EPA Air · stack tests by county and year
Air-emissions stack tests in Anchorage Municipality County, Alaska, 2023
- 15Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Anchorage Municipality County, Alaska during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Anchorage Municipality County facility page.
Anchorage Municipality County, Alaska, 2023
Air-emissions stack tests in Anchorage Municipality County, other years
Air-emissions stack tests recorded in Anchorage Municipality County, Alaska, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-08-22 | CHUGACH ELECTRIC ASSOCIATION / HANK NIKKELS PLANT ONE | Pass | State |
| 2023-07-27 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-27 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-26 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-26 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-25 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-25 | CHUGACH ELECTRIC ASSOCIATION / INTERNATIONAL STATION POWER PLANT | Pass | State |
| 2023-07-20 | GRANITE CONSTRUCTION COMPANY / X700 GENCOR/BARBER GREENE ASPHALT PLANT | Pass | State |
| 2023-06-30 | DOYON UTILITIES, LLC / DU-JBER-ELECTRIC, GAS, DRINKING WATER A | Pass | State |
| 2023-06-08 | ANCHORAGE WATER & WASTEWATER UTILITY / JOHN M. ASPLUND WATER POLLUTION CONTROL | Pass | State |
| 2023-06-06 | MATANUSKA ELECTRIC ASSOCIATION, INC / EKLUTNA GENERATION STATION | Pass | State |
| 2023-06-06 | MATANUSKA ELECTRIC ASSOCIATION, INC / EKLUTNA GENERATION STATION | Pass | State |
| 2023-05-23 | DOYON UTILITIES, LLC / DU-JBER-ELECTRIC, GAS, DRINKING WATER A | Pass | State |
| 2023-03-15 | CHUGACH ELECTRIC ASSOCIATION / GEORGE SULLIVAN PLANT TWO | Pass | State |
| 2023-03-14 | CHUGACH ELECTRIC ASSOCIATION / GEORGE SULLIVAN PLANT TWO | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.