- 24Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2026 at a Kansas source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Kansas, other years
Other industries in Kansas, 2026
- Mining and quarrying (NAICS 2123) 11
- Pipeline transportation (NAICS 4862) 7
- Oil and gas extraction (NAICS 2111) 5
- Chemical manufacturing (NAICS 3251) 4
- Nonmetallic mineral product manufacturing (NAICS 3273) 3
Air-emissions stack tests recorded in Kansas, 2026
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2026-08-12 | SABETHA MUN. POWER PLANT (AIR) | SABETHA, Nemaha, KS | Pass | State |
| 2026-07-16 | ARK VALLEY ELECTRIC CO-OP - ARLINGTON SUBSTATION (AIR) | ARLINGTON, Reno, KS | Pass | State |
| 2026-07-14 | KMEA - JAMESON ENERGY CENTER (AIR) | GARDEN CITY, Finney, KS | Pass | State |
| 2026-06-25 | OSAGE CITY MUN. POWER PLANT (AIR) | OSAGE CITY, Osage, KS | Pass | State |
| 2026-06-16 | BALDWIN CITY MUN. POWER PLANT #2 (AIR) | BALDWIN CITY, Douglas, KS | Pass | State |
| 2026-05-05 | HORTON MUN. POWER PLANT (AIR) | HORTON, Brown, KS | Pass | State |
| 2026-04-30 | IOLA MUN. POWER PLANT #1 (AIR) | IOLA, Allen, KS | Pass | State |
| 2026-04-17 | HEARTLAND RURAL ELECTRIC - COLUMBUS SUBSTATION | COLUMBUS, Cherokee, KS | Pass | State |
| 2026-04-17 | HEARTLAND RURAL ELECTRIC - WEIR | WEIR, Cherokee, KS | Pass | State |
| 2026-04-17 | HEARTLAND RURAL ELECTRIC - GREENBUSH | GIRARD, Crawford, KS | Pass | State |
| 2026-04-17 | HEARTLAND RURAL ELECTRIC - WALNUT | WALNUT, Crawford, KS | Pass | State |
| 2026-04-17 | HEARTLAND RURAL ELECTRIC - PWWSD13 | MOUND CITY, Linn, KS | Pass | State |
| 2026-04-08 | OSBORNE MUN. POWER PLANT (AIR) | OSBORNE, Osborne, KS | Pass | State |
| 2026-04-08 | SHARON SPRINGS MUN. POWER PLANT (AIR) | SHARON SPRINGS, Wallace, KS | Pass | State |
| 2026-03-19 | HUGOTON MUN. POWER PLANT #2 (AIR) | HUGOTON, Stevens, KS | Pass | State |
| 2026-03-04 | KANSAS CITY BPU - NEARMAN (AIR) | KANSAS CITY, Wyandotte, KS | Pass | State |
| 2026-02-26 | LACROSSE MUN. POWER PLANT (AIR) | LA CROSSE, Rush, KS | Pass | State |
| 2026-02-25 | KINGMAN MUN. POWER PLANT (AIR) | KINGMAN, Kingman, KS | Pass | State |
| 2026-02-22 | EVERGY, INC. - JEFFREY ENERGY CENTER (AIR) | ST. MARY'S, Pottawatomie, KS | Pass | State |
| 2026-01-13 | EVERGY, INC. - JEFFREY ENERGY CENTER (AIR) | ST. MARY'S, Pottawatomie, KS | Pass | State |
| 2026-01-09 | EVERGY, INC. - JEFFREY ENERGY CENTER (AIR) | ST. MARY'S, Pottawatomie, KS | Pass | State |
| 2026-01-07 | MIDWEST ENERGY - HAYS (GOODMAN ENERGY CENTER)(AIR) | HAYS, Ellis, KS | Pass | State |
| 2026-01-07 | EVERGY, INC. - JEFFREY ENERGY CENTER (AIR) | ST. MARY'S, Pottawatomie, KS | Pass | State |
| 2026-01-06 | EVERGY, INC. - JEFFREY ENERGY CENTER (AIR) | ST. MARY'S, Pottawatomie, KS | Pass | State |
Primary NAICS code as filed on the facility record; dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.