EPA Air · stack tests by county and year
Air-emissions stack tests in Mississippi County, Arkansas, 2024
- 35Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row below is one stack test recorded against a source in Mississippi County, Arkansas during 2024. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Mississippi County facility page.
Mississippi County, Arkansas, 2024
- Inspections 22
Air-emissions stack tests in Mississippi County, other years
Air-emissions stack tests recorded in Mississippi County, Arkansas, 2024
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2024-12-20 | NUCOR YAMATO STEEL COMPANY | Pass | State |
| 2024-10-29 | PLUM POINT SERVICES COMPANY, LLC - PLUM POINT ENERGY STATION | Pass | State |
| 2024-10-17 | BIG RIVER STEEL LLC | Pass | State |
| 2024-10-13 | NUCOR YAMATO STEEL COMPANY | Pass | State |
| 2024-10-12 | NUCOR YAMATO STEEL COMPANY | Pass | State |
| 2024-09-11 | PLUM POINT SERVICES COMPANY, LLC - PLUM POINT ENERGY STATION | Pass | State |
| 2024-08-28 | BIG RIVER STEEL LLC | Pass | State |
| 2024-08-16 | EXPLORATORY VENTURES, LLC. | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-08-01 | MID-CONTINENT COAL AND COKE COMPANY | Pass | State |
| 2024-06-20 | PLUM POINT SERVICES COMPANY, LLC - PLUM POINT ENERGY STATION | Pass | State |
| 2024-06-19 | PLUM POINT SERVICES COMPANY, LLC - PLUM POINT ENERGY STATION | Pass | State |
| 2024-06-04 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-06-04 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-06-04 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-05-16 | ASSOCIATED ELECTRIC COOPERATIVE, INC. - DELL POWER PLANT | Pass | State |
| 2024-03-26 | BIG RIVER STEEL LLC | Pass | State |
| 2024-03-14 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-03-14 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-03-14 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-03-07 | BIG RIVER STEEL LLC | Pass | State |
| 2024-03-07 | BIG RIVER STEEL LLC | Pass | State |
| 2024-03-07 | BIG RIVER STEEL LLC | Pass | State |
| 2024-02-27 | PLUM POINT SERVICES COMPANY, LLC - PLUM POINT ENERGY STATION | Pass | State |
| 2024-02-15 | NUCOR YAMATO STEEL COMPANY | Pass | State |
| 2024-02-02 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-02-01 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-01-30 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-01-30 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-01-30 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
| 2024-01-30 | NUCOR CORPORATION - NUCOR STEEL, ARKANSAS | Pass | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.