EPA Air · stack tests by county and year
Air-emissions stack tests in Kenai Peninsula County, Alaska, 2021
- 29Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Kenai Peninsula County, Alaska during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Kenai Peninsula County facility page.
Kenai Peninsula County, Alaska, 2021
Air-emissions stack tests in Kenai Peninsula County, other years
Air-emissions stack tests recorded in Kenai Peninsula County, Alaska, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-11-16 | HILCORP ALASKA, LLC / PLATFORM A — high-priority violation on file | Pass | State |
| 2021-08-03 | TESORO LOGISTICS OPERATIONS, LLC / NIKISKI TERMINAL | Pass | State |
| 2021-07-16 | COLASKA INC, DBA QAP / CEDAR RAPIDS ASPHALT PLANT | Pass | State |
| 2021-07-10 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-07-09 | HILCORP ALASKA, LLC / BELUGA RIVER UNIT — high-priority violation on file | Pass | State |
| 2021-06-17 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-17 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-17 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-17 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-16 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-14 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-14 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-12 | TESORO ALASKA COMPANY, LLC / KENAI REFINERY — high-priority violation on file | Pass | State |
| 2021-06-10 | HILCORP ALASKA, LLC / BEAVER CREEK PRODUCTION FACILITY | Pass | State |
| 2021-04-30 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / BERNICE LAKE COMBUSTION TURBINE (BCT) P | Pass | State |
| 2021-04-30 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / BERNICE LAKE COMBUSTION TURBINE (BCT) P | Pass | State |
| 2021-04-23 | HILCORP ALASKA, LLC / STEELHEAD PLATFORM | Pass | State |
| 2021-04-21 | HILCORP ALASKA, LLC / TYONEK PLATFORM | Pass | State |
| 2021-04-21 | HILCORP ALASKA, LLC / TYONEK PLATFORM | Pass | State |
| 2021-04-21 | HILCORP ALASKA, LLC / TYONEK PLATFORM | Pass | State |
| 2021-04-21 | HILCORP ALASKA, LLC / TYONEK PLATFORM | Pass | State |
| 2021-03-18 | HILCORP ALASKA, LLC / DOLLY VARDEN PLATFORM — high-priority violation on file | Pass | State |
| 2021-02-11 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / NIKISKI COMBINED CYCLE PLANT | Pass | State |
| 2021-02-11 | ALASKA ELECTRIC AND ENERGY COOPERATIVE / NIKISKI COMBINED CYCLE PLANT | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.