EPA Air · stack tests by state and year
Air-emissions stack tests in Missouri, 2018
- 414Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Every stack test below was recorded against a source in Missouri during 2018; one facility can appear more than once, because this is a record of what happened rather than a list of places.
Counties in Missouri, 2018
- Jackson County 39
- Ste. Genevieve County 36
- Stoddard County 35
- Buchanan County 30
- Greene County 21
- Franklin County 20
- Jasper County 19
- Randolph County 17
- St. Louis County 16
- Dent County 15
- Cape Girardeau County 15
- New Madrid County 12
- Boone County 11
- Platte County 11
- Jefferson County 11
- Scott County 9
- Clay County 9
- Marion County 9
- St. Louis (city) County 9
- Cass County 8
- Barton County 8
- St. Charles County 7
- Holt County 6
- Montgomery County 5
- Ralls County 4
- Pettis County 4
- Cole County 4
Missouri, other years
Air-emissions stack tests recorded in Missouri, 2018
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2018-04-26 | PANHANDLE EASTERN PIPELINE CO - HOUSTONIA | LA MONTE, Pettis, MO | Pending | State |
| 2018-04-26 | METROPOLITAN ST. LOUIS SEWER DISTRICT | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-25 | DOE RUN CO-BUICK RESOURCE RECYCLING FCLT | BOSS, Dent, MO | Pending | State |
| 2018-04-25 | DOE RUN CO-BUICK RESOURCE RECYCLING FCLT | BOSS, Dent, MO | Pending | State |
| 2018-04-25 | BLUE RIVER WASTEWATER TREATMENT PLANT | KANSAS CITY, Jackson, MO | Fail | State |
| 2018-04-25 | BLUE RIVER WASTEWATER TREATMENT PLANT | KANSAS CITY, Jackson, MO | Pass | State |
| 2018-04-25 | METROPOLITAN ST. LOUIS SEWER DISTRICT | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-24 | FOREST CITY FACILITY, LLC | FOREST CITY, Holt, MO | Pending | State |
| 2018-04-24 | FOREST CITY FACILITY, LLC | FOREST CITY, Holt, MO | Pending | State |
| 2018-04-24 | FOREST CITY FACILITY, LLC | FOREST CITY, Holt, MO | Pending | State |
| 2018-04-24 | FOREST CITY FACILITY, LLC | FOREST CITY, Holt, MO | Pending | State |
| 2018-04-24 | FOREST CITY FACILITY, LLC | FOREST CITY, Holt, MO | Pending | State |
| 2018-04-24 | AMEREN MISSOURI MERAMEC ENERGY CENTER | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-20 | JOPLIN STONE | JOPLIN, Jasper, MO | Pass | State |
| 2018-04-19 | PROCTER & GAMBLE PAPER PRODUCTS COMPANY | JACKSON, Cape Girardeau, MO | Pending | State |
| 2018-04-19 | PROCTER & GAMBLE PAPER PRODUCTS COMPANY | JACKSON, Cape Girardeau, MO | Pending | State |
| 2018-04-18 | PROCTER & GAMBLE PAPER PRODUCTS COMPANY | JACKSON, Cape Girardeau, MO | Pending | State |
| 2018-04-18 | PROCTER & GAMBLE PAPER PRODUCTS COMPANY | JACKSON, Cape Girardeau, MO | Pending | State |
| 2018-04-18 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pass | State |
| 2018-04-17 | PROCTER & GAMBLE PAPER PRODUCTS COMPANY | JACKSON, Cape Girardeau, MO | Pending | State |
| 2018-04-17 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pending | State |
| 2018-04-17 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2018-04-17 | AMEREN MISSOURI MERAMEC ENERGY CENTER | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-12 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2018-04-11 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2018-04-11 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2018-04-11 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2018-04-11 | AMEREN MISSOURI MERAMEC ENERGY CENTER | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-10 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2018-04-10 | AMEREN MISSOURI MERAMEC ENERGY CENTER | SAINT LOUIS COUNTY, St. Louis, MO | Pending | State |
| 2018-04-06 | PANHANDLE EASTERN PIPELINE CO - HOUSTONIA | LA MONTE, Pettis, MO | Pending | State |
| 2018-04-06 | PANHANDLE EASTERN PIPELINE CO - HOUSTONIA | LA MONTE, Pettis, MO | Pending | State |
| 2018-04-05 | CENTRAL STONE COMPANY EDINA QUARRY-KC01 | EDINA, Knox, MO | Pass | State |
| 2018-04-04 | BUZZI UNICEM USA, MIDWEST DIV | CAPE GIRARDEAU, Cape Girardeau, MO | Pending | State |
| 2018-04-04 | BUZZI UNICEM USA, MIDWEST DIV | CAPE GIRARDEAU, Cape Girardeau, MO | Pending | State |
| 2018-04-04 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2018-04-04 | NORRIS AGGREGATE PRODUCTS (PORT-0591) | PORTABLE, Undetermined, MO | Pass | State |
| 2018-03-31 | AMEREN MISSOURI - SIOUX ENERGY CENTER | WEST ALTON, St. Charles, MO | Pending | State |
| 2018-03-28 | POET BIOREFINING - LADDONIA | LADDONIA, Audrain, MO | Pending | State |
| 2018-03-28 | CARTHAGE WATER & ELECTRIC | CARTHAGE, Jasper, MO | Pass | State |
| 2018-03-28 | CARTHAGE WATER & ELECTRIC | CARTHAGE, Jasper, MO | Pass | State |
| 2018-03-28 | RIVER CEMENT CO. DBA BUZZI UNICEM USA SELMA PLANT | FESTUS, Jefferson, MO | Pending | State |
| 2018-03-27 | CARTHAGE WATER & ELECTRIC | CARTHAGE, Jasper, MO | Pass | State |
| 2018-03-27 | RIVER CEMENT CO. DBA BUZZI UNICEM USA SELMA PLANT | FESTUS, Jefferson, MO | Pending | State |
| 2018-03-27 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pending | State |
| 2018-03-27 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pending | State |
| 2018-03-26 | CARTHAGE WATER & ELECTRIC | CARTHAGE, Jasper, MO | Pass | State |
| 2018-03-22 | LITTLE BLUE VALLEY SEWER DISTRICT - ATHERTON WASTEWATER TREATMENT PLANT | INDEPENDENCE, Jackson, MO | Pending | State |
| 2018-03-21 | DOE RUN COMPANY-BUICK MINE & MILL | BOSS, Dent, MO | Pending | State |
| 2018-03-19 | DOE RUN CO-BUICK RESOURCE RECYCLING FCLT | BOSS, Dent, MO | Pending | State |
| 2018-03-16 | AUDUBON MATERIALS, LLC - SUGAR CREEK PLANT | SUGAR CREEK, Jackson, MO | Pending | State |
| 2018-03-14 | ADM - DEERFIELD | DEERFIELD, Vernon, MO | Pending | State |
| 2018-03-12 | PANHANDLE EASTERN PIPELINE CO - HOUSTONIA | LA MONTE, Pettis, MO | Pending | State |
| 2018-03-09 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-03-08 | SIKESTON POWER STATION | SIKESTON, Scott, MO | Pending | State |
| 2018-03-06 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pending | State |
| 2018-03-06 | LAMAR CITY ELECTRICAL GENERATION | LAMAR, Barton, MO | Pending | State |
| 2018-03-06 | GATEWAY ALUMINUM LLC | SAINT LOUIS, St. Louis (city), MO | Pending | State |
| 2018-03-01 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-03-01 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | N/A | State |
| 2018-03-01 | EVERGY-SIBLEY GENERATING STATION | SIBLEY, Jackson, MO | Pending | State |
| 2018-03-01 | EVERGY-SIBLEY GENERATING STATION | SIBLEY, Jackson, MO | Pending | State |
| 2018-02-28 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-28 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pending | State |
| 2018-02-28 | EVERGY-SIBLEY GENERATING STATION | SIBLEY, Jackson, MO | Pending | State |
| 2018-02-28 | EVERGY-SIBLEY GENERATING STATION | SIBLEY, Jackson, MO | Pending | State |
| 2018-02-28 | MISSISSIPPI LIME COMPANY | SAINTE GENEVIEVE, Ste. Genevieve, MO | Pending | State |
| 2018-02-28 | MISSISSIPPI LIME COMPANY | SAINTE GENEVIEVE, Ste. Genevieve, MO | Pending | State |
| 2018-02-27 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-23 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-23 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-23 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pass | State |
| 2018-02-23 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pending | State |
| 2018-02-22 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-22 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-02-21 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pass | State |
| 2018-02-21 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pass | State |
| 2018-02-20 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2018-02-20 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2018-02-19 | LAKE CITY ARMY AMMUNITION PLANT — high-priority violation on file | INDEPENDENCE, Jackson, MO | Pending | State |
| 2018-02-15 | CLARIOS, LLC | SAINT JOSEPH, Buchanan, MO | Pending | State |
| 2018-02-15 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2018-02-14 | CLARIOS, LLC | SAINT JOSEPH, Buchanan, MO | Pending | State |
| 2018-02-14 | CLARIOS, LLC | SAINT JOSEPH, Buchanan, MO | Pending | State |
| 2018-02-14 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2018-02-13 | CLARIOS, LLC | SAINT JOSEPH, Buchanan, MO | Pending | State |
| 2018-02-13 | CLARIOS, LLC | SAINT JOSEPH, Buchanan, MO | Pending | State |
| 2018-02-13 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2018-02-13 | GENERAL MOTORS LLC | WENTZVILLE, St. Charles, MO | Pending | State |
| 2018-02-13 | GENERAL MOTORS LLC | WENTZVILLE, St. Charles, MO | Pending | State |
| 2018-02-09 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2018-02-08 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2018-02-07 | DOE RUN CO-BUICK RESOURCE RECYCLING FCLT | BOSS, Dent, MO | Pending | State |
| 2018-02-07 | DOE RUN CO-BUICK RESOURCE RECYCLING FCLT | BOSS, Dent, MO | Pending | State |
| 2018-02-06 | G & M CONCRETE & ASPHALT CO., INC. | TROY, Lincoln, MO | Pass | State |
| 2018-02-06 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2018-01-31 | AUDUBON MATERIALS, LLC - SUGAR CREEK PLANT | SUGAR CREEK, Jackson, MO | Pending | State |
| 2018-01-25 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
| 2018-01-25 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2018-01-24 | AMEREN MISSOURI LABADIE ENERGY CENTER | LABADIE, Franklin, MO | Pending | State |
Dates as filed by the agency that recorded the stack test. Figures from EPA’s ICIS-AIR download.