FCE On-SiteStateTitle V Permits
July 18, 2023FCE On-SiteStateTitle V Permits
August 3, 2021FCE On-SiteStateTitle V Permits
August 21, 2019FCE On-SiteStateTitle V Permits
August 15, 2017FCE On-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
May 12, 2020HPV day-zero determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

DateWhat EPA recordedAgencyPenalty, as filed
November 10, 2020Civil Judicial ActionState$0

Informal enforcement

DateWhat EPA recordedAgency
July 2, 2020Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
September 9, 2026PassState
September 9, 2026PassState
January 9, 2023PassState
November 3, 2022PassState
October 6, 2021PassState
July 13, 2021PassState
November 18, 2020PassState
May 6, 2020PassState
March 26, 2020PassState
March 26, 2020PassState
March 26, 2020PassState
March 26, 2020FailState
October 23, 2019PassState
September 5, 2018PassState
September 15, 2017PassState

Watch LOVELL GRINDING PLANT (BENTONITE PERFORMANCE MINERALS)

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110007347004).

Other air sources in Wyoming beside LOVELL GRINDING PLANT (BENTONITE PERFORMANCE MINERALS)

EPA ICIS-AIR download, loaded September 14, 2026.