Air-emissions stack tests in North Slope County, Alaska, 2019
- 21Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in North Slope County, Alaska during 2019. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the North Slope County facility page.
North Slope County, Alaska, 2019
Air-emissions stack tests in North Slope County, other years
Air-emissions stack tests recorded in North Slope County, Alaska, 2019
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2019-11-20 | BARROW UTILITIES & ELECTRIC COOPERATIV / BARROW POWER PLANT | Pass | State |
| 2019-10-26 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | Pass | State |
| 2019-10-26 | HILCORP ALASKA, LLC / GATHERING CENTER #2 (GC 2) | Pass | State |
| 2019-10-25 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-10-24 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-10-23 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-10-21 | HILCORP ALASKA, LLC / MILNE POINT PRODUCTION FACILITY (MPU) | Pass | State |
| 2019-09-07 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | Pass | State |
| 2019-09-06 | HILCORP ALASKA, LLC / CENTRAL COMPRESSOR PLANT (CCP) | Pass | State |
| 2019-08-04 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | Pass | State |
| 2019-08-03 | SAVANT ALASKA LLC / BADAMI DEVELOPMENT FACILITY — high-priority violation on file | Pass | State |
| 2019-07-24 | HILCORP ALASKA, LLC / PRUDHOE BAY OPERATIONS CENTER / MAIN CO | Pass | State |
| 2019-04-26 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-04-25 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-04-24 | HILCORP ALASKA, LLC / ENDICOTT PRODUCTION FACILITY (END) | Pass | State |
| 2019-04-21 | HILCORP ALASKA, LLC / NORTHSTAR PRODUCTION FACILITY (NOR) | Pass | State |
| 2019-04-14 | HILCORP ALASKA, LLC / LISBURNE PRODUCTION CENTER (LPC) | Pass | State |
| 2019-03-20 | ALYESKA PIPELINE SERVICE COMPANY / PS #04, TAPS PUMP STATION | N/A | State |
| 2019-03-20 | ALYESKA PIPELINE SERVICE COMPANY / PS #04, TAPS PUMP STATION | Pass | State |
| 2019-01-19 | TDX NORTH SLOPE GENERATING, LLC / TNSG SOUTH PLANT | Pass | State |
| 2019-01-18 | TDX NORTH SLOPE GENERATING, LLC / TNSG SOUTH PLANT | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.