Utilities (NAICS 2211): stack tests in Arizona, 2020

A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2020 at a Arizona source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.

Utilities (NAICS 2211) in Arizona, other years

Other industries in Arizona, 2020

Air-emissions stack tests recorded in Arizona, 2020

DateFacilityWhereKindAgency
2020-12-15APS WEST PHX POWER PLANTMARICOPA COUNTY, Maricopa, AZPassLocal
2020-12-02APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState
2020-10-06SOLANA GENERATING STATIONMARICOPA COUNTY, Maricopa, AZPassLocal
2020-08-27SOLANA GENERATING STATIONMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-08-20APS REDHAWK GENERATING FACILITYMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-08-20ARLINGTON VALLEY — high-priority violation on fileMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-08-19NOVO BIOPOWER, LLCSNOWFLAKE, Navajo, AZPassState
2020-08-19VALENCIA POWER PLANTNOGALES, Santa Cruz, AZPassState
2020-08-12APACHE GENERATING STATIONCOCHISE, Cochise, AZPendingState
2020-08-12APS WEST PHX POWER PLANTMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-07-15APS WEST PHX POWER PLANTMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-07-15SALT RIVER PROJECT - AGUA FRIA GENERATING STATIONMARICOPA COUNTY, Maricopa, AZPassLocal
2020-06-18CHOLLA GENERATING STATIONJOSEPH CITY, Navajo, AZPassState
2020-06-15CORONADO GENERATING PLANTSAINT JOHNS, Apache, AZPassState
2020-06-11TUCSON ELECTRIC POWER-IRVINGTONTUCSON, Pima, AZPassLocal
2020-06-11TUCSON ELECTRIC POWER-IRVINGTONTUCSON, Pima, AZPassLocal
2020-06-09UNS ELECTRIC INC - BLACK MOUNTAIN GENERATING STATIONGRIFFITH, Mohave, AZPassState
2020-06-07TUCSON ELECTRIC POWER - SPRINGERVILLE GENERATING STATIONSPRINGERVILLE, Apache, AZPassState
2020-06-03TUCSON ELECTRIC POWER - SPRINGERVILLE GENERATING STATIONSPRINGERVILLE, Apache, AZPassState
2020-06-02YUMA COGENERATION ASSOCIATESYUMA, Yuma, AZPassState
2020-06-02SALT RIVER PROJECT - KYRENE GENERATING STATION — high-priority violation on fileMARICOPA COUNTY, Maricopa, AZPassLocal
2020-05-22APS OCOTILLO POWER PLANTMARICOPA COUNTY, Maricopa, AZPassLocal
2020-05-07SALT RIVER PROJECT - SANTAN GENERATING STATIONMARICOPA COUNTY, Maricopa, AZPassLocal
2020-04-21MESQUITE GENERATING STATIONMARICOPA COUNTY, Maricopa, AZPassLocal
2020-04-17GILA RIVER POWER STATION — high-priority violation on fileMARICOPA COUNTY, Maricopa, AZPendingLocal
2020-04-14APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState
2020-02-27APS OCOTILLO POWER PLANTMARICOPA COUNTY, Maricopa, AZPassLocal
2020-02-12APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState
2020-01-29APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState
2020-01-03APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState
2020-01-03APACHE GENERATING STATIONCOCHISE, Cochise, AZPassState

Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.